Madrid, 27 October 2009
South Gas Regional InitiativeOpen Season France-Spain
Validation of the results
29th S GRI IG meeting – 27th October – Madrid
Test to validate capacity allocation
• As required at the 8th SG meeting of of 27th April in Paris, a test to validate capacity allocation in France has been published in the information memorandum for the open season 2013
• This test has been presented at the 9th Stakeholders meeting of 15th July in Madrid and some clarifications were brought
• No further comments were raised regarding this test
• The test is related to investment validation on the French side of the interconnection between Spain and France
39th S GRI IG meeting – 27th October – Madrid
Principles and priority of the test
• General principle: • If less than 50% of the marketed capacity is allocated, then the capacity
allocation will be considered as non valid and no capacity booking contracts will be signed
• If more than 90% of the marketed capacity is allocated, then the capacity allocation will be considered as valid and the relevant contracts will be signed
• If the capacity allocated lies between 50 and 90%, then the continuation on whether to continue the open season will be discussed
• Priority given to Larrau:1. Validation of Larrau
2. Then allocation up to the maximum capacity of Larrau
3. Remaining quantity taken into consideration to validate or not Biriatou
4. Validation of Biriatou
49th S GRI IG meeting – 27th October – Madrid
Figures of the test
Capacity Calculation of the figures
> 288 288 = 100% of Larrau (132+70) + 90% of Biriatou (48+48)
288 - 250 250 = 100% of Larrau + 50% of Biriatou
250 - 182 182 = 90% of Larrau
182 – 101 101 = 50% of Larrau
< 101
59th S GRI IG meeting – 27th October – Madrid
Result of the test
Capacity Result of the test
> 288 Larrau and Biriatou validated
288 - 250 Larrau validated and Biriatou discussed
250 - 182 Larrau validated but not Biriatou
182 – 101 Larrau discussed and Biriatou not validated
< 101 Nor Larrau neither Biriatou validated
• The demanded quantity amounts to 249 GWh/j
69th S GRI IG meeting – 27th October – Madrid
Application of the test
• According to the test:
Larrau is validated but not Biriatou
CRE proposes to validate the results of the open season accordingly, i.e. to allocate capacity at Larrau but not at Biriatou
79th S GRI IG meeting – 27th October – Madrid
Possible next steps
• CRE considers that the strong demand in the direction France to Spain has to be taken into account:
• It could be envisaged to re-offer the capacity at Irun/Biriatou during the binding phase of the open season 2015, together with the capacity of MidCat
• In this perspective, TSOs could realise some complementary studies, in order to adjust, if necessary, the physical investments needed, the investment costs and the date of availibility of capacity