MA DG Working Group Update Restructuring Roundtable October 26, 2012
description
Transcript of MA DG Working Group Update Restructuring Roundtable October 26, 2012
Fran Cummings – Peregrine Energy GroupTim Roughan – National Grid
MA DG Working Group UpdateRestructuring Roundtable
October 26, 2012
Source: DOER chart of data from Massachusetts utilities
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
2009 2010 Jan. 2010 -June 2011
July 2011 -Oct. 2011
Nov. 2011 -March 2012
kW/M
onth
Vol
ume
of A
pplic
ation
sAverage Monthly kW Volume of MA DG Applications
>3MW Projects
1-3 MW
501kW-1MW
<=500kW
Source: Monthly data from Massachusetts utilities
DPU 11-75 DG Working Group
• DPU orders 4-month WG process to improve interconnection process– Utilities and other stakeholders – over 20 entities– Facilitated/mediated process
• Reached consensus on package of report recommendations filed 9/14– Only one issue about minimum load screen for Expedited
process was not agreed to– Had DPU technical conference 10/24 and will submit
redlined tariff by 10/31• WG to meet monthly during implementation/transition year,
and form new Tech Standards WG
Findings: “necessary characteristics” of an efficient and effective interconnection process that will foster continued DG growth
RequirementsDG customers must know:
how long the steps in the process over which utility has control will take, &
what technical standards will be.
And those expectations must be reliably adhered to by utility.Utilities, to reliably adhere to those expectations, must be given sufficient time & resources to process all applications.Customers need to respond quickly to utility information needs to keep the process moving
StrategiesEnforce timelines on both utility & customer sides,
which cannot be done without tracking performance against timelines;
Include more transparent technical standards with non-utility parties process for inputHave specific ways to deal with projects that are not moving forward, but holding a space in the interconnection queue
7 Main Improvements to Interconnection ProcessImplementation of strategies1. Assurance – utilities: a multi-faceted utility timeline assurance and enforcement strategy2. Assurance – customers: a more clear-cut and definitive process for utilities to withdraw project applications when applicants miss deadlines
• freeing up feeders for other applicants
3. Additional time for “Complex” applications that will require more analysis – large projects requiring dedicated feeders or substations4. Utility-run tracking system to monitor both utility and customer timelines, with transparency for each customer, and enhanced monthly reporting
5. Standards Manual & Standards Review Group*: a uniform … Technical Standards Manual that is periodically updated with non-utility … input
Additional process changes6. Revisions to the technical screens
to allow more projects to qualify for the shorter tracks;
7. Pre-Application Report: required for applicants over 500 kW to help applicants prioritize among
locations and configurations & to reduce the number of
speculative applications.
Other Recommendations DGWG recommends that DPU name
a staff DG Ombudsperson with technical interconnection expertise & authority to: conduct independent interviews propose non-binding solutions offer decisions that can be appealed
through normal DPU process identify recurring issues in quarterly
reports participate ex officio in Review Group
Change existing monthly utility briefings into training with online modules may or may not include applicant
certification could be mandatory could address any future online
application process details to be worked out in transition
process
Fees for Expedited & Standard increase application fees from $3.00 to
$4.50/kW & increase maximum from $2,500 to $7,500
Continue no fee for Simplified Develop Group Studies process for
multiple DG on single feeder Consider allowing applicants to use
outside engineers during application & construction
Consider geographic mapping to show feeders & DG activity
Other • Changes Affecting the Simplified
Track* Spot and Area Networks* Increase Engineering Resources
Technical Standards Manual & Review Group– Membership of Review Group: 1 representative each from the 4
utilities & 3 non-utility representatives who are engineers with electric supply systems & DG interconnection expertise• Differences of opinion on standards will be recorded in
