DSD-INT 2015 - Monitoring Maasvlakte 2 impact - IR. William Borst
Maasvlakte CCS Project - ROAD · 2014. 3. 1. · Maasvlakte Power Plant 3 CO 2 Capture Plant...
Transcript of Maasvlakte CCS Project - ROAD · 2014. 3. 1. · Maasvlakte Power Plant 3 CO 2 Capture Plant...
Maasvlakte CCS Project - ROAD
European CCS Demonstration Project Network Meeting
Rotterdam, May 10, 2011
Hans Schoenmakers
Project Director ROAD
Page 2
Power Plant StorageTransportCapture Plant
Permit to modify existing plant
Consents from landowners
Exploration permit
Drilling permits
Building permit capture plant
Environmental Impact Assessment
Environmental Permits
Permit to construct and operate power plant
Environmental Permits
Water abstraction license
Assessment of pipeline routing
Pipeline Works Authorisation
Environmental Impact Assessment
Storage permit
Consents from land owners
Permits for a CCS project
Page 3
Organization
PermittingCommunication &
Public
Engagement
Regulatory
Framework
Funding
Agreements
Knowledge
Dissemination
CaptureTransport &
Storage
Stakeholder
ManagementProject Office
ROAD
Board
Primarily relevant for permits
Page 4
The Maasvlakte CCS Project - ROAD
CO2
Storage into depleted
gas reservoirs
Maasvlakte Power Plant 3
CO2Capture
PlantOnshoreTransport Pipeline
P18 –A Platform
OffshoreTransport
Subsea Pipeline
5 km 20 km3,5 km
Compression and Cooling dehydration, O2-removal,
Metering
Start of CCS scope
This flow diagram is not on scale
Metering
Page 5
Locations and pipeline trace's
Page 6
Five steps:
1. Completing the overview of procedures
Getting an overview of the formal procedures, the authorities and the first estimate scheduling of the procedures (permits, including conditions for an EIA and spatial planning)
2. Preparing the documents
Draft versions prepared by the companies, aligned with technology and equipment supplier and reviewed by the authorities, to make sure the documents meet all requirements
3. Formal procedures
Authorities, including the EIA committee, consider/handle all submitted requests and after public consultation decide on the permit conditions and updated spatial planning
4. Since this whole chain is the first of its kind, the EIA committee has advised a preliminary check
(“Voortoets”) on completeness and compliance with earlier directions. This informal stage takes
additional time (2 months) but is also supported by ROAD
5. Legal procedures
After permits have been granted, legal procedures can be expected. Court procedures may take a long time but - taking the preparations into account - there is no fear of losing the permit
How to obtain the necessary environmental permits for an
offshore CCS Project
Page 7
Applicants environmental permits
Coordinated by
Capture Transpor
tStorage
Maasvlakte CCS Project (ROAD)
Page 8
The scheduling of the project is determined by several technical and non-technical
conditions:
�Starting date CCS operational 2015, first on-site building activities mid 2012
�Building period expected to be 2,5 years
�Period for result form legal procedures not clear
�FID when risks and requirements are 80-90% clear (permit must be acquired, but
need not to be irrevocable yet)
�Spatial planning adjustments by the authorities
Scheduling leaves uncertainties:
�Getting permits as quick as possible
�Feedback of parties involved (direct stakeholders and public) is required
�Authorities take the safe route
Scheduling issues
Page 9
Keeping the pressure on all parties involved
� Maintaining a very tight time schedule to motivate authorities to take action and
make decisions
� Starting with first rough draft versions to get feedback
� The tight time schedule of the Grant Agreement can be used to motivate parties
involved
Showing that the project does everything within its power to reach the deadlines.
� Take the initiative in all meetings
� Supporting authorities with technical help to fulfill their obligations
� Keep everybody involved and do not take over responsibilities
� Accept authorities taking the safe route (accuracy more important than speed!)
Scheduling – lessons learned
Page 10
Technical information
� The FEED (basic engineering) for the project was completed in an early stage.
However, not all technical (detailed) information (on emissions) was available
� Because this is the first time a large scale CCS project is designed, there are few
standards available (pilots give some information but are not always trustworthy
for scale-up)
� This means that it is difficult to fill in permit applications early in the procedure
� It would be more pragmatic to get permits and being allowed to adjust later on,
within established limits
Design issues
Page 11
Supporting the authorities
� There is substantial knowledge on CCS and the rules with the initiator. Sharing
this information with authorities leads to mutual understanding and a combined
idea of the way forward. This may seem clear from the start, but a lessons
learned is that this still takes a lot of time and number of meeting to achieve
� Resources are often lacking with the authorities. The more the initiator prepares
the better the authorities will be able to fulfill their commitments
� Agree on getting the permits in more general terms, keeping open the
opportunity to adjust when detailed design information is available (not always
possible and makes permit more vulnerable)
Permits Lessons learned
Page 12
ROAD’s Regulatory context and the storage permit
Four levels of regulation (for sub-surface CO2-storage)
•E.U. – Directive (and Guidelines)
•National Act (Amendment of Mijnbouw wet) (”Enabler”)
•Ministerial Decree (“Hook”)
•Storage permit (“Tailor Made”)