m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
-
Upload
katie-sanders -
Category
Documents
-
view
224 -
download
0
Transcript of m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
1/67
KIGALI INSTITUTE OF SCIENCE AND TECHNOLOGY
INSTITUT DES SCIENCES ET DE TECHNOLOGIE DE KIGALIAvenue de l'Arme, B.P. 3900 Kigali, Rwanda
FACULTY OF ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING AND ENVIRONMENTAL TECHNOLOGY
A PROJECT REPORT
ON
DESIGN OF FLYOVER SUSPENDED PEDESTRIAN BRIDGE IN KIGALI
CITY
Submitted by
RYOBA VUZIMPUNDU Eugne(REG.NO: GS20031702)Under the Guidance of
Mr. NGARAMBE Andr
Submitted in partial fulfilment of the requirements for the award of
BACHELOR OF SCIENCE DEGREE IN
CIVIL ENGINEERING AND ENVIRONMENTAL TECHNOLOGY
FEBRUARY 2008
PROJECTID:CEET/07/3
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
2/67
Final year project
i
DECLARATION
I, RYOBA VUZIMPUNDU EUGENE declare that this project work is my own work
and has not been represented any were else, either Universities or any other Institutions
of high learning, for academic or any other purposes.
Signature ..
RYOBA Vuzimpundu Eugne
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
3/67
Final year project
ii
DEDICATION
To my GOD, my family; my beloved parents, brothers and sisters, I dedicate this book;it is the fruit of your love and encouragement. I dedicate also this book to all survivors
of genocide of 1994 and NDAHAYO JULES who passed away in last year; we always
remember you.
You all, I love you.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
4/67
Final year project
iii
ACKNOWLEDGEMENTS
It was a deep sense of gratitude that I address my acknowledgements to my parent,
brother and sisters I am grateful to them, for having continuously supported me during
my studies till at present and tough me the value of life.
I am wholeheartedly indebted to my classmates, my friends, whose love, advices,
motivation and encouragement made me who I am now, and without whom this project
would ever have seen light of the day, this is the impatiently awaited fruit of their
endeavors.
I would like to express my heat-felt gratitude to KIST authorities, whose financial
supports and extraordinary effort made this project possible.
I thank my project guidance, Mr. Andre NGARAMBE, whose inspiring guidance and
innovative question have made this project a pleasurable learning and working
experience.
Many thanks whomever his assistance and advice, helped me to successfully complete
my project.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
5/67
Final year project
iv
ABSTRACT
The purpose of this bridge was to make the conception, the analysis and design of
flyover suspended pedestrian bridge in Kigali City. The following study was
completed with three phases. The first phase involved a deep investigation for the
bridge in which enough and relevant information were gathered from different area in
Kigali City.
Investigation did not only cover the site conditions, but also the availability of the local
materials as well as produced by the industries of our country of was used in second
phase of the project; this phase involved mainly the conception or the architectural
design of the bridge. At the end of the second phase, a steel structure was generated and
then in the last phase, subjected to the detailed structural analysis so as to obtain the
forces within the different component of the bridge. These former were used, in turn to
design the different component of the structure. In design, most of standards
specification and practice codes used were prepared.
Finally, detailed plans and drawing were prepared. The achievements of this study
reveal the possibility of improving condition of the mixed traffic by separating
pedestrians and vehicles.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
6/67
Final year project
v
TABLE OF CONTENTS
DECLARATION ............................................................................................................... i
DEDICATION ................................................................................................................. ii
ACKNOWLEDGEMENTS ............................................................................................ iiiABSTRACT .................................................................................................................... iv
TABLE OF CONTENTS ................................................................................................. v
LIST OF FIGURES AND PHOTOS .............................................................................. vii1. FIGURES ............................................................................................................... vii
2. PHOTOS ................................................................................................................ viiiLIST OF TABLES .......................................................................................................... ix
LIST OF SYMBOLS, ABBREVIATIONS AND NOMENCLATURE .......................... x
CHAPTER 0.INTRODUCTION ...................................................................................... 10.1 GENERAL INTRODUCTION .............................................................................. 1
0.2 JUSTIFICATION OF THE PROJECT .................................................................. 2
0.3 GENERAL OBJECTIVES AND AIMS OF THE PROJECT ............................... 30.3.1 GENERAL OBJECTIVES .............................................................................. 30.3.2 AIM OF THE PROJECT ................................................................................. 4
0.4 SCOPE OF THE STUDY ...................................................................................... 4
0.5 SITE INVESTIGATION ........................................................................................ 60.6 PROBLEM FACED ............................................................................................... 6
0.7 TRAFFIC VOLUME STUDY ............................................................................... 8
0.8 DATA COLLECTION FROM TRAFFIC POLICE .............................................. 90.8.1 CAUSE OF ACCIDENTS INYEAR 2005-2006 .......................................... 10
0.8.2 HOUR ACCIDENT SURVEY IN YEAR 2005 AND 2006 ......................... 11
CHAP I. LITERATURE REVIEW .............................................................................. 12
1.1 INTRODUCTION TO SUSPENSION BRIDGES .............................................. 121.2 DESCRIPTION .................................................................................................... 12
1.3 THEORY ON SUSPENSION BRIDGE .............................................................. 14
1.4 TYPES OF SUSPENSION BRIDGES ................................................................ 15CHAP II. MATERIALS FOR CONSTRUCTING OF THE ......................................... 16
PROPOSED PROJECT .................................................................................................. 16
2.1 INTRODUCTION ON COMMONLY USED MATERIALS ............................. 162.2 TYPES OF SUSPENSION BRIDGE CABLES .................................................. 17
2.2.1 CABLE STRUCTURES ............................................................................... 17
2.2.2 TYPES OF WIRE CABLES ......................................................................... 182.3 REINFORCED CONCRETE MATERIAL ......................................................... 20
2.3.1 GENERAL INTRODUCTION ..................................................................... 202.3.2 CEMENT ....................................................................................................... 20
2.3.3 AGGREGATE ............................................................................................... 222.4 STRUCTURE OF WOOD ................................................................................... 23
2.4.1 GENERAL INTRODUCTION ..................................................................... 23
2.4.2 CLASSIFICATION OF TREES ................................................................... 232.5 COLUMNS ........................................................................................................... 23
2.5.1 INTRODUCTION ON COLUMNS .............................................................. 23
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
7/67
Final year project
vi
2.4.2 CLASSIFICATION OF COLUMNS ............................................................ 24
2.6 FOUNDATION .................................................................................................... 242.6.1 GENERAL INTRODUCTION ...................................................................... 24
2.6.2 FOUNDATIONS AND THE EARTH .......................................................... 25
2.6.3 TYPES OF FOUNDATION .......................................................................... 25
2.7 BEARING CAPACITY OF SOIL ........................................................................ 262.8 LOADING ............................................................................................................ 26
2.8.1 DEAD LOADS .............................................................................................. 27
2.8.2 IMPOSED LOADS ........................................................................................ 272.8.3 DESIGN STRESS .......................................................................................... 27
CHAP III METHODOLOGY ......................................................................................... 28
