M5 CostManagment v.2.0

download M5 CostManagment v.2.0

of 37

Transcript of M5 CostManagment v.2.0

  • 8/13/2019 M5 CostManagment v.2.0

    1/37

    3

    www.eng.it

    Maria Maddalena Ruggini, PMP

    CC ERP Roma

    Cost Management (M5)

    Project Management and SAP

  • 8/13/2019 M5 CostManagment v.2.0

    2/37

    3

    www.eng.it

    Cost Management

    1. Introduction

    2. Monitoring and control costs

    3. Performance monitoring4. Earned Value Technique

  • 8/13/2019 M5 CostManagment v.2.0

    3/37

    Introduction

    3 M5_Cost Management www.eng.it

    Once the project is started there are some more question for

    the PM:

    Wheredid you arrive with scheduling?

    How much budget has been consumed?

    How much work has been done?

  • 8/13/2019 M5 CostManagment v.2.0

    4/37

    Introduction

    4

    Control is not intended for the mere detection of the actual

    data.

    Actual data, while important, does not allow itself to make a

    critical judgment on the actual status of the project

    Control means determining if things are going as planned and,

    if not, take timely and appropriate actions.

    There is no control without planning

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    5/37

    Control Costs

    Inputs

    5

    Project Management Plan and cost baseline;

    Project funding requirements (billing plan) Work performance data: are the data on which

    control is based - their accuracy influence the

    assessments of project status and following

    corrective actions. Deliverables completion, actual

    data, estimate to complete, the percentage of completion;

    Organization process assets:policies and procedures for cost

    control, support tools, methods of monitoring and reporting (es.

    SIAL)

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    6/37

    Control Costs

    Tools and techniques

    6

    Performance measurement analysis (Earned Value

    Management or other techniques )

    Forecasts: Forecasting includes making estimatesor predictions of conditions in the projects future based

    on information and knowledge available at the time of

    the forecast. Forecasts are generated, updated, and

    reissued based on work performance information

    provided as the project is executed and progressed.

    Project Performance Reviews (status meeting):Performance reviews compare cost performance over time, schedule

    activities or work packages overrunning and under running budget

    (planned value), milestones due, and milestones met.

    Reserve analysis: The cost management plan describes how costvariances will be managed, for example, having different responses to

    major or minor problems.

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    7/37

    Control Costs

    Process

    7

    Choice of rulesof monitoring: monitoring interval and methods for monitoring

    the progress (in the PM Plan);

    Monitoring of progressin terms of time, cost and resources, with any newestimates for the activities in progress or to be started:

    Consolidation (approval and input into the PM system) of actual

    time, money and resources for the executed part of the project.

    Monitoring the performance of the project through variance

    analysisin terms of time, cost and performance of the entire project and itsparts;

    Replanning(adjustments and realignments) in terms of time, cost and

    resources;

    Formalizationand logging of the situation of the project to date (consolidated

    + replanning ) with production of the progress report;

    Possible redefinitionof the official Baseline (only in extreme cases).

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    8/37

    Performance monitoring

    8

    Performance measurement techniques help to

    assess the magnitude of any variancesthat will

    invariably occur;

    To determine the performance of a project, it is

    essential to measure the actual

    "physical progress" (how much work has been done);

    It is good to keep the measure of the physical progress (earned value)

    disjointfrom other types of feed: time, cost / income and resources;

    A physical progress "inferred" in an indirect way by other

    metrics (e.g.: dd actual / dd planned) would lead to considerable

    errors in the assessment of the real progress of work and in the

    determination of estimates to complete.

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    9/37

    Performance monitoring

    Techniques

    9

    ON/OFF (0/100): 0 at the beginning of the activity

    100 at the end. Useful for short time activities or

    low budget; 50/50 (or 20/80): 50 (20) when the activity starts

    and 100 at the end. Useful for short time activities or

    low budget;

    Weighted events: important events are identified within the activity to

    which it is given a weight, the achievement of an event determine theprogress of the activity. Applicable to activities in which the subparts

    can be demonstrated;

    Number of finished units: Applicable only to activities measured in

    quantity;

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    10/37

    Earned Value Technique

    10

    Earned value management (EVM), or Earned value

    project/performance management (EVPM) is a

    project management technique for measuringproject performance and progress in an

    objective manner.

