L&T SHE program

55
Larsen & Toubro Limited Safety, Health & Environment Plan Proj : PRP Project Rev : 00 Date : 1 st September, 05 Project Specific Safety, Health & Environment Plan For PIPELINES REPLACEMENT PROJECT 00 01 September, 05 For Approval of ONGC PNM DKA JBD REV. DATE DESCRIPTION PREPR’D CHK'D APPR'D APPR'D ACCPT’D

description

SHE Program

Transcript of L&T SHE program

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 1 of 41

Project Specific

Safety, Health & Environment Plan

For

PIPELINES REPLACEMENT PROJECT

00 01 September, 05 For Approval of ONGC PNM DKA JBD

REV. DATE DESCRIPTION PREPR’D CHK'D APPR'D APPR'D ACCPT’D

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 2 of 41

TABLE OF CONTENTS

S/N DESCRIPTION

1.0 SCOPE AND DESCRIPTION OF THE PROJECT

1.1 Scope of Safety, Health & Environment plan

1.2 Description of the Project

2.0POLICY AND MANAGEMENT COMMITMENT TO SAFETY, HEALTH AND ENVIRONMENT

2.1 Corporate Policy

2.2 Safety goals & objectives

2.3 Summary Statement

3.0 SHE ORGANISATION

3.1 SHE Organisation of L&T – E&C Division

3.2 SHE Organisation of Fabrication Facility (MFF-Hazira)

3.3 Offshore SHE Organisation

4.0 DUTIES AND RESPONSIBILITIES

4.1 Management

4.2 Safety Control Department

4.3 Resident Construction Manager

4.4 Site Safety Officer

4.5 Site Engineers and Supervisors

4.6 Construction Sub-Contractor’s Manager/Site in-charge

4.7 Construction Sub-Contractor’s Safety Officer

4.8 Construction Sub-Contractor’s Worker

4.9 Construction Sub-Contractor’s site Engineer

4.10 Workmen

5.0 PERSONAL PROTECTIVE EQUIPMENT

5.1 Types of Personal Protective Equipment

6.0 SAFE WORK PROCEDURES

6.1 Concreting

6.2 Piling

6.3 Excavation

6.4 Working at Height

6.5 Object Falling from Heights

6.6 Electrical Hazards

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 3 of 41

6.7 Electrical Lock / Tag out Procedure

6.8 Pressure Testing

6.9 Shot Blasting / Spray Painting

6.10 Permit-to-Work

6.11 Gas Cutting and Welding

6.12 Electrical Hand Tools

6.13 Scaffolding

6.14 Lifting Equipment / Appliances

6.15 Rigging and Lifting

6.16 Confined Space Entry

6.17 Housekeeping

6.18 Helicopter Safety

6.19 Work Over Water

6.20 Smoking

6.21 Radiography

6.22 Noise

6.23 Vehicle Movement

6.24 Offshore Safety

6.25 Fire Protection

6.26 Hazard Identification and Risk Assessment

6.27 Inspection/ Auditing

7.0 MANAGEMENT OF CHEMICAL HAZARDS

8.0 ACCIDENT/ INCIDENT REPORTING AND INVESTIGATION

9.0 MONTHLY STATISTICS REPORT

10.0 SAFETY COMMUNICATION

10.1 Safety Committee

10.2 Education and Information

10.3 Signs, signals and barricades

Annexures

Annex 1A Safety at working at Height - Check List

Annex 1B General Safety Inspection - Check List

Annex 1C Housekeeping - Check List

Annex 1D Scaffolding - Check List

Annex 1E Electrical Safety Inspection - Check List

Annex 2A Radiography Work Permit (OHSR)

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 4 of 41

Annex 2B Hot Work Permit (OHSH)

Annex 2C Cold Work Permit (OHSC)

Annex 2D Confined Space Entry Permit (OHSCS)

Annex 2E General Electrical Permit (OHSE)

Annex 3A Accident Report (L&T)

Annex 3B Accident Investigation Report (L&T)

Annex 3C Accident Report (Client)

Annex 3D Quarterly Accident Report form

Annex 4 Analysis of First-Aid Cases

Annex 5 Dangerous Occurrence / Near Miss Accident Report

Annex 6 Monthly Statistics Report

Annex 7 Hazard Identification and Risk Assessment

Annex 8 Safety Audit – Check List

Annex 9 Site Safety Audit / Inspection Report

Annex 10 List Of Hazardous Chemicals Not To Be Used

Annex 11A Content Of Toolbox Talks

Annex 11B Pep Talk / Tool Box Talk Report

Annex 12A Minutes of Safety Committee / Council Meeting Attendance Sheet

Annex 12B Minutes of Safety Committee / Council Meeting Report

Annex 13 Safety Induction Report

Annex 14A Crane Inspection – Check List

Annex 14B Crane / Vehicle / Earth Moving Equipment Inspection Report

Annex 14C Vehicle / Earth Moving Equipment Inspection Report

Annex 15 Safety Sign Boards

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 5 of 41

1.0 SCOPE & DESCRIPTION OF THE PROJECT

1.1 Scope of Safety, Health & Environment Plan

This Plan covers: the requirement of the accidents prevention rules, and safety programto be applied to the project.

The primary purpose of this procedure is to provide guidelines for prevention and accidents that may cause employee's injury or property damage of the L&T and its Subcontractors at site.

Construction subcontractors shall abide by: All safety rules and other regulations imposed at the site by the laws of the country, All the applicable local laws, rules and regulations and All the rules, regulations and procedures as applicable from client / prime contractor.

1.2 Description of the Project

Laying and completion of 49 pipeline segments (244.8 kms) which includes project management, survey, engineering, procurement, fabrication, anti corrosion and weight coating wherever applicable, transportation, laying, hook up, pre-commissioning and commissioning and testing of pipelines in western offshore, Mumbai, India on turnkey basis.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 6 of 41

2.0 POLICY AND MANAGEMENT COMMITMENT TO SAFETY, HEALTH & ENVIRONMENT

LARSEN & TOUBRO LIMITEDEngineering & Construction Division

2.1 CORPORATE POLICY

1. To Engineer and Execute projects with consistent quality, cost and delivery in line with the requirements of our customers, and to exceed or meet their expectations, whilst enhancing our shareholder value.

2. To set and review quality objectives for Continual Improvement of our products and services, whilst implementing the globally recognised management systems for Quality, Safety, Environment and Information Technology, and integrating these systems with our business partners and customers.

3. To design / operate and maintain safe and environmentally friendly plants which meet all applicable statutory and regulatory requirements.

4. To advance / ensure the use of better and cleaner technology to minimise adverse environmental impacts.

5. To continually reduce the risk of pollution through setting environmental objectives in our design / operation and maintenance processes, based on the feedback.

6. To deploy Information Technology for increasing the efficiencies of our business processes, while ensuring its security by protecting information as valuable assets and ensure availability, integrity and confidentiality of all information.