CHAP IV DESIGN OF FLYOVER SUSPENDED PEDESTRIAN BRDGE ............... 294.1 DESIGN INFORMATION ................................................................................... 30
4.2 DESIGN THEORY ............................................................................................... 30
4.3 DESIGN OF MAIN CABLE DIAMETER .......................................................... 324.4 DESIGN OF TRUE LENGTH OF MAIN CABLES ........................................... 34
4.5 DESIGN OF TRANSVERSAL AND LONGITUDINAL BEAMS .................... 354.5.1 DESIGN OF TRANSVERSAL ..................................................................... 35
4.5.2 DESIGN LONGITUDINAL BEAMS ........................................................... 374.6 DESIGN OF SUSPENDERS CABLE DIAMETER ............................................ 39
4.7 DESIGN OF TOWERS ........................................................................................ 40
4.8 DESIGN OF FOUNDATION............................................................................... 414.9 DESIGN OF COLUMN BASE ............................................................................ 43
4.10 DESIGN OF STAIRS LONGITIDUNALY BEAMS ........................................ 45
4.11 DESIGN OF LATERAL BEAMS OF STAIRS ................................................. 474.12 DESIGN OF SUPPORT COLUMN OF STAIRS .............................................. 48
4.13 DESIGN OF FOUNDATION FOR COLUMNS OF STAIRS .......................... 494.14 DESIGN OF ANCHORAGE BLOCKS ............................................................. 50
4.15 DESIGN CONNECTIONS WITH BOLTS........................................................ 51
V. CONCLUSION AND RECOMMENDATION ......................................................... 525.1 CONCLUSION ..................................................................................................... 52
5.2 RECOMMENDATION ........................................................................................ 52
REFERENCES ............................................................................................................... 53
APPENDICES ................................................................................................................ 54
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
8/67
Final year project
vii
LIST OF FIGURES AND PHOTOS
1. FIGURES
Figure 1: Parts of suspended bridgep13
Figure2: 1. Galvanized Bridge Wire...p17
Figure3: Parallel Wire Cable...p18
Figure 4: Detail of Main Cable and Cable Band.p18
Figure 5: Close-up view of Main Cable..p19
Figure 6: Cable with Clipp19
Figure 7: bridge span, loading and flesh.p31
Figure 8.1: load diagram.p33
Figure 8.2: loading diagram in lateral direction.p33
Figure 8.3: result of diagram cable.p35
Figure 9: transversal beam..p35
Figure 10: load, shear, moment...p36
Figure 11: load, shear and moment.....p38
Figure 12: suspender cable diameter...p39
Figure 13: load column....p40
Figure 14: column and beam dimension.p41
Figure 15: foundation..p42
Figure 16: Reinforcement in foundation.p43
Figure 17: bars in foundation..p43
Figure 18: base column ..p44
Figure 19: fixation and connection of base column.....p45
Figure 20: stair span.............................................................................p46
Figure 21: load, shear and moment..p48Figure 22: columnp49
Figure 23: anchor and fixation of cable...p50
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
9/67
Final year project
viii
2. PHOTOS
Photo1: Mixture crossing of road of pedestrians and vehiclesp 11
Photo 2: big number of pedestriansp11
Photo 3: scope of the study..p14
Photo 4: big number of vehicles at the site of the study..p14
Photo 5: inattention of policemen, pedestrians, and driversp16
Photo 6: time west for crossing loadp16
Photo 7: Big volume of pedestrians crossing the Round about...p18
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
10/67
Final year project
ix
LIST OF TABLES
Table 1: traffic volume survey; Round about Kigali city, Nyarugengep17
Table 2: percentage of death, injured and accident in Kigali city...p18
Table 3: causes of accidents in Kigali city..p 19
Table 4: Daily hour accidentp19
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
11/67
Final year project
x
LIST OF SYMBOLS, ABBREVIATIONS AND NOMENCLATURE
A cross sectional area
B beam width, foundation base
bf width of pad of foundation
cm centimeter
C span, width
FCV vertical component of force
FCH horizontal component of force
D diameter, depth
DW horizontal distance
DT vertical inclined distance
d effective depth
F axial Force
E modulus of elasticity
y deflection
fk characteristic of compressive strength of masonry
fck concrete characteristic strength
fyk reinforcement characteristic strength
g gram
I moment of inertia of area
k kilo
L length, length of span
l true length
LE effective length
M bending moment
Max maximum
Min minimum
m2 meter square
mm2
millimeter square
N Newton
Pc compressive strength of beam
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
12/67
Final year project
xi
q Ground pressure under foundation
R reaction at the end
r radius of gyration
S plastic modulus
t beam web thickness
T tension
UDL uniformly distributed load
V shear force
v design shear stress
W magnitude of uniformly distributed load
w uniformly distributed load
WA weight of anchor block
angle
Stress
y yield stress
pi
Elongation
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
13/67
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
14/67
Final year project
1
CHAPTER 0.INTRODUCTION
DESIGN OF ECONOMIC FLYOVER SUSPENDED PEDESTRIAN BRIDGE
IN KIGALI CITY
0.1 GENERAL INTRODUCTION
The Kigali City, the now days facing traffic problems mainly due to the increase in the
number of vehicles, The increase is directly related to the parallel increase in population
number and based also on the vision plan of the Kigali City.
The traffic problems include traffic jams, which normally result in delays and
increase in load cost, accident which result in damage to vehicles as well as loss of
human lives.
It may be observed that most of accidents involving pedestrians occurs while
they crossing road of heavy vehicles, inattention or/and high speed traffic. Mean while,
quite number of solution has been worked out and implemented at different location of
interest within the City of Kigali; among this we can mention here, the use of traffic
policemen, traffic lights, speed ramps, zebra crossing and road signs. Some of these,
such as traffic lights (signals) and policemen or manual control and other measures
control and other previous performed ineffectively if not failed.
Therefore, based on the previous stated solution, my challenge in the prevent
project was to find out a new and better solution why not be best, using the modern
trend and technologies. The solution would be the permitting the smooth, safe, secure,
and smart passage of vehicles and pedestrians. While studying this problem of crossing
the roads, I thought the possible and effective solution would aim at separating the two
traffic component mean pedestrians and vehicles.
This implies directly prevision for a pedestrian path under above the road way.
However, further observation of how roads are constructed in Kigali City dictate thesolution of an economic flyover pedestrian bridge as the adequate solution.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
15/67
Final year project
2
Photo1: Mixture crossing of road of pedestrians and vehicles in Kigali road.
0.2 JUSTIFICATION OF THE PROJECT
As here above mentioned, there is a problem of crossing roads certain particular places
in KIGALI CITY, where the traffic is heavy. There is proved or supported by findings
from accidents study made by traffic police office. The survey conducted by this office
shows the increase of big number of accident along with an increase in number of
vehicles. The cause of different accidents varies from an accident to another. Some are
due to the high speed of vehicles, bad driving, other to the violation of road codes,
either intentionally or not, on other hand, some of road users such as children, present
difficulties in crossing roads of heavy traffic.
However, the services in change took measures so in order to overcome this
problem. Different methods as mentioned in the introduction of this project are now
used but they are suffering from certain handicap, and sometimes create auxiliary
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
16/67
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
17/67
Final year project
4
0.3.2 AIM OF THE PROJECT
The main aim of the project can be follows:
Making conception, analysis, as well as design of an economic flyoversuspended pedestrian bridge in KIGALI CITY constructed by local materialsuch as metallic profiles, steel and wood etc.
0.4 SCOPE OF THE STUDY
The suitable site was selected based on the traffic volume mean for pedestrian and
vehicles where there is a big number of pedestrians crossing the roads, also the second
criteria was to find out the most difficult place to within Kigalis districts as well as
Nyarugenge, Kicuciro and Gasabo district.
Gitega (EPA)
Kanogo at TOTAL (ex-SOPETRAD) Payage (on boulevard de lOUA Kiyovu) Kimihurura (primarly school) Sainte famille church (round about) Round about (town center RUBANGURA) Remera Giporoso
The third criteria concerned the category of pedestrians facing problem such as children
going and coming from school, adult people going or coming from church and also
based on the accidents records from the traffic police office.