    It has the ability to combine measurements of:

    Scope

    Schedule, and

    Costs

    In a single integrated system, Earned Value Management is able

    to provide accurate forecasts of project performance problems,

    which is an important contribution for project management.

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    11/37

    Earned Value Technique

    11

    Earned value management (EVM), translates all the values into

    a homogeneous unit (money in the defined currency

    but even days in some contexts) and is basedon the comparison of three values:

    Planned Value - PV (or BCWS - Budgeted Cost

    of Work Scheduled): represents the planned budget (estimated

    cost) at the date of measurement - is the Baseline value;

    Actual Cost - AC (or ACWP - Actual Cost of Work Performed) is

    the actual cost (posted) at the date;

    Earned Value - EV (or BCWP - Budgeted Cost of Work

    Performed): represents the budgeted value of the work actually

    produced (deliverable) at the date of measurement.

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    12/37

    Earned Value

    12

    The Earned Value represents the progress of the project (deliverable

    or portion of deliverable produced);

    EV provides guidance on project progress in termsof time and productivity;

    EV is calculated by multiplying the Total

    Planned Budget (BAC) for the percentage of physical progress: EV =

    BAC * %physical completion at the date;

    EV can be calculated at the level of activity, work package or entire

    project;

    EV allows to measure the actual variances between planned and

    actual value, also highlighting the performance of the project;

    EV is used to calculate forecasts (EAC);

    EV is a great instruments to feed synthetic managerial "dashboards.

    M5_Cost Management www.eng.it

  • 8/13/2019 M5 CostManagment v.2.0

    13/37

    Earned Value

    Example

    13 M5_Cost Management www.eng.it

    PLANNED =100ACTUAL =150

    ACT. JAN FEB MAR APR MAY JUN TOTALBUDGET

    A

    B

    C

    D

    150

    150

    200

    100

    PLANNED =150ACTUAL =120

    PLANED =150ACTUAL =100

    PLANNED =0ACTUAL =0

    TIMENOW 30.04

    Totalat

    Timenow

    Planned Cost (PV) = 400Actual Cost (AC) = 370

    Variance: - 30 600

    ?

    E d V l

  • 8/13/2019 M5 CostManagment v.2.0

    14/37

    Earned Value

    Example

    14 M5_Cost Management www.eng.it

    PLANNED =100 EARNED= 150ACTUAL =150

    ACT. JAN FEB MAR APR MAY JUN TOTALBUDGET

    A

    B

    C

    D

    150

    150

    200

    100

    PLANNED =150 EARNED=150ACTUAL =120

    PLANNED =150 EARNED= 50

    ACTUAL =100

    PLANNED =0 EARNED= 0EARNED =0

    TIMENOW100%

    33%

    75%

    TIMENOW 30.04

    Totalat

    timenow

    Planned Cost (PV) = 400Earned Value (EV) = 350

    Actual Cost (AC) = 370

    Schedule variance: -50Cost variance: -20

    600

    ?

    E d V l

  • 8/13/2019 M5 CostManagment v.2.0

    15/37

    Earned Value

    Deviations and efficiency ratios

    15 M5_Cost Management www.eng.it

    Cost Variance: CV = EV AC

    Schedule Variance: SV = EV PV

    Cost Performance Index: CPI = EV / AC

    Schedule Performance Index: SPI = EV / PV

    E d V l

  • 8/13/2019 M5 CostManagment v.2.0

    16/37

    Earned Value

    Deviations and efficiency ratios

    16 M5_Cost Management www.eng.it

    To-Complete Performance Index (TCPI) = (BAC-EV)

    (BAC-AC) or (EAC-AC)

    The TCPIformula gives the efficiency at which the project team should be utilized for the remainder of the project.