7. To comply with all applicable occupational Health & Safety legislation and continually improve safe working practices through setting health and safety objectives and ensure good health, safety and security of all our people, our biggest asset.

8. To encourage enthusiasm, innovation and empowerment whilst developing inspiring leaders to make working at L&T a rich experience and create new global benchmarks in whatever we do.

9. To promote a culture of mutual trust, caring and sharing achievements, with our people, our society, our stakeholders and our customers for the growth and benefit of our Nation.

10. As an undisputed leader in the Indian context, we continue to make things that make India proud, and shall strive to be amongst the globally outstanding companies, which the World is proud of.

__________________________Issue : Jan, 2002 K. VENKATARAMANAN

(Member of the Board & President)

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 7 of 41

2.2 Safety Goals & Objectives

Safety Goal: Zero Injuries and Losses in the work undertaken by L&T

Objective: The objective of this program is to ensure effective control of Injuries and Losses in Construction work undertaken by L&T, E&C Division. It describes the plans and essential procedures for the protection of men, and properties in Construction Work.

The Construction Industry functions in a dynamically changing work environment in which updating of equipment and standards is a continuous process resulting from changes in operating variables, regulatory requirements, and Safety Practices.

The Program is designed to assist all those who deal with safety program as a functional responsibility within context of their Job. Good Loss Prevention is an integral part of good Project Management.

Loss Prevention should be encouraged by example, knowledge, skills, overall attitude, and involvement in the total Safety Program.

All L&T, E&C Division and Subcontractor personnel involved in Construction activities, whether Management or Line employees, need to understand and follow the provisions in this Procedure.

Thrust Areas for Safety: Each one has the RESPONSIBILITY AT ALL LEVELS in management to enforce

standards of loss prevention within their department of project. Continuous EDUCATION, TRAINING & MONITORING. Establish and comply with Safety Regulations Take precautionary measure BEFORE an accident occurs. Create HAZARD FREE & CLEAN ENVIRONMENT. SAFETY PROMOTION through recognition of Safety Performance.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 8 of 41

2.3 Summary Statement:

L&T’s Corporate policy expresses the view of the L&T management towards the SHE, which considers the Safety, Health and Environment of all personnel as important factor and recognise them as very essential for welfare and morale of personnel as also for contributing to company’s growth.

L&T understands that high standards of Health and Safety shall only be achieved by the dedicated and demonstrated efforts of all project personnel from top management down. At L&T planning and accountability for health, safety of people precedes all other project objectives.

L&T corporate policy recognises the importance of Safety and assure compliance with Law of country and local laws for creating safe working conditions at Project sites.

L&T is committed to upgrade the skills and abilities through continuous training and education.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 9 of 41

3.0 SHE ORGANISATION

3.1 SHE Organisation of L&T - E&C Division

The SHE organisational structure of L&T’s E&C Division Safety Management’s system and personnel responsible for safety aspects are as follows:

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 10 of 41

3.2 SHE ORGANISATION OF FABRICATION FACILITY (MFF-HAZIRA)

Head

MFF Hazira

Head – Safety

MFF Hazira

Safety Engineer

MFF Hazira

Contractor Safety Stewards

Head – Safety

Head Office, Powai

Safety Engineers

Head Office, Powai

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 11 of 41

3.3 OFFSHORE SHE ORGANISATION

Project Manager

L&T

Project Manager

Sub-contractor

Safety Manager

Sub-contractor

Safety Co-ordinator(Offshore)

Sub-contractor

L&TRepresentative

(Offshore)

Site Safety Officer(Offshore)

L&T

Head – Safety

Head Office, Powai

Safety Engineers

Head Office, Powai

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 12 of 41

4.0 DUTIES AND RESPONSIBILITIES

4.1 ManagementThe safety, health and welfare of all employees are the management's prime concern. The management shall constantly achieve its objective by: Providing and maintaining safe and healthy work environment. Providing all supports and resources for creating safe working conditions. Establishing and adhering to proper work practices and procedures to prevent accidents

and illnesses. Adherence to statutory requirements pertaining to occupational Safety, Health and

Environment.

4.2 Safety Control Department To participate in safety activities and give full support for the programme. To review and act upon safety records. To insist on safety being planned into all the operations undertaken at all times under

any conditions. To develop an effective programme of accident prevention. To review the effectiveness of the provisions of the Safety, Health and Environment

Manual. To periodically inspect and audit the site for SHE. To provide adequate training to the engineers, supervisors and construction team

members.

4.3 Resident Construction ManagerHe is overall in-charge of the safety of the site, for the statutory compliance and adherence to the guidelines given in this manual. In addition to this his other responsibilities are: To ensure & maintain safe working conditions and practices for all employees under his

supervision. Ensure that contractors follow safe working practices in line with the company policy and

will take steps to rectify. To interact with the clients and ensure their expectations with regard to safety are met in

project execution. To provide adequate training to all personnel working at site. To ensure the understanding of the job hazards and safe procedures before putting

them on to the job. To maintain good housekeeping at the project site.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 13 of 41

To ensure the provision of adequate personal protective equipment and their maintenance and proper use.

To encourage safety suggestions and act upon them immediately. To conduct regular safety meetings. To ensure that SHE manual is made available at site and copies/ abstracts are issued to

all concerned including sub contractors. To ensure that sub contractors are given proper instructions to comply with safety

standards and entries are made in the daily logbook maintained at the site of all verbal instructions given to the contractors.

To ensure proper feedback is given to the connected L&T departments about shortfalls in design etc. from construction safety point of view, for future actions.

To ensure First aid arrangement are made and maintained at work place. To ensure positive measures are implemented at site and give encouragement and

recognition for best safety practices. To review with all supervisors and safety officers and to ensure that all unsafe acts and

conditions are eliminated.

4.4 Site Safety OfficerThe site safety officer is responsible to ensure the over all safety of the site. Functionally he will be reporting to the safety control department, L&T HO and take guidance from them. He will familiarize himself with Safety Program and Safety Procedures of L&T. In addition he will: Promote & implement the SHE manual at project sites. Give assistance in solving safety-related problems, and making recommendations for

improving safety. Suggest standards to prevent injuries/losses. Investigate near miss incident and accident reports and monitor the site safety

performance. Advise concerned supervisor/RCM to stop work when the need arises. Advice on legal requirements affecting safety. Maintain liaison with client’s safety officer/safety, subcontractor’s, other departments

such as Medical and Training, etc. Propagate safety through leaflets, memos, reports, poster, notices, etc. Provide assistance to all level of management to implement accident prevention

activities. Arrange and participate in periodic safety inspection of work areas. Prepare and keep adequate records of accidents and reports and tendering of advice to

prevent recurrences.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 14 of 41

Conduct Safety meeting at least once a month to discuss various aspects on safety with sub contractors and clients and minuted. The frequency of the meeting shall be increased during peak time.

Review the implementation of points discussed in Safety Committee meetings. Conduct Safety Tool Box Talks. Be important member of the emergency response team and perform duties as

mentioned in the emergency plan. Develop material handling procedure for heavy lifts and ensure its implementation. Report accidents and other safety reports such as positive reports, safety committee

reports and investigation reports to the safety control department, L&T HO.