Gitega (EPA) Sainte famille (near round about town center) Kimihurura (primarily school) Round about (town center RUBANGURA in front of Ex-Nyira-Rock )
Finely, ROUND ABOUT town center (RUBANGURA) in front of near Nyira-Rock
was selected as the site thats the characteristics mentioned above.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
18/67
Final year project
5
Photo 3: scope of the
study
Photo 4: big number of vehicles at the site of the study
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
19/67
Final year project
6
0.5 SITE INVESTIGATION
Before a pedestrian bridge can be built at a particular site, it is essential to consider
many factors, such as the need for a pedestrian bridge, the present and future traffic,stream characteristics, subsoil condition, aesthetics and cost. For the design of this
pedestrian bridge, the highest vehicles are considered so the height of 3.5m of the
pedestrian bridge has been chosen.
0.6 PROBLEM FACED
The big number of pedestrians crossing Kigali roads where zebra crossings arenot efficient enough to guarantee security of pedestrians.
The time people use waiting for priority to cross roads. The time drivers use waiting for priority to go. Tasks for pedestrians and for drivers in the roads during the crossing roads of
pedestrians.
Traffic jams in Kigali roads Inefficiency of the zebra crossing while peak period. Inattentions of pedestrians and drivers.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
20/67
Final year project
7
Photo 5: inattention of policemen, pedestrians, and drivers
Photo 6: time west for crossing road
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
21/67
Final year project
8
0.7 TRAFFIC VOLUME STUDY
The traffic volume study was conducted with the aim of determining the number of
vehicles as well as pedestrians crossing the section of the road where the bridge is
proposed to be built, per unit time within peak traffic periods
The traffic volume counts were done manually and here below are tabulated result.
All bellow survey are counted in the period of 3 days of week mean that a number is a
mean value of 3 days of week, Monday, Wednesday, and Friday.
Table 1: traffic volume survey; Round about Kigali city, Nyarugene
Peak
period
Peak
hour
Number of
pedestrians/minute
Number of
vehicles/minute
Total number
of
pedest./hour
Total number
of vehic/hour
Morning 7h00-
8h00
59 36 3540 2160
Noon 12h30-
13h30
48 23 2880 1380
Evening 16h30-
17h30
63 42 3780 2520
MEAN TOTAL
VALUE
57 34 3400 2020
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
22/67
Final year project
9
Photo 7: Big volume of pedestrians crossing the Round about Kigali city
0.8 DATA COLLECTION FROM TRAFFIC POLICE
This is the percentage of death, injured, and accidents in the period of 2 years.
Table 2: percentage of death, injured and accident in Kigali city
Death Injured AccidentYear 2005, Jan-Dec 33,2% 66,7% 70,1%
Year 2006, Jan-Dec 27,5% 57,1% 67,1%
Source: Traffic police
Those are the accident happened in KIGALI CITY.
Year 2005: From the total number of accident which was happen in all country the
70, 1%; 33% dead; and 66, 7% injured in Kigali City only.
Year 2007: the total number of accident is 67, 1%; 27, 5% death, and 57, 1 injured.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
23/67
Final year project
10
0.8.1 CAUSE OF ACCIDENTS INYEAR 2005-2006
Table 3: causes of accidents in Kigali city
Causes 2005 2006 %of 2006 % of 2005
Signalisation
03 08 0,23 0,065
Other 205 1373,89
4,5
High speed 573 40711,6
12,58
Inattention 2552 186452,9
56,01
State of road 43 501,42
0,94
Bad driving 871 74721,2
19,12
Alcholism 110 1243,52
2,41
Rain 11 120,34
0,24
Mecanical errors 187 1744,94
4,1
Total 4556 3523
Source: Traffic police
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
24/67
Final year project
11
0.8.2 HOUR ACCIDENT SURVEY IN YEAR 2005 AND 2006
Table 4: Daily hour accident
Hourly Year 2005 % Year 2006 %
06h00-08h00 -
08h00-09h00 230 6,5% 230 6,5%
09h00-10h00 - - 230 6,5%
10h00-11h00 - - 226 6,4%
14h00-15h00 319 7% - -
15h00-16h00 331 7,2% - -
16h00-17h00 331 7,2% - -17h00-18h00 370 8,1% 244 6,9%
18h00-19h00 338 7,4% 243 6,9%
19h00-20h00 230 6,5%
Source: National
police
As it seems from table the percentage of accident in one hour is the counted
from the total number of accident happened in one day in hourly
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
25/67
Final year project
12
CHAP I. LITERATURE REVIEW
1.1 INTRODUCTION TO SUSPENSION BRIDGES
This booklet was put together to familiarize the general reader with the terminology of
suspension bridge components and to help the designer, builder or user of a small
suspension bridge. Its use should enable him to make up preliminary calculations for
determining the cable size as well as the various quantities of material required. Then, a
comparative estimate can be made between the suspension bridge and any other type
that may also be under consideration for a particular location.
It is rather interesting to note that, in spite of the relative simplicity of design and
erection of a suspension bridge, there are a number of cases where other types have
been used, even though the suspension type might have been more economical. We
think that this is because many engineers have been of the opinion that the cable
analysis might be difficult and complicated as to its solution. However, the simple
formulae used in the catalog should dispel this thought.
True to their name, suspension bridges suspend the roadway from huge main cables,
which extend from one end of the bridge to the other. These cables rest on top of high
towers and are secured at each end by anchorages. The towers enable the main cables to
be draped over long distances.
1.2 DESCRIPTION
Suspension bridges have two basic systems-main cables supported by towers at each
end over the obstacle and a roadway suspended from the main cables. Suspender cables
support the floor beams, which support the stringers that support the roadway.
Stiffening trusses further spread the live load to the suspenders. Suspension-bridge
design requires analysis of the following items:
Load to be carried. Panel length. Floor beams and stringers.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
26/67
Final year project
13
Stiffening trusses. Dead load. Suspenders. Main cables or suspension cables. Towers. Tower bracing and backstays. Anchorages or deadman.
Figure 1: Parts of suspended bridge
Source: hp: // www.google.com
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
27/67
Final year project
14
1.3 THEORY ON SUSPENSION BRIDGE
A suspension bridge is composed of a deck that is attached to or suspended from cables.
Just like the name states, the suspended bridge literally suspends the roadbed from huge
cables, which extend form one end of the bridge to the other. The cables are attached totwo tall towers and are secured at each end by anchorages. The tower allows the cables
to be draped over very long distances. The cable carries the weight on a suspended
bridge to the anchorages that are imbedded in solid rock or massive concrete blocks.
The cables are spread over a large area in order to evenly distribute the load inside the
anchorages to prevent the cables from breaking free.
In the suspension bridge each cable supporting a segment of the roadbed is vertically
suspended from the primary draped cable spanning between main pylon towers. The
forces from permanent and moving loads push down onto the roadbed placing it in
compression. The cables through tension then transfer the forces to the towers, which
carries the forces, through compression, directly into the earth where they are firmly
imbedded. The tension cables running between the two anchorages support the forces.
The cables stretch from the weight of the bridge and the traffic that travels from anchor
to anchor. In addition to the cables, the anchorages are also under the forces of tension.
Because they are firmly imbedded into the earth like the towers, the amount of tensionexerted on them is resisted by the counter forces of the dead load. Most suspension
bridges also have a supporting truss system underneath the bridge deck to help stiffen
the roadbed and to provide a lateral stabilization of the roadbed. This extra support
system resists wind and lateral forces and reduces the tendency of the roadbed to ripple
and sway.
