M5 CostManagment v.2.0
Transcript of M5 CostManagment v.2.0
-
8/13/2019 M5 CostManagment v.2.0
1/37
3
www.eng.it
Maria Maddalena Ruggini, PMP
CC ERP Roma
Cost Management (M5)
Project Management and SAP
-
8/13/2019 M5 CostManagment v.2.0
2/37
3
www.eng.it
Cost Management
1. Introduction
2. Monitoring and control costs
3. Performance monitoring4. Earned Value Technique
-
8/13/2019 M5 CostManagment v.2.0
3/37
Introduction
3 M5_Cost Management www.eng.it
Once the project is started there are some more question for
the PM:
Wheredid you arrive with scheduling?
How much budget has been consumed?
How much work has been done?
-
8/13/2019 M5 CostManagment v.2.0
4/37
Introduction
4
Control is not intended for the mere detection of the actual
data.
Actual data, while important, does not allow itself to make a
critical judgment on the actual status of the project
Control means determining if things are going as planned and,
if not, take timely and appropriate actions.
There is no control without planning
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
5/37
Control Costs
Inputs
5
Project Management Plan and cost baseline;
Project funding requirements (billing plan) Work performance data: are the data on which
control is based - their accuracy influence the
assessments of project status and following
corrective actions. Deliverables completion, actual
data, estimate to complete, the percentage of completion;
Organization process assets:policies and procedures for cost
control, support tools, methods of monitoring and reporting (es.
SIAL)
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
6/37
Control Costs
Tools and techniques
6
Performance measurement analysis (Earned Value
Management or other techniques )
Forecasts: Forecasting includes making estimatesor predictions of conditions in the projects future based
on information and knowledge available at the time of
the forecast. Forecasts are generated, updated, and
reissued based on work performance information
provided as the project is executed and progressed.
Project Performance Reviews (status meeting):Performance reviews compare cost performance over time, schedule
activities or work packages overrunning and under running budget
(planned value), milestones due, and milestones met.
Reserve analysis: The cost management plan describes how costvariances will be managed, for example, having different responses to
major or minor problems.
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
7/37
Control Costs
Process
7
Choice of rulesof monitoring: monitoring interval and methods for monitoring
the progress (in the PM Plan);
Monitoring of progressin terms of time, cost and resources, with any newestimates for the activities in progress or to be started:
Consolidation (approval and input into the PM system) of actual
time, money and resources for the executed part of the project.
Monitoring the performance of the project through variance
analysisin terms of time, cost and performance of the entire project and itsparts;
Replanning(adjustments and realignments) in terms of time, cost and
resources;
Formalizationand logging of the situation of the project to date (consolidated
+ replanning ) with production of the progress report;
Possible redefinitionof the official Baseline (only in extreme cases).
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
8/37
Performance monitoring
8
Performance measurement techniques help to
assess the magnitude of any variancesthat will
invariably occur;
To determine the performance of a project, it is
essential to measure the actual
"physical progress" (how much work has been done);
It is good to keep the measure of the physical progress (earned value)
disjointfrom other types of feed: time, cost / income and resources;
A physical progress "inferred" in an indirect way by other
metrics (e.g.: dd actual / dd planned) would lead to considerable
errors in the assessment of the real progress of work and in the
determination of estimates to complete.
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
9/37
Performance monitoring
Techniques
9
ON/OFF (0/100): 0 at the beginning of the activity
100 at the end. Useful for short time activities or
low budget; 50/50 (or 20/80): 50 (20) when the activity starts
and 100 at the end. Useful for short time activities or
low budget;
Weighted events: important events are identified within the activity to
which it is given a weight, the achievement of an event determine theprogress of the activity. Applicable to activities in which the subparts
can be demonstrated;
Number of finished units: Applicable only to activities measured in
quantity;
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
10/37
Earned Value Technique
10
Earned value management (EVM), or Earned value
project/performance management (EVPM) is a
project management technique for measuringproject performance and progress in an
objective manner.
It has the ability to combine measurements of:
Scope
Schedule, and
Costs
In a single integrated system, Earned Value Management is able
to provide accurate forecasts of project performance problems,
which is an important contribution for project management.
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
11/37
Earned Value Technique
11
Earned value management (EVM), translates all the values into
a homogeneous unit (money in the defined currency
but even days in some contexts) and is basedon the comparison of three values:
Planned Value - PV (or BCWS - Budgeted Cost
of Work Scheduled): represents the planned budget (estimated
cost) at the date of measurement - is the Baseline value;
Actual Cost - AC (or ACWP - Actual Cost of Work Performed) is
the actual cost (posted) at the date;
Earned Value - EV (or BCWP - Budgeted Cost of Work
Performed): represents the budgeted value of the work actually
produced (deliverable) at the date of measurement.