4.5 Site Engineers and Supervisors Supervisors on site will familiarise with Safety Manual, Emergency Response plan

approved by ONGC. They will actively supervise safety of their workers; conduct daily inspection of their

construction site, equipment, and work area to detect and correct hazardous conditions and unsafe acts.

Provide adequate Personnel Protective Equipment, the standard equipment and materials related to Safety as required.

Plan and provide for good housekeeping. Check that equipment and tools, both power and hand tools are maintained in good

condition. Position equipment effectively and ensure that electricity supply is installed, used and

maintained correctly. Be familiar with work permit system of ONGC. Make sure that all men know how to obtain and administer first aid properly and

efficiently to all injured persons. They should also know how to summon assistance in case of emergency and nominate others to act in your absence.

Ensure that verbal instructions are fully understood and check back to see that they are carried out as intended.

Conduct weekly safety meeting with the foremen and their crew once a week. Co-operate with L&T, E&C Division SSO by action on his recommendations. Set personal example on site by wearing appropriate protective clothing and equipment

at all times. Ensure that regular tool box talks are conducted to communicate the hazard in various

construction activities in progress. Ensure all safe activities are put into practice for construction activities and the safe

procedures covered in Safety program are followed strictly.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 15 of 41

4.6 Construction Sub-contractor's Manager / Site In-charge shall Be responsible for all safety activities, including fire prevention during the construction

period. Submit a safety program including safety measures for the work to the safety engineer

prior to commencement of the work. Establish, implement and maintain the safety program and determine the effectiveness

of individual elements of the program.

4.7 Construction Subcontractor's Safety officer shall: Conduct a safety program under the direction of the Construction Manager/Site

incharge. Patrol the work site periodically to verify that the work is carried out under safe

conditions, with no violations of safety requirements. Advise promptly the construction supervisors and workers of the corrective action when

any unsafe conditions or violations are observed. Check each work procedure from the safety point of view and advise the construction

supervisors before commencement of work and/or while working. Safety supervisor shall closely work with Site Safety Officer and ensure that no

contradictory work methods are practised during construction. Submit accident report to L&T Site Safety Officer and Company's representative. Maintain the published safety literature, safety regulations, codes and other

communications. Advise management of compliance and conditions requiring attention.

Make thorough analysis of the statistical data through inspection, delineate problem areas, and make recommendations for solutions.

Check on the use of all types of personnel protective equipment effectiveness and suggest improvements.

Submit the plan to L&T safety officers prior to start the activities.

4.8 Construction Subcontractor's Worker shall: Do nothing to endanger him or co-workers. Use the correct tools and equipment for the job. Keep tools in good condition. Undergo Safety orientation and training conducted by L&T Safety Officer. Observe all site safety rules and regulations.

4.9 Construction Subcontractor’s Site Engineer

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 16 of 41

Be familiar with those parts of L&T, E&C Division's Safety Program applicable to the work on which subordinate workers are engaged.

Incorporate safety procedures in routine tasks and see that they are obeyed. Conduct toolbox talks for crewmembers in consultation with RCM and SSO, prior to

daily work starts. Conduct daily work site inspections to identify and correct any existing unsafe

conditions. Document and co-ordinate the safety inspection activities and findings with the job site safety supervisor.

Eliminate unsafe acts and unsafe conditions at construction site. Ensure all workmen undergo a safety orientation program at project site before they are

engaged in site work. Ensure that new employees are properly instructed in precaution to be taken before they

are allowed to start work. Commend men who, by action or initiative, eliminate hazards. Report accidents, unsafe conditions and defects in equipment to immediate superiors. Set a personal example.

4.10 Workmen Do nothing to endanger himself, his co-worker or the work. Refrains from horseplay. Use only the correct tools and equipment for the job. Uses the personal protective

equipment provided and uses them correctly. Refrains from abuse of safety devices, equipment and welfare facilities.

Keep tools and equipment in good condition. Report defects to supervisors. Observe all safety rules and regulations at all time and obey all posted

warning/regulatory signs. Take no chances if safe work procedure is unknown or in doubt. Serve on the safety committee; make safety suggestions and undertake no risks or

short cuts. Report all unsafe practices and unsafe condition. Maintain good housekeeping, teach safety to new employees, and set a good example. Make Safety a part of everyday job. If in doubt, please check with your immediate supervisor. There always is a right and

safe way to do a job.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 17 of 41

5.0 PERSONAL PROTECTIVE EQUIPMENT

5.1 Types of Personal Protective Equipment:

Various types of PPE are available & must be worn to lessen the seriousness of injury. There are thousands of people maimed for life because they fell to wear their PPE. Following are the rules & regulations that apply to this project.

(1) Head Protection: Welders will wear hard hat when on the open deck or on land except when they are

actually welding or working within the welding stalls or booths. Rigger will wear hard hat on the top deck or on the land and when working in the

construction spaces where head injury hazard exist. Engineer will wear hard hat on the top deck or on the land where head injury hazard

exist.

(2) Foot Protection: Safety Shoes must be worn by all project personnel at all times during shifts and any

time when they are engaged in project work.

(3) Eye Protection: Safety glasses with side shield or safety goggles and a full face shield will be worn

by all personnel when buffing or grinding, gas cutting, this include welder also. All personnel when chipping, paints, cleaning activity, etc. All personnel carrying out any operation or entering any area where eye injury can

occur. This includes inspectors, client’s representatives.

(4) Face shield: All personnel using strong cleaning agents including engineers, etc. All personnel working or entering in any area where corrosive substance are being

used. Area where the RCM deemed it necessary.

(5) Hand Protection: Any job that will cause injury to hand i.e working with hot object, wire rope, handling

metal plates, etc.

(6) Hearing Protection:

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 18 of 41

Ear plugs or muffs shall be worn in all areas designated as a high noise area or any operation where hearing can be impaired.

(7) Respiratory Protection: Dust mask respirators are to be worn in dusty areas. Fume or toxic respirators are to be worn when painting or spraying any solvent or

chemical. Hose line or self-contained breathing apparatus will be worn when entering untested

voids, extremely smoke field atmosphere where oxygen deficiency exists. Abrasive blasting hose (with protective suit also) with air line breathing apparatus

during any blasting operation.

(8) Safety Belts: All employees will wear safety belt when working above 2m height from ground. No more than 4ft of lanyard will be permitted. The lanyard should be secured to a substantial member of the structure no lower

than the waist of the wearer. It is responsibility of the employee to obtain and to wear the safety belt where there

is no safe scaffolding or staging is provided and where falling hazard exist.