Suspension bridges come in two different types of designs; the elongated "M" shape and
the "A" shaped design called a cable-stayed bridge. The two designs support the load of
the roadbed in very different ways. The differences lie in the way the cables are
connected to the towers. The cable-stayed bridge attaches all cables that support the
roadbed to the tower and they alone carry the weight of the roadbed and the traffic. The
series of cables are attached to the roadbed in two basic ways, using a running parallel
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
28/67
Final year project
15
pattern or a radial pattern. In the parallel pattern, the cables are parallel to one another
and attached at different heights along the tower. Each cable carries a segment of the
roadbed. In the radial pattern, each cable carries its section of the roadbed and they are
attached to the tower at a single point. In the cable stay bridge, all segments of the
roadbed must carry a horizontal compressive force to counter balance the equal force
from the other side.
1.4 TYPES OF SUSPENSION BRIDGES
Unstiffened bridges
Unstiffened bridges consist of floors, without stiffening trusses or girders, suspended
from cables. These bridges are suitable only where live load or wind load can never
cause serious deformation of the cable. An example of this type of bridge would be a
footbridge, where the live load is very light. Other examples are structures with a large
dead load but insignificant live load.
Stiffened bridges
Stiffened bridges have flexible cables that are stiffened by suspended girders or trusses.
These bridges minimize local changes in roadway slope due to live loads. They are
constructed by framing the floor beams of the floor system into stiffening trusses and
supporting these trusses with hangers running to the cables.
Self-anchored bridges
Self-anchored bridges are supported on vertical foundations, and no anchor cable is
required. The horizontal force on the main cable is exerted by endwise thrusts in the
stiffening girder.
Multiple-span bridges
Multiple-span bridges are a combination of two or more adjoining suspension bridges
sharing a common anchorage. The towers of these bridges are connected by a tie cable
to restrain movement of the tower tops from unbalanced live loads.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
29/67
Final year project
16
CHAP II. MATERIALS FOR CONSTRUCTING OF THE
PROPOSED PROJECT
2.1 INTRODUCTION ON COMMONLY USED MATERIALS
Steel, Concrete, Aluminum alloy, Timber, Masonry and Fiber composite Materials fall
in three categories:
- Natural material such as stone and timber have been used for centuries asbuilding material, and their properties are well understood by craftsmen for use
in small-scale building. However, because they are natural materials, they are of
variable quality and often contain significant defects. This means that, for use in
large scale engineered structures, they need to be carefully selected andsubjected to large material safety factors to ensure safety.
- Manufactured materials such us steel and aluminum alloy are produced undercarefully controlled factory conditions, with frequent testing and monitoring
throughout the manufacturing process. This obliviously produces a more
predictable and consistent material which is reflected in lower material safety
factors being required. Concrete lies somewhere between these two being
manufactured from naturals with little intermediate processing.
- New materials such as fiber reinforced composites. They are highlymanufactured materials, but unlike steel, have not been in existence long enough
to be fully understood.
Factors affecting the selection of structural materialsThis chapter briefly describes the commonly used material. We then go on to examine
the various factors that must be considered when selecting a material for the building of
safe and durable structures. Those factors are: strength and stiffness, durability, fatigue,
brittle fracture, creep, fire resistance, weight, economics environmental factors. This is
firstly done by considering the properties of steel, which is one of the most commonly,
used materials.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
30/67
Final year project
17
2.2 TYPES OF SUSPENSION BRIDGE CABLES
2.2.1 CABLE STRUCTURES
Cable structures can be exciting, lightweight and highly efficient. It is usual to use
cables made from a very high grade steel. This produces large concentrations of
load, and hence particular care must be taken with the design and manufacture of
end connections if catastrophic failure is to be avoided. A key feature of all design
involving cables is that they are assumed to support only tensile loads.
Figure2: 1. Galvanized Bridge Wire for Parallel Wire
Bridge Cables.
2. Galvanized Bridge Strand--consists of
several bridge wires, of various diameters
twisted together.
3. Galvanized Bridge Rope--consists of six
strands twisted around a strand core.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
31/67
Final year project
18
2.2.2 TYPES OF WIRE CABLES
1. Parallel Wire Cables--This type of cable is made up of a large number of individual
wires which are parallel to one another. Neither the cables nor the wires are twisted in
any manner. The wire i6 shipped to the site of the bridge on reels and the individual
wires are installed or' "spun" on the bridge and later compacted together to form a round
cross section. Cables of this type are used on monumental structures, such as the Golden
Gate Bridge and the George Washington Bridge.
Figure3: Parallel Wire Cable
2. Parallel Strand Cables, Closed Construction--These consist of several
prefabricated Galvanized Bridge Strands, all laid parallel and in contact with one
another. Wood or aluminum fillers are used to bring the cable to a circular cross-
section, after which the whole cable is wrapped with wire for protection. The cable may
contain 7, 19 37, 61, 91 or 127 strands.
Figure 4: Detail of Main Cable and Cable Band The wrapping
wire is omitted at the right for clarity. Note the
closed construction and aluminum fillers.
3. Parallel Strand Cables, Open Construction--This type of cable consists of several
prefabricated Galvanized bridge Strands which are all laid parallel to one another and
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
32/67
Final year project
19
not in contact. The strands are usually arranged in the form of a rectangle and the cable
may contain 2, 4, 6, 9, 12, 16, 20, 24 or 30 strands.
4. Parallel Rope Cables, Open Construction--These are the same as Parallel Strand
Cables except that Galvanized Bridge Rope is used in place of Bridge Strand.
Figure 5: Close-up view of Main Cable, Cable Bend
and Suspender Note the open construction.
5. Single Rope or Single Strand Cables--These are used for small structures.
Figure 6: Cable with Clip Type Cable Band and
Suspender
For many years the main cables of most suspension bridges, large and small, consisted
of parallel wires installed individually at the site of the bridge. On small bridges thisproved to be an expensive procedure and consequently placed the suspension type
bridge at an economic disadvantage for the shorter span crossings.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
33/67
Final year project
20
2.3 REINFORCED CONCRETE MATERIAL
2.3.1 GENERAL INTRODUCTION
Concrete is the most commonly used building material. It has being formed into any
desired shape most conveniently. It is an artificial stone obtained by mixing aggregates,
cement and water, and allowing the product to cure for hardening. Its essential
ingredients are cement and water, which react with each other chemically, to form
another material having useful strength. The strength of concrete depends upon the
quality of its ingredient, their relative quantity and the manner in which they are mixed,
compacted and cured. It is possible to produce concrete of different specifications for
various purposes by suitably adjusting the proposition of cement aggregate and water.
Reinforced concrete is a composite material made of concrete and steel. Plain
concrete possesses high compressive strength but little tensile strength. Reinforcing
steel possesses high compressive strength both in tension and compression. In
reinforced concrete, steel provides the strength and the concrete provides the
compressive strength. So, by combining these features and the concrete and steel, it
attains high utility and versatility.
2.3.2 CEMENT
Cement is produced burning together, in a definite proportion; a mixture of siliceous
(containing silica) argillaceous (containing alumina) and calcareous (containing lime)
materials in particular fusion, at a temperature of 1400 to 1450oC.by doing so, a
material called clinker is obtained. It is cooled and then ground to the required fineness
to get cement. Different types of cement are obtained by varying the proposition of theraw materials and also by adding small percentage of other chemicals.
Chemical composition of cement
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
34/67
Final year project
21
The main raw materials for manufacturing cement are lime, silica, alumina and iron
oxide. Depending upon the wide variety of raw materials used in the manufacture of
cement, its oxide components vary widely.