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
12/37
Earned Value
12
The Earned Value represents the progress of the project (deliverable
or portion of deliverable produced);
EV provides guidance on project progress in termsof time and productivity;
EV is calculated by multiplying the Total
Planned Budget (BAC) for the percentage of physical progress: EV =
BAC * %physical completion at the date;
EV can be calculated at the level of activity, work package or entire
project;
EV allows to measure the actual variances between planned and
actual value, also highlighting the performance of the project;
EV is used to calculate forecasts (EAC);
EV is a great instruments to feed synthetic managerial "dashboards.
M5_Cost Management www.eng.it
-
8/13/2019 M5 CostManagment v.2.0
13/37
Earned Value
Example
13 M5_Cost Management www.eng.it
PLANNED =100ACTUAL =150
ACT. JAN FEB MAR APR MAY JUN TOTALBUDGET
A
B
C
D
150
150
200
100
PLANNED =150ACTUAL =120
PLANED =150ACTUAL =100
PLANNED =0ACTUAL =0
TIMENOW 30.04
Totalat
Timenow
Planned Cost (PV) = 400Actual Cost (AC) = 370
Variance: - 30 600
?
E d V l
-
8/13/2019 M5 CostManagment v.2.0
14/37
Earned Value
Example
14 M5_Cost Management www.eng.it
PLANNED =100 EARNED= 150ACTUAL =150
ACT. JAN FEB MAR APR MAY JUN TOTALBUDGET
A
B
C
D
150
150
200
100
PLANNED =150 EARNED=150ACTUAL =120
PLANNED =150 EARNED= 50
ACTUAL =100
PLANNED =0 EARNED= 0EARNED =0
TIMENOW100%
33%
75%
TIMENOW 30.04
Totalat
timenow
Planned Cost (PV) = 400Earned Value (EV) = 350
Actual Cost (AC) = 370
Schedule variance: -50Cost variance: -20
600
?
E d V l
-
8/13/2019 M5 CostManagment v.2.0
15/37
Earned Value
Deviations and efficiency ratios
15 M5_Cost Management www.eng.it
Cost Variance: CV = EV AC
Schedule Variance: SV = EV PV
Cost Performance Index: CPI = EV / AC
Schedule Performance Index: SPI = EV / PV
E d V l
-
8/13/2019 M5 CostManagment v.2.0
16/37
Earned Value
Deviations and efficiency ratios
16 M5_Cost Management www.eng.it
To-Complete Performance Index (TCPI) = (BAC-EV)
(BAC-AC) or (EAC-AC)
The TCPIformula gives the efficiency at which the project team should be utilized for the remainder of the project.
TCPI > 1 indicates utilization of the project team for the remainder of the project can be stringent.
TCPI < 1 indicates utilization of the project team for the remainder of the project should be lenient.
To-Complete Schedule Performance Index (TSPI) = (BAC-EV)
(BAC-PV)
TSPIgives the efficiency at which the project team should utilize the remaining time allocated for the project.
TSPI < 1 indicates project team can be lenientin utilizing the remaining time allocated to the project.
TSPI > 1 indicates project team needs to work harder in utilizing the remaining time allocated to the project
Earned Val e
-
8/13/2019 M5 CostManagment v.2.0
17/37
Earned Value
Example
17 M5_Cost Management www.eng.it
The actual cost at TimeNow is greater Earned Value: we are spendingmore than you would have had to spend on what has been achieved: we are
above budget
The planned value at TimeNow is greater than the Earned Value: The
value of what is actually achieved in terms of budget is less than what hadbeen planned, we are behind schedule
CV = 350 - 370 = - 20SV = 350 - 400 = - 50
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
18/37
Earned Value
Example
18 M5_Cost Management www.eng.it
The index of cost efficiency is less than 1: we are getting 94% of value forevery euro spent, we are inefficient with the costs;
The efficiency index of the schedule is less than 1: We are making 87% of
what was planned, we are inefficient with the schedule;
The efficiency to finish (TCPI) is > 1: the use of resources until the end of
the project must be stringent.