    TCPI > 1 indicates utilization of the project team for the remainder of the project can be stringent.

    TCPI < 1 indicates utilization of the project team for the remainder of the project should be lenient.

    To-Complete Schedule Performance Index (TSPI) = (BAC-EV)

    (BAC-PV)

    TSPIgives the efficiency at which the project team should utilize the remaining time allocated for the project.

    TSPI < 1 indicates project team can be lenientin utilizing the remaining time allocated to the project.

    TSPI > 1 indicates project team needs to work harder in utilizing the remaining time allocated to the project

    Earned Val e

  • 8/13/2019 M5 CostManagment v.2.0

    17/37

    Earned Value

    Example

    17 M5_Cost Management www.eng.it

    The actual cost at TimeNow is greater Earned Value: we are spendingmore than you would have had to spend on what has been achieved: we are

    above budget

    The planned value at TimeNow is greater than the Earned Value: The

    value of what is actually achieved in terms of budget is less than what hadbeen planned, we are behind schedule

    CV = 350 - 370 = - 20SV = 350 - 400 = - 50

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    18/37

    Earned Value

    Example

    18 M5_Cost Management www.eng.it

    The index of cost efficiency is less than 1: we are getting 94% of value forevery euro spent, we are inefficient with the costs;

    The efficiency index of the schedule is less than 1: We are making 87% of

    what was planned, we are inefficient with the schedule;

    The efficiency to finish (TCPI) is > 1: the use of resources until the end of

    the project must be stringent.

    CPI = 350 / 370 = 0,94

    SPI = 350 / 400 = 0,87

    with BAC = 600

    TCPI= 600-350/600-370= 1,1

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    19/37

    Earned Value

    Example

    19 M5_Cost Management www.eng.it

    Time

    Costs

    AC = 370

    EV =350

    TimenowCPI < 1

    SPI < 1

    SV

    Delay

    CV

    DB=Delta

    Budget

    PV = 400

    TotalBudget

    TF

    600

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    20/37

    Earned Value

    S Curves

    20 M5_Cost Management www.eng.it

    AC

    EV

    PV

    SPI 1 Costs: positive

    AC

    EV

    PV

    SPI >1 Sched: positive

    CPI >1 Costs: positive

    AC

    EV

    PV

    SPI >1 Sched: positiveCPI

  • 8/13/2019 M5 CostManagment v.2.0

    21/37

    Earned Value

    Application with WBS

    21 M5_Cost Management www.eng.it

    1.1.1 1.1.2 1.1.3

    1.1

    1.2.1 1.2.2 1.2.3 1.2.4

    1.2

    1.3.1 1.3.2

    1.3

    1

    AV

    EV

    PV

    Positive

    AV

    EVPV

    Positive

    Lets analyze this project

    TOP-

    DOWN

    AC

    EV

    PV

    Negativeon costsand sched

    AC

    EV

    PV

    Negativeon costs

    and sched

    Negative

    On sched

    AC

    EV

    PV Negative

    On costs

    AC

    EV

    PV

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    22/37

    Earned Value

    Estimate to complete

    22 M5_Cost Management www.eng.it

    Represents the estimated cost at the end of the project, taking into account

    what is actually spent (sunk costs = AC) and how much further you have to

    achieve;

    Estimate At Completion (EAC) is the estimated cost of the project at the end of

    the project.