Types of cement
A wide variety of cement is available which are suitable for use under certain condition
due to its special properties. They are,
1. Ordinary Portland cement
2. Rapid hardening Portland cement
3. Extra rapid hardening cement
4. Low heat Portland cement
5. Sulphate-resisting Portland cement
6. Supersulphate cement
7. Portland blast furnace cement
8. Pozzolanic cement etc
Physical properties of cement
Following are important physical properties of cement.
1. Chemical composition loss of ignition insoluble residues lime and alumina content magnesia content and sulphur content
2. Fineness3. Formal consistency4. Setting time
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
35/67
Final year project
22
5. Soundness6. Heat of hydration and Strength of cement.
2.3.3 AGGREGATE
A mixture only of water and cement is costly and possesses low strength and shrinks
unacceptably on drying. In order to reduce the cost and modify such properties as the
strength and drying shrinkage of the hardened mass, it is usual to introduce insoluble
non-cementitious particles described as aggregates. Such aggregates usually constitute
between 50 and 80% of the volume of conventional concrete and may thus greatly
influence its properties.
Aggregates should not contain any constituent which affect the hardening of the
cement and durability of the hardened concrete adversely. It should be free from organic
matter which reduces the hydraulic activity of cement and affects its normal setting and
hardening. It should also be free from constituents whom decompose or change
significantly in volume on exposure to atmosphere or react adversely cement paste.
Physical properties of aggregates
Following are the physical properties of aggregates
1. Size of aggregates2. Shape of particles3. Surface texture4. Strength of coarse aggregates5. Specific gravity6. Bulk density7. Water absorption and surface moisture8. Bulking of sand9. Deleterious substance
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
36/67
Final year project
23
10.Soundness and Durability.
2.4 STRUCTURE OF WOOD
2.4.1 GENERAL INTRODUCTION
To utilize any structural materials to optimum effect it is necessary to understand its
composition and structures since these can have a major influence on a materials
properties. For timber this necessitates knowledge of the nature and growth patterns of
trees, since the composition and the structures of wood derive from the requirements of
the growing tree rather than the appreciation of the variations which occur between and
within species, it should then be possible to specify timber correctly for any
performance requirements.
2.4.2 CLASSIFICATION OF TREES
All commercial timber can be classified into two board groups:
Softwoods and Hardwoods When first used in the Middle Ages these terms would have
been indicate of the relative hardness, density or ease of working of the types of timber
in common use, possibly comparing native oak with imported spruce for example
(Ridout, 1992). Nowadays, however, the terms hardwood and softwood are quite
misleading: balsa is a hardwood but is softer and less dense than any soft wood, while
pitch, pine is softwood which is harder and denser than many hardwoods.
2.5 COLUMNS
2.5.1 INTRODUCTION ON COLUMNS
Columns are structural elements used primarily to support compressive loads. They are
usually square, rectangular, circular, L-shaped or octagonal in cross section.
Column subjected to pure axial load are concentrically loaded column. Such columns
rarely occur in practice. Generally they are subjected to moment along with axial load.
If the moment acts about one axis only, they are classified as uneasily eccentrically
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
37/67
Final year project
24
loaded columns. If the moments act about both axes, they are classified as biaxial
loaded columns.
2.4.2 CLASSIFICATION OF COLUMNS
Classifications of column due to its construction material are:
They are Metallic column, reinforced concrete column and brick column.
Columns are also classified as pedestal, short, and slender column depending upon its
effective length and lateral dimension. The effective length of column is the length
between the points of inflection of the column. Very short column with effective length
lesser than three times least lateral dimension are called pedestal columns. Column of
intermediate length with effective length lesser than or equal to12 times least lateral
dimension are called short columns. Columns of large length with effective length
greater than 12 times the least lateral dimension are called long or slender columns.
2.6 FOUNDATION
2.6.1 GENERAL INTRODUCTION
All structures on earth consist of superstructure and substructure. The foundation can be
defined as the substructure which interfaces the superstructure and the supporting
ground. Its purposes are to transfer all loads from the superstructure to the ground safely
and provide stable base to the superstructure. It distributes the loads over a larger area
so that pressure on the soil does not exceed its allowable capacity, the total settlement is
limited to permissible value and differential settlement is minimum possible.
These are different types of foundation for transfer of loads from superstructureto the ground. They depend primarily on the type and magnitude of the loads and the
bearing capacity of the soil. Their behavior and design are described in this chapter.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
38/67
Final year project
25
2.6.2 FOUNDATIONS AND THE EARTH
Foundations are the structures that connect the main structure with the ground. Forces
do not end at the ends of a bridge. They do not even end at the boundaries of the
foundations. In theory, they spread throughout the earth, getting weaker as the distanceincreases, though at some point they are so weak that they cannot be detected.
Foundations must be made wide enough to reduce the stresses to values that the ground
beyond can sustain indefinitely. The size and strength of foundations will depend on the
quality of the ground. Over bridge and the famous Pisa campanile are examples where
the combination of foundations and ground were less than ideal. The foundations may
be deep underground, and in some cases under water as well, requiring the use of
pneumatic caissons with sharp cutting edges, and pressurized air keep the water out.
Eads' Mississippi Bridge and the Roeblings' Brooklyn Bridge are early examples of the
use of caissons.
If the weight of earth removed for foundations is greater than the weight of the structure
supported, the foundations on average cannot settle, because the structure is floating.
Nevertheless, a building might still tilt in these conditions, while not sinking overall.
This principle of apostasy applies approximately to huge mountain ranges, whose roots
go deep below the mean surface level of the earth. If glacier ice melts in large
quantities, the rock below will start to rise, and in fact parts of the earth's surface are
still moving slowly, and have been moving, since the end of the last ice age.
It is in dam construction that knowledge of the ground is most important, because of the
potential for great loss of life. The dam must be integrated into the rock to avoid
leakage and uplift; extensive grouting is often required. Just as important is the huge
weight of the water in the reservoir, and its effect on the rocks below and around. A
terrible catastrophe resulted when water behind the Vajont dam penetrated the ground
and enabled a large piece of a mountain slope to slide into the reservoir.
2.6.3 TYPES OF FOUNDATION
Foundations are classified as shallow and deep foundations. These are described as
follows:
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
39/67
Final year project
26
1. Shallow foundationit has a smaller depth limited to the width of footing. It spreads
The load from superstructure on a larger area of the soil so that stress intensity is
reduced to a value which can be carried safely by soil they are classified as isolated
and combined footing.
2.Deep foundation when the top layer of soil is too weak to support the structure on a
Shallow foundation, the depth of foundation is increased till more suitable soil is
found to support the structure. Such a foundation is termed as deep foundation
because of its large depth. Different types of deep foundation are pile foundation and
well foundation
2.7 BEARING CAPACITY OF SOIL
Bearing capacity of soil is the maximum intensity of load or pressure developed under
the foundation without causing failure of soil and damaging settlement of superstructure
supported on foundation. Therefore allowable bearing capacity is evaluated with an
adequate factor of safety against ultimate bearing capacity of soil and adequate margin
against excessive settlement. The ultimate capacity of soil corresponds to load beyond
which settlement increases rapidly.
Soil pressure at footing bases
Actual soil pressure at the base of the infinitely stiff footing resting on ideal cohesion
less and cohesive subsoil under a concentric load generally footings are not infinitely
stiff and very few soils exhibit such behavior.
2.8 LOADING
Analysis of begins with the evaluation of the structures own weight and the loads to be
supported, such loads are variable both in magnitude and some in position. In general,
there are two types of loads which are dead and imposed loads.