(9) Life jacket/ work vest on barge:Any personnel (inspectors, client’s representative, visitors included) will wear work west under the following circumstances: When working or standing beyond the handrails or where no handrail is provided and

on any structure. During stormy or rough weather. While any flight over water. When transferring from or to, any equipment or vessel by any means. When ridding in an open boat or when outside the cabin or wheel house of any other

type boat. A safety belt may be used while working on a structure or equipment where it is not

possible to wear life jacket due to restriction of workspace or nature of job. Circumstances where the RCM deemed necessary.

(10) Protection against falls:

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 19 of 41

Opening between railings, on floor, wall, gang ways, elevated work places and other places where an employee is subjected to danger of falling shall be barricaded by barrication tape, chained or railings installed.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 20 of 41

6.0 Safe Work Procedures

6.1 Concreting Formwork stability should be checked previous to starting of concreting and during

pouring. While pouring at height / depth, concreting area to be barricaded. Pipelines for concrete pumping not to be attached to temporary supports for scaffold

and form work. Safety cages / guards shall be provided around moving motors etc. Vibrator hoses shall be in proper working conditions and mechanically locked. Workers working with cements shall be wear respirators. Electrical mixers, vibrators etc shall be suitable earthed. Cleaning of rotating concrete drums shall be done from outside. In case of IC engines as prime movers for concrete mixers, exhaust points shall be

located away form the worker’s workstation. Same workers shall not be allowed to pour concrete round the clock, shift pattern should

be insisted upon. Adequate illumination should be ensured in concreting area.

6.2 Piling To ensure that boreholes are properly covered to prevent anybody falling into it. All requirements of handling / lifting equipment are met under material handling.

6.3 Excavation Trenches 1.2 m or more depth shall be sloped back to a safe angle. Excavation in

unstable soil may require shoring or additional sloping. All excavated materials shall be placed at least 2m from the edge of excavation. Safe access must be provided into all excavations by means of ladders, stairs or ramps.

Excavations beyond 3m shall have two entries / exits. Excavations beyond 3m depths shall be barricaded and proper lighting arrangements

shall be made. Necessary precautions at the edge of excavation to be taken where machines are in

operation and also to protect entry of water in to trenches. No excavations should be proceeding in an area suspected of having live, buried oil,

and gas lines unless the lines have been located and marked and a permit is granted to this effect.

If any animal trapped inside the excavation pit, It shall be rescued by providing proper ramp

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 21 of 41

6.4 Working At Height1. Use Annex-1A safety at working checklist during commencing the work.2. Proper use of safety belt/ Safety harness / Fall arrester.3. Use of scaffolding & safety net below working area.4. Use of barricading for tall structures, while working at height.5. Use of roof ladders and crawling boards while working on the roof.6. Use of linesman safety belt while climbing on poles. Other structures.

6.5 Objects falling from Heights Use of toe guards Use of toolboxes / pouches for carrying the hand tools. Use of safety nets Discouragement of throwing up or down of materials / tools. Use of safety helmets by all.

6.6 Electrical hazards To ensure use of ELCBs / RCCBs of 30mA sensitivity. To ensure use of electrical “Tag Out” procedures. Electricians no to wear / possess any metallic objects during work. To ensure use of rubber mats / gloves by electricians. To use only properly armored and insulated cables and not to lay cables in wet / damp

areas. To ensure that cables are laid only below ground or at a height of minimum 4.5m.

To ensure proper earthing for all electrical systems / equipment. Electricians to check that contact points are not loose. To ensure use of only DC hand lamps when entering a confined space. To ensure not to work on or near live parts of electrical equipment excepts for

exceptional cases.

6.7 Electrical Lock / Tag out ProcedureTo ensure protection of project personnel who performs electrical work on electrical circuits or electrically powered equipment and to protect anyone who performs mechanical work on electrically powered equipment.

Only qualified personnel are permitted to operate or carry out maintenance on electrical system & equipment.

Before electrician works on electrical circuits or electrically powered equipment in a position such that he could be endangered, either electrically or mechanically, the

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 22 of 41

electrical power source shall be turned off and disconnected in accordance with the following lock-out procedure.

The electrician shall shut the equipment down. The electrician shall turn the main disconnect switch to the OFF position, and tag it with

the DO NOT OPERATE tag. The electrician shall additionally switch off auxiliary equipment. This will require a second tag.

The electrician shall push station to be sure the correct disconnect switch is tagged out. He shall then tag the push button with a DO NOT OPERATE tag.

The electrician shall inform the electrical engineer. Electrician working on the equipment shall de-energy unit & attached. ‘DO NOT

OPERATE’ tag on which he will write his name and date. It is the responsibility of this person to assure his own safety by keeping his tag on the disconnected equipment while he works on the equipment.

Portable equipment & electrical powered tools shall be checked prior to be issued to any employee.

After Work Completion Disconnecting and ‘DO NOT OPERATE’ tag shall be removed as follows: As electrician finished his work, he shall remove his tag. He shall advice the electrician / Engineer that he has energized the circuit. Any electrical system work requires the authorized of the electrician / electrical engineer.

There will be no exception.

Testing equipmentElectrician shall ensure testing equipment are regularly calibrated & in good working conditions.

Protective guardsGuards and protective items removed during the repair of electrical equipment are to be replaced immediately after the repair work has been completed.

Danger notice & singsDanger notices and signs shall be posted on all installation

6.8 Pressure testing Provide relief valves of adequate size while testing. Keep the vents open before opening any valve for filling/draining of liquid used for

hydro testing. The filling/draining should not exceed the designed pressure.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 23 of 41

Provide separate gauges of suitable range for pressurising pump and the equipment to be tested for monitoring of pressures.

6.9 Shot blasting / Spray Painting Shot balls used for shot blasting should be suitably covered & protected form rain /

moisture. Air compressor should be suitably guarded. Exhausted of the prime mover, if IC engine

should be directed away form the work place and in case electric motor is the prime mover the body of the motor and compressor to be properly earthed. The air shall be of proper quality.

The operator of shot blasting / painting should wear suitable PPEs including masks. Shot blasting should not be carried out in confined space.

6.10 Permit-to-Work (Refer Annex 02A -E)When any form of work listed in the Safety, Health and Environment Plan, L&T’s Safety Management System and any other local legislation is to be carried out on project the Permit-to-Work system shall be implemented.

The purpose of the Permit-to-work system is to: Ensure that such works can be carried out with due regards to safety, health and

welfare of workers; Prevent any incompatible work from being carried out at the same time on project. Ensure that the necessary safety precautions are taken and enforced when such work is

being carried out.

There are following types of permit used in the Permit-to-Work system. The following permits shall be implemented at onshore job & client permit system shall be followed during offshore job.- Radiography work permit for NDT (OHSR) (Annex-2A)- Hot work permit (OHSH) (Annex-2B)

For welding/ gas cutting, sand blasting, grinding, Spray Painting, running I.C. engines etc.

- Cold work permit (OHSC) (Annex-2C)For working at height, opening of flanges, manual sand removal, Manual Painting, Working on lifting tools/ tackles including chain pulley block, cranes (EOT, gantry, mobile) etc.

- Permit for entry into confined space (OHSCS) (Annex-2D)For entry into vessel, pit/opening excavated area etc.