minutes• Meets semi-annually, plus meetings if requested
– Group will begin to meet in January 2013 & begin discussion of at least:1) DTT and anti-islanding,2) Limit of 3 MW/MVA on 13-15 kV feeders and related capacity
limits,3) RTUs,4) External disconnect switches for small generators,5) Interconnection practices in other states,6) Witness testing protocols
Changes Affecting the Simplified Track(generally for smaller projects)
Size Thresholds• Increase single phase maximum size from 10 kW to 15 kW
Leave three phase maximum size at 25 kWPeak Load Threshold (Screen #2)
• Increase threshold from 7.5% to 15% so screen will read: “Is the aggregate generating Facility capacity less than 15% of
feeder/circuit annual peak load and, if available, line segment?• Objective: allow more DG to stay in Simplified or Expedited Track
Timeline• Keep total utility review time at 15 days, but • Allow utilities 5 extra days for applications that fail Screen #5
(~must be all single-phase or all 3-phase) in order to keep those applications in the Simplified Track rather than moving them to the Expedited Track
Spot and Area Networks (mostly downtown areas)For “spot” networks, remove size screen (< 15 kW) for simplified process, if:
• the existing < 1/15 of Customer’s minimum load screen requirement is met
Extend the simplified network screen also to “area” networks, if:• DG capacity < 15 kW, as well as < 1/15 of Customer’s minimum load• applicant has interval meter data for appropriate period (i.e., for on-
site load)• minimum load data is available (i.e., for utility’s network)• other necessary screens are passed
Continue to monitor & track IEEE 1547 & national best practices, and incorporate IEEE guidance on networks into the new TSM Manual
• (While not stated in Report, similar discussions were held about IEEE guidance on microgrids.)
Continue to study & experiment on Massachusetts area networks (e.g., NSTAR’s current Boston pilot project)
Evolving DG-related Policy Landscape
If policy makers want to address rate impacts of increased DG, must also weigh societal benefits, esp. mkt price suppression & GHG
As concerns rise about intermittency, need to test & demonstrate potential of storage (VTG at 8pm) & local demand response to mitigate cost Impact of MA DG on MA Prices
$-
$10
$20
$30
$40
$50
$60
$70
PV Energy Efficiency CHP
Pric
e Ef
fect
(200
7 $
/ MW
h of
Dem
and
Res
ourc
e)
Price Effect: impact on annual average costs of Massachusetts purchases of wholesale electric energy in 2020 due to MA PV, EE and CHP (2007 dollars). Source: Synapse Energy Economics, Inc., “Impacts of Distributed Generation on Wholesale Electric Prices and Air Emissions in Massachusetts,” for Massachusetts Technology Collaborative, March 2008
• Benefits of DG to grid & power market & local customers (incl. reliability) are greater for DG on-site or near loads, but may require ride-thru & backup (gen &/or DR),
• Need hard look at utility ownership or other win-win business models to align DG benefits with costs
– need positive DG incentive for utility shareholders on top of decoupling
– core functionality of a green ‘smartgrid’ should be DG plug & play, reducing cost to DG to interconnect
Impacts & issues: Quantity of DG Reliable operation of electric distribution system Clarity needed from DPU on recovery of on-going costs to
operate the systemAnalysis of costs and rates for DG users and non-participantsNeed to maintain a transparent and fair allocation of these
costs Expansion of net-metering
3% private, 3% public caps When cap is reached - increase in costs to National Grid
distribution customers could reach $40-$60M/year 11-11C order of August 24th
Limits net-metering to 2 MWs per site and a single meter
Evolving DG-related Policy Landscape
Evolving DG-related Policy Landscape
Policies in MA & other states:Can we leverage energy efficiency with net metering & solar
incentives? CHP policiesGrid ModernizationNon-Transmission Alternatives & distribution planning
Location, location, locationThe MA utilities fully recognize the push for expanded
renewables with the clear policy decisions by the state legislature and executive branchNeed to balance this against workload demands in providing
service to all customersDG installations can not affect the reliability and safety of the
electric distribution system for their neighbors