Another type of load frequently encountered in building is wind load which is the
impact of the local wind on the structure. The wind speed is converted to force and the
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
40/67
Final year project
27
effect on the structure is analyzed. This is common with tall structures such as tall
buildings and bridges. Wind loads can also be combined with both dead and imposed
loads.
2.8.1 DEAD LOADS
The dead loads are the weight of the structure its self, and the structural element such
as ceiling, I beam, floor board, cladding, cables and permanent partitions, where panels
and other equipments are permanently located they can be assumed as dead loads.
2.8.2 IMPOSED LOADS
These are loads to be carried by the structures and because of their nature are more
different to be determined precisely. For many of them, it is only possible to make
conservative estimates based on standard codes of practice or past experience.
e.g.: imposed load for bridges: pedestrians, panels, vehicles, etc.
For houses: its occupants, furniture, and presence of wind
2.8.3 DESIGN STRESS
This study is mostly concerned with two materials namely concrete and reinforcements.
The steel used is round bars of high yield steel or high tensile bars. Concrete
characteristics strength fck = 30KN/mm3. This value of fck is also minimum cube
strength at 28 days. All Characteristics strength are given in DIN codes and British
Standards; for mild steel rand bars, fyk=250N/mm2 while for high yield steel,
fyk=420N/mm2.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
41/67
Final year project
28
CHAP III METHODOLOGY
These data collection methods have been used to collect needed data:
Observation:This method has been used to enable traffic study and collect some preliminary data at
the selected site which would help in making conception, analysis as well as design of
an economic flyover suspended pedestrian bridge and Providing detailed plans and
drawings of final structure.
Literature Survey :Internets and books have been used in order to get secondary data need for designing
and getting the required calculations and formulas.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
42/67
Final year project
29
CHAP IV DESIGN OF FLYOVER SUSPENDED PEDESTRIAN
BRDGE
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
43/67
Final year project
30
4.1 DESIGN INFORMATION
Properties of various materials to be used in design
Concrete strength at 28 days 25 kN /m3 and fck, cyl=20 N/mm2,fck, cube= 30N/mm
Timber 8 6 kN/m3 Steel rolled or cast 74 kN/m3
Unit weight of various sheet materials
Timber boards 0.15 kN/m2 Steel sheeting 0.15 kN/m2 Live load 5 kN/m2 Stair live 5 kN/m2 Imposed load 3 kN/m2 Allowable compression stress of column 210 kN/mm2 Allowable stress for cables 240 N/mm2 allowable shear stress for I beam 210 N/mm2 The assumed soil bearing capacity in Nyarugenge is 200 kN/m2 = 0.02
kN/cm2.
4.2 DESIGN THEORY
The cable has a uniform weight and may also be subjected to a uniformly distributed
load. The tension is assumed to be sufficiently great to that the sag f is not large. Since
the curve is reasonably flat, the weight of the cable may be replaced, with the practical
error by a uniform loading w, then
- y = wc2/8TSince the curve is flat, the true length of cable is
- L =c+Where from the following formulas:
- = 8y2/3c
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
44/67
Final year project
31
Figure 7: bridge span, UDL and flesh
Where, l is the true length of the cable- y is deflection- w is load (kN/m)- C is span- T is tension force- is elongation
In order to find the maximum force in cable that is better to have the horizontal
component and vertical component.
Horizontal component
RCH
= wL/8y and the vertical component
RCV = wL/2
Cable will exert the maximum stress. The maximum stress is obtained by the force per
unit area which is equal to the allowable stress. The max force
F max= {(wL/2)2+ (wL
2/8y)}
1/ 2
And we know that the maximum stress = Max force/Area
Or, Area = max force/max stress
Where area A is the cross section of one suspended cable
A = D2/4
D is diameter of cable
= 3.14
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
45/67
Final year project
32
4.3 DESIGN OF MAIN CABLE DIAMETER
Surface area of the moving space area 1.5m of width and lengthlof 15.2m
Design parameters
Floor surface area = 1.5*15.2= 21,28m2
Deflection y=1.4m
Number of main cable = 2 cables
Working cable stress = 240 N/mm2
Live load = 5 kN/ m2
Timber boards = 0.15 kN/m2
Imposed load = 3 kN/m2
Design load
Dead load = ((live load + timber board)*l)
Where l is the of opposite distance of center to center of the span l = 1.4 /2 = 0.7 m
Cis the span
Dead load = ((5 + 0.15)*0.75) = 3.862 kN/m
Balustrade =1.0 kN/m
Imposed load = 3 kN*0.7 = 2.1 kN/m
Total load = 3.862+1.0 = 4.862 kN/m
Then design load = (4.862*1.4) + (2.1*1.6) = 10.17 kN/m
W= 10.17 kN/m per cable span
Figure 8.1: load diagram
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
46/67
Final year project
33
Design of main cable diameter
Reaction of horizontal componentRCH=wC2/8f
RCH = 10.17*15.22/8*1.4 = 209.726 kN
Reaction of vertical componentRCV = wL/2
RCV= 10.17*15.2/2 = 77.292 kN
Thus the maximum force = (RCV2+RCH
2)
1/2
Fmax = (209.7262+77.292
2)
1/2= 223.515 kN
Area = max force/max stress
A = 223.515*103/240 = 931.31 mm
2
Then the diameter of main cable is equal to (931.31*4/3.14)1/2
= 34.44 mm
Take the cable diameter of 3.5 cm for each main cable.
Figure 8.2: result of diagram cable
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
47/67
Final year project
34
4.4 DESIGN OF TRUE LENGTH OF MAIN CABLES
Calculation of true length
- y = wL2/8TSince the curve is flat, the true length of cable is
- l = L+Where from the following formulas
- = 8y2/3LWhere, lthe true length of the cable- y is deflection- W is load ( kN/m)- L is span- elongation- l is true length
Then, = 8*1.42/3*15.2 = 0.344 m
Thusl=15.2 + 0.344 = 15.544 m
The true length lof cable between the towers is 15.544m
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
48/67
Final year project
35
4.5 DESIGN OF TRANSVERSAL AND LONGITUDINAL BEAMS
4.5.1 DESIGN OF TRANSVERSAL
Beam B1Beam support to carry lateral load which are resisted by bending and shear. However,
deflections and local stresses are also important. Beam may be cantilever, simply
supported, fixed ended or continuous. In this work we are going to use simply supported
beam and is uniformly distributed load.
Figure 9: transversal beam
Design loadLive load = 5 kN/m
2
Timber structure = 0.15 kN/m2
Imposed load = 3 kN/m2
Dead load: 5+0.15 = 5.15 kN/m2
Then, total load is 5.15*0.77 = 3.965 kN/m
Where 0.77m is equal to the half of lateral distance of walkway
Imposed load = 3 kN/m2*0.77 = 2.31 kN/m
Design load = (3.965*1.4) + (2.31*1.6) = 9.247 kN/m
Max moment = wL2/8
Deflection = 5wL3/384EI
w: is the design load
L: is the considered length
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
49/67
Final year project
36
I: is the moment of inertia and
E: is the elasticity modulus
Evaluation of beam reaction, shear force and bending moment
Two end ReactionRA andRB = wL/2
= 9.247*1.7/2 = 7.86 kN
The resulting diagrams are shown in figure below. Beam B1 is standard case i.e. a
simply supported beam with uniformly distributed load.