- Permit for working on electrical lines/ equipment (OHSE) (Annex-2E)

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 24 of 41

There are five different ‘Permit’ forms, each dealing with one of the five activities mentioned above. Each form has certain standard instructions and space for writing special instructions by RCM/ RCE, related to the activity and site situation. These instructions have to be clearly understood by the workers, Manager/ Engineer/ Supervisor and ensured that they are followed by the persons actually carrying out the concerned activity. The forms, therefore, require signatures of concerned responsible persons, implying their commitment to the instructions. The forms also require communication regarding completion of the ‘permitted’ activities. After a form is returned stating completion of an activity, the same can not be carried out again unless the permit is renewed. The permit can be renewed for maximum 6 days only. Thereafter a fresh permit is required.

6.11 Gas cutting & Welding Gas cutting torches and hoses shall not be connected to cylinders when stored in any

enclosure or building. When work is shut down and hoses disconnected all valves at the gas and oxygen cylinder must be closed.

A flash back arrester must be equipped to flammable gas cylinder. Gas cylinder shall be handled with care, properly supported in an upright position. All cylinders shall be safety capped when not in use. Correct use at cut-off wrench to cylinder and be located at cylinder all the times. All cylinders shall be kept vertical position and secured in a cylinder trolley or similar

handcart. Acetylene cylinders shall be stored, handled and used vertical position to avoid liquid

action from escaping and damaging down stream equipment. Transport cylinder by manualing shall not be allowed. (Use trolley or handcart). LPG is often used as a fuel gas for cutting purpose and it is supplied in cylinder. Spark lighters shall be used to light torches. Matches and smoldering rags shall not be

used. Cylinders shall not be transported with the regulators and hose attached, except on a

purpose made trolley. Cylinders shall not be located in any enclosed space where welding or cutting job is

taking place. Oxygen and acetylene cylinder shall be kept at least 15 ft away from blowtorches or any

other approved source of ignition. Oxygen and acetylene hoses shall be of different colors otherwise identified and

distinguished from each other. Safety band to hose connection shall be used. Acetylene regulator pressure shall not be allowed to exceed 15 psig.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 25 of 41

Butane and propane cylinders should be kept as far from marked flame as possible and should never be left in the vicinity of hot material.

A blow-torch and hose, when not in use shall not be left unattended in any enclosed space even for short period, lunch breaks.

Alternatively, oxygen and acetylene connections shall be disconnected from the cylinders located outside closed space.

Closing of cylinder valves shall not be treated as disconnection. A safety cap must be securely screwed on before any cylinder in moved and cylinders

must be given the standard test every two years. Oxygen and combustible gases should not be stored together. Oxygen should never be used for the purpose of cleaning fume or other blowing

purpose. Cylinders should not be allowed to come into contact with electrical apparatus or live

wire. Gas cylinders should be painted in different colors according to it’s contained. Broken cylinder gauge shall not be used. Fire extinguisher shall be provided in front of gas storage room and welding & cutting

job is performed. Specially designed and tested man cage will be used for lifting cylinder.

6.12 Electrical Hand Tools All temporary electrical installations supplying electricity to any portable electrical

equipment shall be provided by effective earth leakage circuit breakers with a tripping current of not more than 30 mA.

All electrical hand held tools used inside the confined spaces must be operated at a voltage not exceeding a direct current (DC) 110 volts.

All plugs and sockets used for connecting any electrical equipment shall be of heavy-duty industrial plugs.

All electrical hand tools and equipment, including wires and cables must be properly insulated with no exposed wires or parts.

All wire and cable connections must be properly joined with cable or wire connectors. Use Annex-1E electrical safety inspection check-list during safety inspection/audit.

6.13 Scaffolding All scaffolds must be erected and modified by qualified scaffold erectors and supervised

by a qualified scaffold erector supervisor. During the erection, dismantling or alteration of a scaffold, A scafftag “Scaffold Not

Safe for Use” shall be placed on the uncompleted scaffold. All affected areas beneath the scaffold under erection or dismantling shall be

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 26 of 41

cordoned off with suitable warning barricades. Upon the completion of the scaffold, the scaffold Supervisor will certified the scaffold is

safe for use and put up the green scafftag indicating “Safe for Use” and remove any warning barricades.

The scaffold must be re-certified by the scaffold supervisor after every seven days and the date of the re-certification must be recorded on the scafftag.

No unauthorised dismantling, alteration or erection of a scaffold is permitted. All scaffolds shall have proper handrails, closely boarded flooring planks and safe

means of access ladders. Follow Checklist enclosed in Annexure –1D

6.14 Lifting Equipment/Appliances All lifting equipment/appliances such as chain blocks, lever blocks, slings, etc. shall be

registered with L&T’s Tool store with the valid test certificates. All lifting equipments/ appliance to be used shall be visually inspected for wear, tear and

defects prior to usage as per Annex-14A crane inspection check list and report shall be maintained as per Annex-14B

Safe Working Load (SWL) must be indicated on all the lifting equipment / appliance and these SWL must not exceeded at all times.

Daily inspections will be carried out by the Crane Operator, with the aid of a checklist, on the cranes.

All lifting equipment/appliance shall be in accordance to lands of the rule.

6.15 Rigging and Lifting All lifting shall only be rigged and lifted with an approved lifting equipment/appliance. All loads shall be properly rigged and checked by a qualified rigger to ensure that it is

not overloaded or off-balanced. During lifting, proper visual lifting signals or radio signals, when the view of crane

operator is obstructed, must be given. All lifting shall be properly planned and co-ordinated. The planning should include the

location of the pad-eyes, types of slings used, route of travel of the load, loading and unloading area, method of lifting / lowering etc.

During lifting, a tag line of adequate strength shall be used at all time to control the load. At no time should a load be lifted over any employees working in area and if avoidance

of such lifts is not feasible, the employees working in the area must be warned of the dangers and be cleared from the area until such lifts has been completed.

6.16 Confined Space Entry

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 27 of 41

No employee shall be allowed to enter a confined space without the approval of a valid Operations Permit / Confined Space Entry Permit.

The procedure for the application of the Operations Permit /Confined Space Entry Permit shall in accordance to the procedure stated in Section 8.4.

If a manhole needs to be opened prior to entry into the confined space or tank. A similar Operations Permit /Confined Space Entry Permit for opening manhole shall be applied as per Annex – 2D.

Upon opening of the manhole, the confined space will be checked by the Safety Personnel for any combustible gas, hazardous gas and sufficient oxygen content level.

Upon certifying sufficient oxygen level and free from combustible gas, the confined space shall be adequately ventilated by forced ventilation prior to the installation of temporary lighting.

The Operations Permit / Confined Space Entry Permit shall only be approved once the forced ventilation and the temporary lighting is installed and a re-test of the oxygen content and combustible gas is carried out.

Upon entering the confined space or tank, the permit must be displayed at the entry point. In addition, the boarding tag of the employees shall also be displayed on the Entry Tag Board at the entry point.

