MAIN SUPPLIES - vescovinigroup.it · MAIN SUPPLIES Period :2008-2013 Building Site : Train Station...
Transcript of MAIN SUPPLIES - vescovinigroup.it · MAIN SUPPLIES Period :2008-2013 Building Site : Train Station...
MAIN SUPPLIES
Period :2008-2013
Building Site : Train Station AV Bologna (Italy)
Customer/Steel Erectors : Costruzioni Metalliche Prefabbricate, Edimo, Cimolai, Cordioli, Cometal; Astaldi
Value of the project : 1.5Mio€
Period :2010-2011-2012
Building Site : High ways bridges (Italy)
Customer/Steel Erectors : Cimolai , Maeg
Value of the project : 350K €
Period :2010-2011
Building Site : High speed train station (ROME Italy)
Customer/Steel Erectors : Cimolai
Value of the project : 300K €
Period :2011-2012
Building Site : Football Stadium Refurbishment (Brasilia – Brasil )
Customer/Steel Erectors : Cimolai
Value of the project : 250K €
Period :2012
Building Site : High ways bridges (North Italy)
Customer/Steel Erectors : Cimolai, Castaldo
Value of the project : 250K €
Period :2012
Building Site : High ways bridges (Milan To North Italy)
Customer/Steel Erectors : Cordioli
Value of the project : 300K €
Period :2011-2012-2013
Building Site : Industrial & Commercial Building (IMI San Paolo Tower – Turin North Italy)
Customer/Steel Erectors : MBM, BIT , Cometal
Value of the project : 250K €
Period :2010-2011-2012
Building Site : Industrial & Commercial Building (Le Varesine Tower – Milan North Italy)
Customer/Steel Erectors : Sthalbau Pichler
Value of the project : 200K €
Period :2011-2012
Building Site : High ways bridges (Milan To North Italy)
Customer/Steel Erectors : Edimo – Taddei
Value of the project : 200K €
Period :2011
Building Site : Musik Arena (Baku – Azerbaijan)
Customer/Steel Erectors : Hasslinger
Value of the project : 200K €
Period :2013-2014 (on-going)
Building Site : Rail Ways line Algeria (250 Km)
Customer/Steel Erectors : Rizzani de Eccher – Societa' Italiana Per Condotte D'Acqua Spa
Value of the project : 8Mio €
Period :2014 (on-going)
Building Site : Industrial & Oil-Gas Building SINI –GAZPROM RUSSIA
Customer/Steel Erectors : LMV spa
Value of the project : 250 K €
Period :2014 (on-going)
Building Site : Road System – N. 5 Rail Ways Bridge (Lambro River ; MI)
Customer/Steel Erectors : CIMOLAI
Value of the project : 500 K €
Period :2014 (on-going)
Building Site : N. 11 Segment erection launcher (Metro Riad –Saudi Arabia)
Customer/Steel Erectors : DEAL –RDE / SPIC SPA
Value of the project : 200 K €
Period :2014 (on-going)
Building Site : Extensions Fiumicino -Airport
Customer/Steel Erectors : CIMOLAI Spa
Value of the project : 200 K €
Period :2014 (on-going)
Building Site : Expo Milano 2015 (PAVILLON : Italia; Japan ; China; Home theatre ; Fruit/Coffee ; Swiss ; Expo
Center, Belarus; UEA; USA; )- Footbridge
Customer/Steel Erectors : LMV spa ; MAP spa ; WOLF spa ; OCML spa ; PREMETAL spa ; STHALBAU P. spa;
MAEG Spa
Value of the project : 500 K €