M max = wL2/8
=9.247*1.72/8 = 3.34 kNm
Figure 10: load, shear, momentdiagram
Let use a typical yield stress of yis 210 N/mm2(St 25) DIN 18800 German standard
From equation required S = M max/y
= 3.34*106/210*10
3= 15.905 cm
3
Where S is plastic modulus
UDL, Reaction and moment diagram for beam B1
Use I 80 DIN 1025which have cross section area of 7.57 cm2
Average shear stress = 7.86*103/7.57*10
2= 10.515 N/mm
2< 139N/mm
2
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
50/67
Final year project
37
Beam B2Design of beam in 1,4m of transversal distance from the towers
Load on the Uniformly Distributed Load on beam
5.15*0.89 = 4.584 kN/m
Where 0.885m is equal to the half of perpendicular distance of the span and 1.7m is the
length taken in design.
Imposed load = 3 kN/m2*0.885 = 2.655 kN/m
Design load = (4.584*1.4) + (2.655*1.6) = 10.07 kN
Two end ReactionRA andRB = wL/2
= 10.07*1.7/2 = 9.086 kN
The resulting diagrams are shown in figure 10. Beam B1 is standard case i.e. a simply
supported beam with uniformly distributed load.
M max = WL2/8
= 10.07*1.72/8 = 3.64 kN m
From equation required S = M max/y
= 3.64*106/210*10
3 = 17.333 cm
3 Try I 80 DIN 1025
4.5.2 DESIGN LONGITUDINAL BEAMS
Beam B3 of 1.4 m lengthDesign load
Design of beam of 1,4m of longitudinal distance from the towers
Load on the Uniformly Distributed Load on beam
Live load = 5 kN/m2
Timber structure = 0.15 kN/m2
Imposed load = 3 kN/m2
Dead load: 5+0.15 = 5.15 kN/m2
Then, total load is 5.15*0.75 = 3.8625 kN/m
Where 0.75m is equal to the half of lateral distance of walkway
Imposed load = 3 kN/m2*0.75 = 2.25 kN/m
Design load = (3.8625*1.4) + (2.25*1.6) = 9.007 kN/m
Evaluation of beam reaction, shear force and bending moment
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
51/67
Final year project
38
Two end ReactionRA andRB = wL/2
= 9.007*0.894/2 = 4.026 kN
The resulting diagrams are shown in figure below. Beam B3 is standard case i.e. a
simply supported beam with uniformly distributed load.
M max = wL2/8
=9.007*1.42/8 = 2.207 kNm
Figure 11: load, shear, moment diagram
From equation required S = M max/y
= 2.207*106/210*10
3= 10.509 cm
3
Try I 80 DIN 1025 having area of 7.57 cm2
Beam B3Design of beam of 0.77m length of longitudinal distance in 2.94m from the towers
Load on the Uniformly Distributed Load on beam
5.15*0.75 = 3.8625 kN/m
Where 0.885m is equal to the half of perpendicular distance of the span and 1.7m is the
length taken in design.
Imposed load = 3 kN/m2*0.75 = 2.25 kN/m
Design load = (3.8625 *1.4) + (2.25*1.6) = 9.007 kN
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
52/67
Final year project
39
Two end ReactionRA andRB = wL/2
= 9.007*0.77/2 = 3.467 kN
The resulting diagrams are shown in figure 11. Beam B3 is standard case i.e. a simply
supported beam with uniformly distributed load.
M max = wL2/8
= 9.007*0.772/8 = 0.667 kN m
From equation required S = M max/y
= 0.667*106/210*10
3= 3.176 cm
3
Try I 80 DIN 1025 having area of 7.57 cm2
4.6 DESIGN OF SUSPENDERS CABLE DIAMETER
Design reaction in the suspenders is equal to the reaction in the beam floor
Reaction or tension R = 10.22 kN
Area = tension/max stress
A = 10.22*103/240
A = 45.583 mm2
Then, cable diameter D = (45.583*4/3.14)1/2
= 7.62 mm = 0.762 cm
Take the cable diameter of 0.8cm for each suspender
Figure 12: suspender cable diameter
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
53/67
Final year project
40
4.7 DESIGN OF TOWERS
Determination of the dimension of suitable standard universal columns
Load in one tower is 77.292 kN
Design load for 1 column 77.292 kN
Length of the columns 6 m = 6000 mm
The estimated Compressive strength at the member is 210 N/mm2
Appropriate area = design load/estimated stress and the
Actual stress = design load /actual area
Figure 13: load column
Design of one tower
Approximate area = 77.292*103/210*10
2= 3.68 cm
2
Checking of Deflection:
Shear force = 5wL3/384EI
Allowable shear force =L/325
Actual shear force = 6000/325 = 18.46mm
I = 384*52.9*18.46*102/ (5*77.292*6
3) = 449.33 cm
4
Use I 140 DIN 1025
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
54/67
Final year project
41
Figure 14: column and beam dimension
4.8 DESIGN OF FOUNDATION
Data
Load w = 77.292 kN
Concrete class c20/25gives:
Use Soil bearing pressure of soil= 0.02 kN/cm2
Compression resistance of concrete fck,cyl= 20 N/mm2, fck, cube= 25N/mm
2
Tension resistance of concrete fcy= 460 kN/cm2
Calculation of DimensionRequired area of foundationA = w/soil
A = 77.292/0.02 = 3864.6 cm2
Use square foundation, width of pad bf = (3864.6)1/2
=62.166 cm
Take width bf of 63 cm.
Depth of pad is equal to B*1/6
D = 63/6 = 10.5 cm
The depth of 10.5 is very small, so we can take D = 20 cm
Use a foundation of B = 63 cm square and 20 cm deep
Figure 15: foundation
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
55/67
Final year project
42
ReinforcementFor concrete cover of 5 cm and assuming 1.0cm diameter bars, the effective depth d of
the top layer of reinforcement is:
d1= 10.5-5-1.0-0.5 = 4
d2= 20-5-1.0-0.5 = 13.5 cm
As = M max/0.9* d1*Rs
Ground pressure, q = w/B2= 77.292/632= 0.01947 kN/cm2 = 194.7 kN/m2
And maximum moment = p*lc*bf* (lc/2)
0.02*24*63*24/2 = 362.88 kNcm
As = 362.88*103/0.9*40*37.5 = 268.8 mm
2
Cross sectional area of one bars = 102*3.14/4 = 78.5
Number of bars = 268.8*4/78.5= 3.424 bars
Take 4 bars
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
56/67
Final year project
43
Figure 16: Reinforcement in foundation
Shear
Shear across the pad:
Actual Shear force 0.54*d2*bf*RbtActual shear force = q*bf* (lc- d2)
= 0.02*63* (24-13.5) = 13.23 kN
Actual Shear force 0.54*0.09*13.5*63
13.23 < 41.33
Proposed dimensions and reinforcement are satisfactory.
Figure 17: distribution of bars
4.9 DESIGN OF COLUMN BASE
The column is axially loaded slab base; the column has 152*152*37 Kg which carries a
total load of 77.292 adopting a square slab.
The concrete strength is 30kN/mm2.
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
57/67
Final year project
44
Design load = 77.292kN
Area = 77.292*103/0.4*30
= 5520.857 mm2
Make the base of 600mm square.