All employees entering the confined space or tank must carry a portable torch light with them in case of power failure resulting in a lighting black-out.

Upon leaving the confined space or tank, the employee must retrieve his permit and tag from the Entry Tag Board.

The manhole of the confined space or tank shall be appropriately covered.

6.17 Housekeeping: Work location, equipment and buildings are to be kept clean and orderly at all times.

Use Annex-1C Housekeeping checklist during Inspection / Audit. All work areas are to be free of dangerous projections or obstructions, and are to be

maintained free of rubbish, oil, grease and water. All toilet facilities, including hand basins must be maintained in a clean and hygienic

condition. No food must be kept in work area. All scrap and refuse bins must be clearly marked as to the type of the scrap or refuse

that must be deposited in them. Scrap and refuse bins must be removed by the subcontractor on a daily basis.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 28 of 41

Flammable waste must be stored in metal containers located at a safe distance from any possible ignition source.

Spillages of oil, grease etc., shall be cleaned up as soon as is practicable. All stacking of material must be made on ground that is level and all stacks must be neat

and stable. All circular objects must be suitably chocked to prevent them from rolling. Good Housekeeping prevents accidents.

6.18 Helicopter SafetyHelicopter provides unique service that is not typical to any other vehicle. Extreme caution must be used at all times when in or around a helicopter or it’s landing zone.

Loading / unloading precautions The landing zone should always be clear while the helicopter is landing or lifting off Wait for a direct command or signal from the helicopter pilot before approaching or

departing the craft. The helicopter must be firmly on the ground before you board or disembark

Always stay in pilot’s view when approaching or leaving a helicopter Always approach a helicopter from the FRONT – never approach a helicopter from

behind or walk under a tail boom or tail rotor Stay in bent-over position when approaching or departing from an idling helicopter When approaching or leaving a helicopter on downward slope or incline, make sure a

helicopter engine is turned off and the rotor blades are not turning When walking toward or away from a helicopter make sure you keep tight grip on all

carry-ons Advise the pilot of any magnetic or hazardous material you may be carrying before

boarding A pilot will provide a complete safety briefing before departing the landing zone.This will

include instructions for any special such as life raft or life vests The pilot is in-charge of the helicopter and its passengers follow his/her instruction

completely Do not throw anything out of helicopter. Damage to rotor system may occur. Carry on items must be secured before lift off.

Helicopter passenger safety Refueling a helicopter is the responsibility of aircraft company personnel Helicopter are not allowed to land on platform under radio silence No casual person on board while a helicopter is performing long life operation (Sling

load) or has an external hook or line attached to it.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 29 of 41

The only person allow to stand under a hovering helicopter is the person responsible for hooking or unhooking the load.

The platform must maintain communication with the pilot when hooking or unhooking a load

High static electrical charges can be build up in a helicopter, lines should be allowed to touch the ground before handling to eliminate the charge.

The length of the tag line should be short enough to prevent it from being drawn into the main or tail rotor blades.

6.19 Work over water Where work is done over or in close proximity to water for preventing workers from

falling into water by providing1. Fencing, safety nets and safety harnesses;2. Lifebuoys, life jackets and / or manned boats 3. Rescuer of workers in danger of drowning;4. Safe and sufficient transport;5. Protection against such hazards as reptiles and other animals.

Gangways, pontoons, bridges, footbridges and other walkways or work places over water should:a) Be sufficiently wide to allow safe movement of workers;b) Have level surfaces free from tripping hazards;c) Be adequately lit when natural light is insufficient;d) Prevent dislodgement by rising water or high winds;e) All deck, openings should be fenced.

Nobody should work alone on or above water.

6.20 Smoking No smoking shall be allowed on the project by all personnel, including Contractor’s

employees. The RCM shall designate, in consultation with the Safety Personnel and sub-contractors

Representative, a smoking area if necessary.

6.21 Radiography All radiography operations shall be carried out in accordance with the regulations laid

down by the Radiation Protective Inspectorate. All radiography equipment shall be adequately shielded. All radioactive sources shall be kept in their respective exposure devices, or sealed in

the source changer and stored in a safe storage pit.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 30 of 41

The radiography supervisor shall inform their radiation-licensed officer immediately of the loss or damage of the radioactive source, or the malfunction of equipment, resulting in a leak of contamination to the environment.

All personal involved in the industrial radiography shall be provided with the Thermoluminescent dosimeter (TLD) and a portable radiation monitor (meter) for the measurement of radiation in the affected area.

The radiography supervisor shall ensure that all-possible safety precautions and measures have been implemented, areas of operation have been cordon off and the standard radiation hazard signs are displayed.

The radiography supervisor shall ensure that all radioactive waste is disposed at an authorized dumping area.

6.22 Noise Identify & measure the noise at various site locations. Minimise noise exposure of personnel by engineering & administrating controls or by

providing PPEs. Noise level for continuous 8 hrs. exposure shall not exceed 90 dBA. For every rise in

5 dBA thereon, the exposure time of employees shall be reduced by half the value of exposure hours.

No exposure in excess of 115 dBA is to be permitted. To reduce the effects on local inhabitants, noise levels at the site boundary fences

shall be limited to 45 dBA.

6.23 Vehicle movement Driver with proper valid driving license shall only be allowed to drive the vehicle. Park vehicles only at designated places. Don't block roads to create hindrance for other

vehicles. Don’t overload the vehicle. Load should be properly secured. Obey speed limits and traffic rules laid down by L&T/ Client. Drive carefully during adverse weather and road conditions. While reversing the vehicles, reversed horn / help of another worker should be ensured

at all times. An unattended vehicle should have the engine switched off. Barriers/fixed stops should be provided for excavation/openings to prevent fall of

vehicle. The body of the tipper lorry should always be lowered before driving the vehicle off. Signs/signals/caution boards etc. should be provided on routes All vehicle and ships must have radios on board and will make hourly radio checks.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 31 of 41

No vehicle will be permitted to travel alone outside of radio range. Refueling of vehicles, ships and equipment shall be performed using appropriate

measurers to prevent spillage. No refueling will takes place with 100m of watercourse.

All vehicles will be maintained at designated place. Use annex-14C for inspection report. All vehicles should be equipped with the kit designed for response to small spills of fuel

and other materials. All spills are to be verbally reported to employer within one hour of spill occurring. Do not wash vehicles in surface water bodies or in streams. All washing shall occur at a

dedicated washing facility.

6.24 Offshore Safety(A) General Offshore Safety Guidelines On arrival at offshore everyone should be briefed about the safety rules to be followed at

offshore, evacuation system etc. All personnel should wear, helmet and shoes for personnel protection. In case of emergency, workers should follow instruction of Barge Master and follow emergency response procedure (Doc. No. )

In certain cases instructions may be given to abandon the offshore installation and evacuate the persons to safe location.

Offshore personnel must receive training for using life saving appliances and other personal survival techniques.

Radio and other communication facilities should be such to maintain contact with base all times.

