LTSEC summer auction Transmission Workstream 6 th April 2006 Dave Adlam, National Grid NTS.
-
Upload
aldous-pope -
Category
Documents
-
view
214 -
download
0
Transcript of LTSEC summer auction Transmission Workstream 6 th April 2006 Dave Adlam, National Grid NTS.
LTSEC summer auction
Transmission Workstream
6th April 2006
Dave Adlam, National Grid NTS
LTSEC Auction timetable
Currently runs in September (UNC obligation) An earlier timetable may be beneficial because:
Greater notice of requirements for incremental capacity Potential to reduce the requirement for the request for extension
to lead times under the IECR Align with TBE process
Greater information to formulate supply and demand position
Annual auction would potentially be better in May Can’t achieve it this year Uncertainty for 2007 onwards
Requirements to enable an early 2006 LTSEC auction
Amendments required to allow an early 2006 LTSEC auction
Approval of UNC Mod Proposal IECR review and consultation Extension to investment lead times consultation
UNC Modification Proposal
UNC Modification Proposal To include transitional legal text to enable an early
auction this summer [July] Workstream comments on draft proposal?
Support for a 10 day consultation
Requirements to enable an early 2006 LTSEC auction
IECR Commence IECR review in early April (draft issued to
workstream) Introduction of a methodology describing how the incremental
costs will be generated each year.
Submit to the Authority by beginning of May The proposed changes for the IECR are
Introduction of a methodology to determine the future cost of investment
Amendment from Transco to National Grid
IECR Proposals
Introduce a Methodology to determine the future cost of investment
Currently the IECR contains a table which indicates the cost (in £m per km) of future investments
National Grid undertakes work to establish these values each year and are affected by:-
Steel PricesConstruction costsInflation
The proposal is to replace the existing formula with a methodology that demonstrates how these values are derived.
Investment Cost Methodology
National Grid would utilise projects that have been undertaken in the last 4 years and are planned and projected to complete in the next four years as a basis for deriving the cost of the release of any incremental capacity
Produces an average cost for each project per metre, dependent on pipeline diameter
This data is normalised, by use of the Structural Steelworks Labour Price costs index according to the construction year to take account of changes in
Steel Prices Construction Costs Inflation
Investment Cost Methodology
Once the costs have been normalised the values are plotted onto a scatter graph and a trend line is drawn between the data to establish the values that will populate the pipeline cost formula.
Investment Cost Methodology
Cost per metre £
Pipeline Diameter (mm)
£/m range of existing schemes
Linear regression
Values for Trancost formula
Pipeline Cost Formula
Pipeline cost £m per km = 0.0012507 * diameter (mm) – 0.01507 / km
Revised Formula
Pipeline cost £m per km = 0.000407 * diameter (mm) + 0.38561 / km
Current Formula
Requirements to enable an early 2006 LTSEC auction
Request to adjust investment lead times consultation
Requirement to amend lead time to ensure efficient delivery of incremental capacity
Finalising our requirements
Next Steps
UNC Mod Proposal Submitted to April Mod Panel
IECR annual review & Consultation to extend investment lead times
Released for consultation shortly 28 day consultation