CPI = 350 / 370 = 0,94
SPI = 350 / 400 = 0,87
with BAC = 600
TCPI= 600-350/600-370= 1,1
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
19/37
Earned Value
Example
19 M5_Cost Management www.eng.it
Time
Costs
AC = 370
EV =350
TimenowCPI < 1
SPI < 1
SV
Delay
CV
DB=Delta
Budget
PV = 400
TotalBudget
TF
600
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
20/37
Earned Value
S Curves
20 M5_Cost Management www.eng.it
AC
EV
PV
SPI 1 Costs: positive
AC
EV
PV
SPI >1 Sched: positive
CPI >1 Costs: positive
AC
EV
PV
SPI >1 Sched: positiveCPI
-
8/13/2019 M5 CostManagment v.2.0
21/37
Earned Value
Application with WBS
21 M5_Cost Management www.eng.it
1.1.1 1.1.2 1.1.3
1.1
1.2.1 1.2.2 1.2.3 1.2.4
1.2
1.3.1 1.3.2
1.3
1
AV
EV
PV
Positive
AV
EVPV
Positive
Lets analyze this project
TOP-
DOWN
AC
EV
PV
Negativeon costsand sched
AC
EV
PV
Negativeon costs
and sched
Negative
On sched
AC
EV
PV Negative
On costs
AC
EV
PV
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
22/37
Earned Value
Estimate to complete
22 M5_Cost Management www.eng.it
Represents the estimated cost at the end of the project, taking into account
what is actually spent (sunk costs = AC) and how much further you have to
achieve;
Estimate At Completion (EAC) is the estimated cost of the project at the end of
the project.
There are three methods to calculate EAC
EAC = AC + ETC
Estimate At Completion (EAC):
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
23/37
Earned Value
Estimate to complete
23 M5_Cost Management www.eng.it
Variances are Atypical -This method is used when the
variances at the current stage are atypical and are not expected
to occur in the future;
Without taking into account the (in)efficiency at TimeNow
EAC = AC + (BAC EV)Compared to the example:
370+(600-350) = 620
Estimate At Completion (EAC):
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
24/37
Earned Value
Estimate to complete
24 M5_Cost Management www.eng.it
Variances are Typical -Variances will be present in the future
- This method is used when the assumption is that the current
variances will continue to be present in the future
Taking into account the (in)efficiency at TimeNow
EAC = AC + ((BAC EV)/CPI)Compared to the example:
370+((600-350)/0,94) = 636
Estimate At Completion (EAC):
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
25/37
Earned Value
Estimate to complete
25 M5_Cost Management www.eng.it
Time
SV
Costs
AC
EV
PVCV
Timenow
EAC 1(Total
Budget)
Delay
EAC 2
EAC 3
DBDB*CPI
Delay Delay
What is the estimate to complete more correct?
1
2
3
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
26/37
Earned Value
Estimate to complete
26 M5_Cost Management www.eng.it
What is the third method?
Estimate At Completion (EAC):
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
27/37
Estimate to complete
27 M5_Cost Management www.eng.it
Estimate To Complete (ETC)
Estimate To Complete (ETC) is the estimated cost required to
complete the remainder of the project.
Estimate To Complete (ETC) is calculated and applied when
the past estimating assumptions become invalid and aneed for fresh estimates arises.
ETC is used to compute the Estimation at Completion (EAC).
EAC = AC + ETC
Estimate At Completion (EAC):
Consolidation
-
8/13/2019 M5 CostManagment v.2.0
28/37
28 M5_Cost Management www.eng.it
Formalization of the data collected (time, costs, resources, ...) at TimeNow;
Loading data into the computer system of Project Management;
Historicization of work plan version at TimeNow (Versioning).
Schedule
Resources
Costs andPerformance
A
B
C
D
% Compl. Dur. Rim.
100%
40%
0
4 sett.
2,5 sett.
Timenow
4 sett.