(B) Loading /Unloading1. Working areas of the crane should be illuminated during night to avoid accident.2. Clear space should be available for despatch and receipt of load and, in

particular, basket transfer of passengers. Persons engaged in loading unloading of materials should be protected from failing into the sea.

3. Signal light should be fitted at the top of the jib.4. Crane hook should be fitted with safety latches.5. Experienced person should be engaged in operation of specific equipment like

winches, cranes etc.6. At least three cable turns shall always be there on the winch drum.7. Crane operation should be completely stopped during helicopter landing/taking

off.8. Except for helicopter landing deck, all decks, platforms, bridges, ladders should

have rigid and fixed guard-rails at least 1m high and should have one intermediate rail midway between the handrail and 100mm toe board.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 32 of 41

9. Wooden ladders shall not be used at offshore.

(C) Fire Prevention and Control Smoking should be restricted and no smoking area should be identified. Fire and smoke detectors i.e. ultraviolet heat thermal and smoke detector should be

function tested once in three months. Lightweight breathing system should be used. The fire control plan at offshore should reveal control station, fire alarms and fire

detectors, deluge valves and sprinkler, fire extinguishing appliances, fireman outfit and ventilation system.

(D) Life Saving Appliances Lifeboats with a speed of 6 knots and carrying capacity up to 50 persons are used. No. of life boats on one installation should have a capacity to accommodate twice the

number of persons onboard installation. Launching appliances and lifeboat equipment should be checked every week. Boat landing areas should be adequately illuminated. Life raft has no power and they rely on drift. Life jacket lifts the wearer after entering water. Life buoys are used to rescue persons if any person accidentally falls in the sea. All life saving appliances shall be inspected by competent authority once in a year. Every lifeboat shall be inspected once a week. Every lifeboat and life raft should be serviced once a year by a competent authority.

6.25 Fire Protection Smoke only in designated area. Know the fire alarm signal and how to turn on an alarm. Know where fire extinguishers are and how to use them. Know where is the emergency evacuation assembly point. Flammables shall be stored in properly labeled containers Accumulation of trash, oily rags, combustible materials and similar fire hazards of any

nature will not be permitted. All welding and cutting torches must be equipped with flash back arrester. Refueling equipment with the engine running is prohibited. Fire fighting equipment to be available all times at the construction site and office. There must be fire extinguisher, water hose, or other fire control equipment easily

accessible for each welding, cutting, burning or other such operation. During any hot work operation, a pressurized fire hose and 2 pieces of 10 kg Dry

Chemical Powder (DCP Type) fire extinguisher must be provided.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 33 of 41

6.26 Hazard Identification and Risk Assessment The hazard identification shall be conducted through careful examination of the actual

job task, which shall be performed. It shall identify the possible hazards encountered in performing the task.

Safety Department has conducted the hazard identification and subsequent risk assessment for all general construction activities after involving all concern persons as per Annexure 7. These individuals know the work process and are most familiar with and sensitive to the actual and potential hazards that might require PPE.

In general the Hazard identification and Risk Assessments of each task shall be evaluated for the following:a. Chemical (inhalation, ingestion and skin contact with dust, fumes, mists, gases,

vapors or liquids)b. Electricalc. Physical (heat, noise, vibration)d. Ergonomic stresses (repetitive motion, lifting, awkward posters)e. Falling/Moving/Flying objectsf. Radiationg. Lasers, infrared and ultraviolet lighth. Biologicali. Other (potential for falls, fire, explosion, pinching)j. Need for control measures (machine guarding, ventilation, isolation, worker

rotation, lifting devices and tool designs) to do the job safely.k. Need to follow procedures (Confined space entry etc.)

1. Site Safety officer shall correct any deficiency identified at any point of time immediately.

2. Any job task change for any process changes which may impact health or safety issues must be review by Safety Engineer, Safety coordinator, or designee.

3. Should an injury/accident occur while performing a job task, it shall be reported as described in section - 9 Assessment shall be reviewed and modified to reflect any additional safety precautions and/or PPE required performing job safely.

4. The result of Risk Assessment process will conclude whether the risk is tolerable or intolerable.

5. It is to be noted that any activities, which lead to fatality or serious injuries are considered as non- tolerable.

6. The identification of all OH & S hazards and Risk Assessment of all routine and non-routine activities are registered (Ref. Annex - 7) and updated as and when necessary by the SD at HQ. The report will indicate the control measures required to be implemented.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 34 of 41

7. The same shall be corrected for all active sites for effective action and further monitoring.

8. Hazard identification and Risk Assessment process will be repeated as and when any new activities take place, before they are put in practice.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 35 of 41

OH&S Hazards Assessment

HAZARDSASSESSMENT

HAZARDS MITIGATION

CONSTRUCTION

DebrisWaste material from the demolition / dismantling and form construction activities will be collected, stored and disposed off in accordance with the local environmental regulations.

Dust EmissionConcrete batching plant will be provided with PVC cover Sheets to minimize dust emission.

Dust Emission from Dust Emission from Movement of Vehicles

Dust prone area will be water sprayed to suppress dust emissions.

Waste Material fromWelding

Waste welding rods will be collected and disposed off according to local regulations.

Waste from Refractory & insulation Works

The waste materials arising out of refractory lining, like refractory bricks, wool blanket and cement would be collected separately and disposed off according to local regulations.

Effluent from Cleaning of Vehicles

Will be settled before disposal to remove grit. Effluent will be disposed in consultation with client.

Waste Packing Materials Will be stored and disposed off according to local regulations

House KeepingGood house keeping will be ensured through the Site Safety Officer / Supervisors

Air Emissions from Vehicles

Only vehicles complying with the local air emission levels will be used during construction.

Sand / Shot Blasting Waste

Will be collected and disposed off according to the local regulations.

PRE- COMMISSIONING

Spillage

1) Spillage of chemicals, greases and oils will be minimized

2) Loading of catalyst will be done without spillage.3) Wastes / Spillage on the paved area will be collected and

disposed in consultation with client’s Environment Management Department.

Disposal

1) Water used for hydro testing will be treated in the existing waste treatment facilities before disposal.

2) Floor washing waste will be treated in the existing waste treatment facility before disposal.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 36 of 41

6.27 Inspection/Auditing By Site Safety Officer / Safety Committee Member(s). Safety officer and/or member(s) of safety committee will carryout Safety

Inspection/audit. Decide on the time and date to carryout the inspection/audit as required preferably

along with the RCM / engineers / supervisors. Conducts physical inspection of the workplaces referring to the standard Safety

Checklist Annex-1B (General safety Inspection – Check List) & Annex-8 (Safety Audit –Check List) and also look for any other unspecified hazards.

Identifies all conformities and non- conformities in respect of physical conditions and practices and specifies them with positive / negative remark on the checklist as the case may be which is enclosed in annexure no. 8.

Circulate copy (duly signed by Safety officer) of the safety inspection / audit report to RCM and the concerned person for taking necessary corrective action.