Pressure P = 77.292*103/600
2
P = 0.215 N/ mm2
The arrangement of the column on the base plate is shown in figure below. From this
Project base a =224 for all side
Figure 18: base column
Assume the thickness of plate is less 40mm. design strength = 265N/mm2(Table 6)
The thickness of the base plate is given by:
t = ((2.5*0215)/265*(2242-0.3*224
2))
Thickness t = 8.38 mm
Design of thickness of welding
Thickness of weld = 0.7* leg length
Let assume the leg length = 1 cm
Then, t = 1*0.7 = 0.7 cm
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
58/67
Final year project
45
4.10 DESIGN OF STAIRS LONGITIDUNALY BEAMS
Data
Rise = 300 cm
Going = 300 cm
Waist = 250 cm
Number of rise 12 risesSpan = 460 cm
Loading
Live load = 5 kN/m2
Timber structure load = 0.15 kN/m2
Imposed load = 3 kN/m2
Dead load: 5+0.15 = 5.15 kN/m2
Then, total load is 5.15*0.7 = 3.605 kN/m
Where 0.70m is equal to the half of lateral distance of walkway of stairs
Imposed load = 3 kN/m2*0.70 = 2.1 kN/m
Design load = (3.605*1.4) + (2.1*1.6) = 7.14 kN/m
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
59/67
Final year project
46
Figure 11: load, shear and moment diagram
Calculation of negative moment
Formulas used
w = 7.14 kN/m
MB * lAB + 2MB (lAB+ lBC ) + MC * lBC= -wlAB3/4-wlBC
3/4
MB*lBC+2 MC (lBC-0)+0 =-wlBC3/4
2MB*5.475+ MC*2.58 = -7.14*(2.8953/3)-7.14*(2.58
3/4)
2.58 MB+ 2 MC*2.58 = -7.14*2.583/4
10.95 MB+2.58 MC= -73.96 (*-2)
2.58 MB+5.16 MC= -30.65 (*1)
21.9 MB+5.16 MC= 147.92
2.58 MB+5.16 MC= -30.65
-19.32 MB= 117.27
MB = - 6.069 kNm
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
60/67
Final year project
47
MC = -2.91 kNm
Calculation Positive moment
Mx= Mo + Mn-1+ (Mn-Mn-1)/ln
Mo= 7.14*2.8952/8 = 7.48 kNm
MAB= 7.48+ (6.09*1.45/2.895) = 4.44 kNm
Moo = 7.14*2.582/8 = 5.94 kNm
MBC= 5.94-6.09 + ((-2.9+6.07)/2) = 1.43 kNm
Then, to find out the dimension of beam we use the maximum moment
Thus, M Max is Mo= 7.48 kNm
Plastic modulus,
S = M max/y
= 7.48*106/210*103= 35.619 cm3
Take I 140 DIN 1025 for each beam of beam
4.11 DESIGN OF LATERAL BEAMS OF STAIRS
Design load = 7.14 kN
Evaluation of beam reaction, shear force and bending moment
Two end ReactionRA andRB = wL/2
= 7.14*1.4/2 = 4.998 kN
The resulting diagrams are shown in figure below. Beam B3 is standard case i.e. a
simply supported beam with uniformly distributed load.
M max = wL2/8
=7.14*1.42/8 = 1.75 kNm
Figure 11: load, shear, moment diagram
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
61/67
Final year project
48
From equation required S = M max/y
= 1.75*106/210
3= 8.33 cm
3
Try I 80 DIN 1025 having area of 7.57 cm2
4.12 DESIGN OF SUPPORT COLUMN OF STAIRS
Determination of the dimension of suitable standard universal columns
Load in one column is =7.747 kN/m *
Length of the columns 3.3 m = 3300 mm
The estimated Compressive strength at the member is 100 N/mm2
Appropriate area = design load/estimated stress and the
Actual stress = design load /actual area
Figure 20: stair column
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
62/67
Final year project
49
Design of column
Reaction at the support = wl2/2
= 7.717*1.4/2 = 5.43 kN
Approximate area = 5.43*103/210*10
2= 0.26 cm
2
Checking of Deflection:Shear force = 5wL3/384EI
Allowable shear force =L/325
Actual shear force = 3300/325 = 10.15mm
I = 384*52.9*10.15/ (5*5.43*100*3.33) = 21,132 cm
4
Use IPE 120
4.13 DESIGN OF FOUNDATION FOR COLUMNS OF STAIRS
Design data
Load w = 5.43 kN
Concrete class c20/25gives:
Use Soil bearing pressure of soil= 0.02 kN/cm2
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
63/67
Final year project
50
Compression resistance of concrete fck,cyl= 20 N/mm2, fck, cube= 25N/mm
2
Tension resistance of concrete fcy= 460 kN/cm2
Required area of foundationA = w/soilA = 5.43/0.02 = 271.5 cm
2
Use square foundation, width of pad bf = (271.1)1/2
=14.53 cm
Take width bf of 20cm.
Depth of pad is equal to B*1/6
D = 20/6 = 3.3 cm
The depth of 3.3 is very small, so we can take D = 20 cm
Use a foundation of B = 20 cm square and 20 cm deep for each foundation of
tower.
4.14 DESIGN OF ANCHORAGE BLOCKS
Figure 21: anchor and fixation of cable
Source: hp: // www.google.com/design of suspended brigdes/anchorageA2
Weight of one anchor block:
WA= Tension in cable*cosine between cable and earth surface
And Weight*DW> Tension *DT
DW: horizontal distance
DT:vertical inclined distance
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
64/67
Final year project
51
Let assume DW = 1 m
Max force or Tension in cable = 223.515 kN
Angle = 590
Then, WA = 223.515*cosine 590= 115.18 kN
Thus, the weight 115.18 kN
Weight*DW > Tension *DT
115.18*1 > 223.515* DT
DT = 1.94 m
Use the anchor of vertical inclined distance of 1.94m and horizontal distance of 1.0m
The volume of anchor =115.18/25 = 4.6 m3
Surface area of bloc = 4.6/1.94sin600= 2.738 m2
Where 1.94sin600is the true height
Take a square base surface = (2.737)1/2= 1.65 m
H = 1.68m, B = 1.65m, L =1.65, DT= 1.94m and DW= 1m
4.15 DESIGN CONNECTIONS WITH BOLTS
For ordinary bolt of grade 4.6 the value of shear stress given in table 30 of bs 5950: Part I: 2000
as 160N/mm2
For bolts the gross diameter is, of course, equal to the nominal diameter. Therefore the safe load
in single shear, or single shear value (ssv)
Shear stress = w/area of 1 bolt, i.e. 160 = w/ area of 1 bolt
Where area of 1 bolt = 3.14*d2/4
Data, for beams, maximum load = 7.48 kN
Shear force = 160 N/mm2
Then A = (7.48*103/160)1/2= 46.75mm2
Diameter D = 7.717mm
Use D = 8mm for each bolt.
For column, maximum load is 77.292 kN
Shear force = 160 N/mm2
Then A = (77.292*103/160) = 483 mm2
Because we have 4 bolts in the base of column
One bolt has diameter D =12.4 mm
Use D = 13 mm for each bolt
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
65/67
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
66/67
Final year project
53
REFERENCES
BOOKS USED:
1. Foundation design and construction, M. J Tomlinson, sixth Edition, 1995,Addison Wesley Longman
2. Steel work design guide to BS 9550: Part I: 1990, volume I, section propertiesand member, capacitors, fifth Edition, 1997, the Steel Construction Institute
3. Structure steel work, design to limit state ,second edition4. Understanding structures analysis, material, design, second Edition, (1998),
DEREK SEWARD (1998)
INTERNETS:
(http://www.google.com/analysis of suspension bridges) (May 2007)
(http://www.google.com/unstiffened bridges) (May 2007)
(http://www.google.com/Multiple-span bridges) (August 2007)
(http://www.google.com/suspension bridges) (August 2007)
(http://www.google.com/design of suspended brigdes/anchorageA2) (August 2007)
-
8/13/2019 m 2008 Ceet 01 Ryoba Vuzimpundu Eugene Gs20031702
67/67
Final year project
APPENDICES