Actual Start dates Actual end dates
0
0,5
1
1,5
2
2,5
3
3,5
1 sett 2 sett 3 sett 4 sett 5 sett 6 sett 7 sett 8 sett 9 sett 10 sett 11 sett 12 sett
Richiesta
Disponibilit
Effettivo
Costs
2 - AC
Time3 - EV
1 - PV
2
1
3
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
29/37
29 M5_Cost Management www.eng.it
Example
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
30/37
30 M5_Cost Management www.eng.it
a) Draw the Gantt (after defining the network of dependencies)You are a PM and you have this sequence of activities with its dependencies:
Activity 1 can start immediately and has an expected duration of 4 weeks
Activity 2 should end together with Activity 1, and has an estimated duration of 2 weeks
Activity 3 begins after Task 1 is finished and has an estimated duration of 6 weeks
Activity 4 starts two weeks after the Activity 2 is over and it has an expected duration of 8 weeks
Activity 5 begins after that activity 3 is over and ends together with Activity 4 and has a duration of 3 weeks
Activity 6 starts after the Activity 4 is over and it has a duration of 5 weeks
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
31/37
31 M5_Cost Management www.eng.it
a) Draw the Gantt (after defining the network of dependencies)You are a PM and you have this sequence of activities with its dependencies:
Activity 1 can start immediately and has an expected duration of 4 weeks
Activity 2 should end together with Activity 1, and has an estimated duration of 2 weeks
Activity 3 begins after Task 1 is finished and has an estimated duration of 6 weeks
Activity 4 starts two weeks after the Activity 2 is over and it has an expected duration of 8 weeks
Activity 5 begins after that activity 3 is over and ends together with Activity 4 and has a duration of 3 weeks
Activity 6 starts after the Activity 4 is over and it has a duration of 5 weeks
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1
2
3
4
5
6Start End1
3 5
4 62+ 2Ws
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
32/37
32 M5_Cost Management www.eng.it
b) Allocate costs
All activities use a mix of resources whose cost is equal to 1000per week.
The Activity 2 instead uses a mix of resources whose cost is equal to 3000per week. What is the trend of costs weekly and cumulative?
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1
2
3
4
5
6
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
33/37
33 M5_Cost Management www.eng.it
b) Allocate costs
All activities use a mix of resources whose cost is equal to 1000per week.
The Activity 2 instead uses a mix of resources whose cost is equal to 3000per week. What is the trend of costs weekly and cumulative?
1.000 1.000 4.000 4.000 1.000 1.000 2.000 2.000 2.000 2.000 1.000 2.000 2.000 2.000 1.000 1.000 1.000 1.000 1.000
1.000 2.000 6.000 10.000 11.000 12.000 14.000 16.000 18.000 20.000 21.000 23.000 25.000 27.000 28.000 29.000 30.000 31.000 32.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1
2
3
4
5
6
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
34/37
34 M5_Cost Management www.eng.it
c) Check the costs
We are at the end of the 10thweek.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1
2
3
4
5
6
1.000 1.000 4.000 4.000 1.000 1.000 2.000 2.000 2.000 2.000 1.000 2.000 2.000 2.000 1.000 1.000 1.000 1.000 1.000
1.000 2.000 6.000 10.000 11.000 12.000 14.000 16.000 18.000 20.000 21.000 23.000 25.000 27.000 28.000 29.000 30.000 31.000 32.000
PV=4000 PV=6000
PV=6000 PV=4000
AC=4000 AC=5000
AC=6000 AC=3000
100%
100%
60%
70%
PV = 20.000
AC = 18.000
now
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
35/37
35 M5_Cost Management www.eng.it
c) Check the costs
Get the Earned Value, the variances and indexes of the
project at the end of the tenth week.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1
2
3
4
5
6
1.000 1.000 4.000 4.000 1.000 1.000 2.000 2.000 2.000 2.000 1.000 2.000 2.000 2.000 1.000 1.000 1.000 1.000 1.000
1.000 2.000 6.000 10.000 11.000 12.000 14.000 16.000 18.000 20.000 21.000 23.000 25.000 27.000 28.000 29.000 30.000 31.000 32.000
PV=4000 PV=6000
PV=6000 PV=4000
AC=4000 AC=5000
AC=6000 AC=3000
100%
100%
60%
70%
EV =
CV =
SV =
CPI =
SPI =now
Earned Value
-
8/13/2019 M5 CostManagment v.2.0
36/37
36 M5_Cost Management www.eng.it
c) Check the costs
Get the Earned Value, the variances and indexes of the
project at the end of the tenth week.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1
2
3
4
5
6
1.000 1.000 4.000 4.000 1.000 1.000 2.000 2.000 2.000 2.000 1.000 2.000 2.000 2.000 1.000 1.000 1.000 1.000 1.000
1.000 2.000 6.000 10.000 11.000 12.000 14.000 16.000 18.000 20.000 21.000 23.000 25.000 27.000 28.000 29.000 30.000 31.000 32.000
PV=4000 PV=6000
PV=6000 PV=4000
AC=4000 AC=5000
AC=6000 AC=3000
100%
100%
60%
70%
now
EV = 19.200
CV = 1200
SV = - 800
CPI = 1,07
SPI = 0,96
AC
EV
PV
SPI 1 Costi: positivo
-
8/13/2019 M5 CostManagment v.2.0
37/37
37
Exercise
Earned valueDuration : 30 min
M5_Cost Management www.eng.it