Review and follow up implementation of the suggested safety measures and records of his findings on the site safety inspection report, which is enclosed in Annexure-9.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 37 of 41

7.0 MANAGEMENT OF CHEMICAL HAZARDS The chemicals defined under this procedure includes paints, solvent, thinners and other

hazardous chemicals. All paints and chemicals that are brought into the project site have to be accompanied

with a Material Safety Data Sheet. (MSDS). In the case of paints, solvents and chemicals, the vendors, supplier or contractors shall

compile the necessary MSDS based on individual projects. This MSDS for the particular project shall be submitted with a summary list of the

product name or code of the paints, solvents and chemicals, to safety department. Upon receipt of the MSDS, the safety department shall then check through the MSDS

and if necessary consults the section to understand the product safety requirement. Under no circumstances the chemical listed in annex10 shall be used for this project. In the case of paints, solvents or chemicals used on irregular basis, the vendor, supplier

or contractor shall declare at the guardroom the MSDS and the approved entry permit application form before entry into the yard.

All hazardous materials delivered into the yard shall be kept at the proper store under lock and the key kept by a competent person.

All paints and solvents and chemicals shall be kept by in a proper store and the issuance of all the paints, solvents or chemicals shall be properly controlled.

Upon completion of the job, all left over chemicals shall be removed from the site and returned to the store or brought out of the yard. All empty containers have to be discarded into the bins provided and brought down from the vessel for proper disposal at authorised disposal center.

The following precautions must be followed by the respective section supervisors, contractors, vendors or owner representative when using chemicals:- Check that all chemicals brought into the yard are as per MSDS submitted.- Ensure that the storage area has been cordoned off with warning signs

displayed.- Ensure that the chemicals are stored in a well ventilated are or open spaces.- Check that suitable fire extinguishers are provided at the storage area.- Ensure that all workers handling the chemicals followed strictly to the work

practices, procedure and safety rules.- Ensure that all workers handling the chemicals are equipped with proper

PPEs.- Ensure that all spillages are immediately cleaned up and the place is

rendered safe before commencing work.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 38 of 41

8.0 ACCIDENT / INCIDENT REPORTING AND INVESTIGATION An incident is defined as an event that results in;

- injury or bodily hurt to any employees or third party persons resulted in death permanent /partial or temporary disablement

- critical damages to equipment or installations;- Unplanned fires/explosions or spills/releases or substance which are

hazardous and /or potentially dangerous to environment. All personnel involved in project is responsible for reporting any incident in their working

area to their immediate superior, who shall then be responsible for notifying the RCM and Safety Personnel.

All incidents, which result in bodily hurt, shall be referred to Medical Centre for immediate treatment and thereafter referred for external medical attention, if necessary.

There shall be a close co-operation between management, supervisors, employees, contractors, sub-contractors and L&T Representatives to ensure that all incidents are reported and investigated and that corrective actions are taken.

All accidents/incident (minor / major or fatal) reports shall be submitted to the Safety and Environment section of Offshore works at 16-F, Maker Towers, Cuffe Parade, Mumbai-5 with a copy to the Regional Safety section, Bengal Chemicals Building, 502, Veer Savarkar Marg, Mumbai-25.

The internal accident assessment report shall be submitted to the Safety and Environment section, 16-F, Maker Towers, Cuffe Parade, Mumbai-5.

The respective supervisors of the incident shall investigate the incident with the assistance of the Safety Personnel.

In cases of a major catastrophic disaster, L&T’s Management and sub-contractors representatives shall jointly investigate the incident.

Any accidents shall be reported in the prescribed proforma of Accident Report (as per the Attachment-2 of Project Instructions) enclosed in Annexure-3C.

A Quarterly Accident return report shall be submitted to the safety section of ONGC in the prescribed proforma as enclosed in Annexure-3D.

Any accidents shall also be reported to Safety Control Department at L&T HO. The formats are as enclosed in Annexure – 3A/B, 4 & 5.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 39 of 41

9.0 MONTHLY STATISTICS REPORT Safety Officer of L&T shall write the correct Accident Data & man-hours after obtaining

relevant data from sub-contractor as per the standard format given in Annexure-6. SSO & RCM/RCC shall sign report. If RCM/RCC is not present, his representative will

have to sign and to be forwarded to client in the first week of every month.

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 40 of 41

10.0 SAFETY COMMUNICATION

10.1 Safety CommitteeSafety Committee shall be formed by L&T -Safety Officer in consultation with L&T-RCM after start of the project. The Safety Committee meeting shall be conducted once in every month. The safety committee members shall consist of following personnel:1. RCM from L&T.2. Safety Officer from L&T.3. Representative from each sub-contractors.4. Safety personnel from each sub-contractors.The minutes of meeting shall be recorded as per Annex-12A&B and shall be maintained at the site.

10.2 Education and Information

Safety orientation training:All the personnel going to offshore will be trained with Offshore Survival Training from recognised institute.The first safety orientation training shall be conducted for all the workmen at the site in the first week of actual start of the construction work. Report shall be maintained as per Annex-13.The next Safety Orientation Training program for the next batch of workmen, shall be finalised and conducted by L&T-Safety Officer in consultation with L&T-RCM as and when required.

Tool Box Talks

GeneralIt is mandatory for each employee to attend the Safety Orientation program on his first day of work. No worker will be permitted to work on the site without attending the safety orientation program.

The orientation will be given by the safety officer/supervisor or construction supervisor and must include following: Brief explanation of the program Safety policy Outlines of applicable regulation and requirements for the project

Larsen & Toubro Limited

Safety, Health & Environment Plan

Proj : PRP Project

Rev : 00

Date : 1st September, 05

Page : Page 41 of 41

Emergency procedure First Aid services Each worker's responsibilities

Every morning before start of work a safety toolbox talk is held by the supervisor with the foreman of each work place to instruct and discuss: Work procedures Safety instruction for using equipment, tools and job performance Particular hazardous conditions and precautions to be taken Workmen's health conditions and other required information

A written record will be maintained on all employees stating that they have received the safety training and fully understand the rules and regulations. This form will be signed by each employee and kept in file in the L&T safety department as per Annexure-11B. Refer Annex-11A for content of toolbox Talk.Periodic updated of the safety training procedure and requirements is provided for supervisors and foreman every two or three month.

10.3 Signs, signals and barricades When hazardous work is to be performed the appropriate signs and symbols will be

posted prior to starting work and will be removed or covered promptly when the hazards no longer exist.

Danger signs will be used only where an immediate hazard exists. Caution sign will be used only to warn against potential hazards or to caution against unsafe practices.

Accident prevention tags are used as a temporary means of warning employees of an existing hazard, such as defective equipment can be repaired or removed.

Refer Annex-15 for standard Safety signboards.

Warning barricades Warning barricades will be erected before work begins or as soon as specific hazard is

identified (in some situations a rigid guardrail will be needed) Warning barricades must be erected and maintained at least two (2) meters from the

edge of an excavation or opening.