    There are three methods to calculate EAC

    EAC = AC + ETC

    Estimate At Completion (EAC):

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    23/37

    Earned Value

    Estimate to complete

    23 M5_Cost Management www.eng.it

    Variances are Atypical -This method is used when the

    variances at the current stage are atypical and are not expected

    to occur in the future;

    Without taking into account the (in)efficiency at TimeNow

    EAC = AC + (BAC EV)Compared to the example:

    370+(600-350) = 620

    Estimate At Completion (EAC):

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    24/37

    Earned Value

    Estimate to complete

    24 M5_Cost Management www.eng.it

    Variances are Typical -Variances will be present in the future

    - This method is used when the assumption is that the current

    variances will continue to be present in the future

    Taking into account the (in)efficiency at TimeNow

    EAC = AC + ((BAC EV)/CPI)Compared to the example:

    370+((600-350)/0,94) = 636

    Estimate At Completion (EAC):

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    25/37

    Earned Value

    Estimate to complete

    25 M5_Cost Management www.eng.it

    Time

    SV

    Costs

    AC

    EV

    PVCV

    Timenow

    EAC 1(Total

    Budget)

    Delay

    EAC 2

    EAC 3

    DBDB*CPI

    Delay Delay

    What is the estimate to complete more correct?

    1

    2

    3

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    26/37

    Earned Value

    Estimate to complete

    26 M5_Cost Management www.eng.it

    What is the third method?

    Estimate At Completion (EAC):

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    27/37

    Estimate to complete

    27 M5_Cost Management www.eng.it

    Estimate To Complete (ETC)

    Estimate To Complete (ETC) is the estimated cost required to

    complete the remainder of the project.

    Estimate To Complete (ETC) is calculated and applied when

    the past estimating assumptions become invalid and aneed for fresh estimates arises.

    ETC is used to compute the Estimation at Completion (EAC).

    EAC = AC + ETC

    Estimate At Completion (EAC):

    Consolidation

  • 8/13/2019 M5 CostManagment v.2.0

    28/37

    28 M5_Cost Management www.eng.it

    Formalization of the data collected (time, costs, resources, ...) at TimeNow;

    Loading data into the computer system of Project Management;

    Historicization of work plan version at TimeNow (Versioning).

    Schedule

    Resources

    Costs andPerformance

    A

    B

    C

    D

    % Compl. Dur. Rim.

    100%

    40%

    0

    4 sett.

    2,5 sett.

    Timenow

    4 sett.

    Actual Start dates Actual end dates

    0

    0,5

    1

    1,5

    2

    2,5

    3

    3,5

    1 sett 2 sett 3 sett 4 sett 5 sett 6 sett 7 sett 8 sett 9 sett 10 sett 11 sett 12 sett

    Richiesta

    Disponibilit

    Effettivo

    Costs

    2 - AC

    Time3 - EV

    1 - PV

    2

    1

    3

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    29/37

    29 M5_Cost Management www.eng.it

    Example

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    30/37

    30 M5_Cost Management www.eng.it

    a) Draw the Gantt (after defining the network of dependencies)You are a PM and you have this sequence of activities with its dependencies:

    Activity 1 can start immediately and has an expected duration of 4 weeks

    Activity 2 should end together with Activity 1, and has an estimated duration of 2 weeks

    Activity 3 begins after Task 1 is finished and has an estimated duration of 6 weeks

    Activity 4 starts two weeks after the Activity 2 is over and it has an expected duration of 8 weeks

    Activity 5 begins after that activity 3 is over and ends together with Activity 4 and has a duration of 3 weeks

    Activity 6 starts after the Activity 4 is over and it has a duration of 5 weeks

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    31/37

    31 M5_Cost Management www.eng.it

    a) Draw the Gantt (after defining the network of dependencies)You are a PM and you have this sequence of activities with its dependencies:

    Activity 1 can start immediately and has an expected duration of 4 weeks

    Activity 2 should end together with Activity 1, and has an estimated duration of 2 weeks

    Activity 3 begins after Task 1 is finished and has an estimated duration of 6 weeks

    Activity 4 starts two weeks after the Activity 2 is over and it has an expected duration of 8 weeks

    Activity 5 begins after that activity 3 is over and ends together with Activity 4 and has a duration of 3 weeks

    Activity 6 starts after the Activity 4 is over and it has a duration of 5 weeks

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

    1

    2

    3

    4

    5

    6Start End1

    3 5

    4 62+ 2Ws

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    32/37

    32 M5_Cost Management www.eng.it

    b) Allocate costs

    All activities use a mix of resources whose cost is equal to 1000per week.

    The Activity 2 instead uses a mix of resources whose cost is equal to 3000per week. What is the trend of costs weekly and cumulative?

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

    1

    2

    3

    4

    5

    6

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    33/37

    33 M5_Cost Management www.eng.it

    b) Allocate costs

    All activities use a mix of resources whose cost is equal to 1000per week.

    The Activity 2 instead uses a mix of resources whose cost is equal to 3000per week. What is the trend of costs weekly and cumulative?

    1.000 1.000 4.000 4.000 1.000 1.000 2.000 2.000 2.000 2.000 1.000 2.000 2.000 2.000 1.000 1.000 1.000 1.000 1.000

    1.000 2.000 6.000 10.000 11.000 12.000 14.000 16.000 18.000 20.000 21.000 23.000 25.000 27.000 28.000 29.000 30.000 31.000 32.000

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

    1

    2

    3

    4

    5

    6

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    34/37

    34 M5_Cost Management www.eng.it

    c) Check the costs

    We are at the end of the 10thweek.

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

    1

    2

    3

    4

    5

    6

    1.000 1.000 4.000 4.000 1.000 1.000 2.000 2.000 2.000 2.000 1.000 2.000 2.000 2.000 1.000 1.000 1.000 1.000 1.000

    1.000 2.000 6.000 10.000 11.000 12.000 14.000 16.000 18.000 20.000 21.000 23.000 25.000 27.000 28.000 29.000 30.000 31.000 32.000

    PV=4000 PV=6000

    PV=6000 PV=4000

    AC=4000 AC=5000

    AC=6000 AC=3000

    100%

    100%

    60%

    70%

    PV = 20.000

    AC = 18.000

    now

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    35/37

    35 M5_Cost Management www.eng.it

    c) Check the costs

    Get the Earned Value, the variances and indexes of the

    project at the end of the tenth week.

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

    1

    2

    3

    4

    5

    6

    1.000 1.000 4.000 4.000 1.000 1.000 2.000 2.000 2.000 2.000 1.000 2.000 2.000 2.000 1.000 1.000 1.000 1.000 1.000

    1.000 2.000 6.000 10.000 11.000 12.000 14.000 16.000 18.000 20.000 21.000 23.000 25.000 27.000 28.000 29.000 30.000 31.000 32.000

    PV=4000 PV=6000

    PV=6000 PV=4000

    AC=4000 AC=5000

    AC=6000 AC=3000

    100%

    100%

    60%

    70%

    EV =

    CV =

    SV =

    CPI =

    SPI =now

    Earned Value

  • 8/13/2019 M5 CostManagment v.2.0

    36/37

    36 M5_Cost Management www.eng.it

    c) Check the costs

    Get the Earned Value, the variances and indexes of the

    project at the end of the tenth week.

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

    1

    2

    3

    4

    5

    6

    1.000 1.000 4.000 4.000 1.000 1.000 2.000 2.000 2.000 2.000 1.000 2.000 2.000 2.000 1.000 1.000 1.000 1.000 1.000

    1.000 2.000 6.000 10.000 11.000 12.000 14.000 16.000 18.000 20.000 21.000 23.000 25.000 27.000 28.000 29.000 30.000 31.000 32.000

    PV=4000 PV=6000

    PV=6000 PV=4000

    AC=4000 AC=5000

    AC=6000 AC=3000

    100%

    100%

    60%

    70%

    now

    EV = 19.200

    CV = 1200

    SV = - 800

    CPI = 1,07

    SPI = 0,96

    AC

    EV

    PV

    SPI 1 Costi: positivo

  • 8/13/2019 M5 CostManagment v.2.0

    37/37

    37

    Exercise

    Earned valueDuration : 30 min

    M5_Cost Management www.eng.it