LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21,...

24
LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003

Transcript of LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21,...

Page 1: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

LST Mechanical Design Review

Utility Routing, Cableways & Crate Locations

Peter KimOctober 21, 2003

Page 2: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 2

OVERVIEW• SPACE ISSUES

– Where Do All the Cables Go?– Cable Routing inside the Sextant– Cable Routing Around the Detector– Cable Routing to Outside Shielding Wall

WITHOUT DISTURBING OTHER COMPONENTS

• Some RPC Infrastructure Remains– Top/Bottom Sextants installed in 2004, Side Sextants

in 2005 – Cylindrical RPC & ENDCAP RPC Operational after

2005

Page 3: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 3

Current IFR/RPC System

• High Voltage– CAEN HV Supply in Elec. Hut outside the Shielding Wall– HV Distribution Boxes positioned around BABAR Detector– 8 kV HV Cables to RPC Modules behind the Corner Plates

• Gas System– Gas Manifold/Bubblers/Flowmeters in Racks above BABAR– Teflon/Polyflo Tubes feed RPC Modules behind the Corner

Plates

• Signal Readout– Preamps on RPC Modules – Twisted Pair Flat Ribbon Cable carries Signal to FEC in Racks

around BABAR Detector; Processed Signals go to DAQ via Optical Fibers

Page 4: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 4

RPC HV Cable Routing

Gas Supply

HV Cables

Drawing from R. Principe

Shielding Wall

Page 5: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 5

BABAR CABLE TRAYS

LST will use North Tray

TRAYS are Busy, but Space available for LST HV/Gas Lines

Page 6: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 6

RPC Gas Tubes

TEFLON Gas Supply Tubes TEFLON / POLYFLO Connections

Backward SideFront SideTEFLON

POLYFLO

Page 7: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 7

A Sextant full of RPC

From R. Boyce’sTalk this Morning

Page 8: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 8

LST High Voltage System• HV Distribution (Baseline Design)

– HV Supply located above Electronic Hut outside Shielding Wall– One HV Cable (10-wire or 20-wire Kerpen) for each LST Module– Total of 564 Cables (94 Cables in each Sextant)– No Distribution Boxes near BABAR: Long Cables (25-40 m) from HV Supply to LST Modules

• Cable Trays & Cableways– HV Cables need to be Separated from Other Supply Lines– New Cable Tray under the Shielding Wall– New Cableways to run HV Cables Around BABAR Detector

• Inside Each Sextant– Top/Bottom Sextants: Use Open Space Either Side of CENTER PLATE – Side Sextants: Use existing RPC Signal Cable Box in the Middle

Page 9: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 9

High Voltage Supply

BABARDetector

Electronic Hut

RPC HV Supply

LST HV Supply

Page 10: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 10

BABAR Viewed From South

Center Plate

Corner Plate

Side PlateRemoved

Page 11: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 11

Closeup View of Side Sextant

Side Plate Goes Back in Here

Page 12: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 12

Open Box

Signal Readout Cable Box(2” Wide, 5” Deep)

Signal Readout Cable Box(2” Wide, 5” Deep)

Space Available forLST HV/Gas Lines(6” Wide, 5” Deep)

Page 13: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 13

High Voltage Cable

KERPEN 6 kV HV Cable

Zero Halogen, Frame Retardant Polymer Sheath

Diameter: 9.1 mm for 10-conductors 10.7 mm for 20-conductors

Minimum Bending Radius = 6 x Diameter Tinned copper, Flexible stranded Conductors (0.16 mm diameter)

Page 14: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 14

LST Gas System• Gas Distribution

– Reuse Rack space on Top of BABAR, currently occupied by RPC Crates

– New Gas Manifolds, but Reuse RPC Bubblers/Flow meters– LST Gas is NON-FLAMMABLE

• Reuse RPC Teflon Tubes– Need to install 60 more lines (228 for RPC; 288 for LST)– RPC Tubes going to the Front Side need to be Rerouted (LST Gas Tubes go to Backward Side only)

• Polyflo Tubing– Teflon/Polyflo Connections – Two Bundles of 24 Polyflo Cables (Input/Output Lines) enter Sextants in the Middle

Page 15: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 15

HV-GAS Supply for LST

Page 16: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 16

LST Electronics Readout

• BASELINE DESIGN– Z-Strip Signal Read out from the Back Side 1152 Channels per Sextant– Phi Signal Read out from the Front Side 758 Channels per Sextant– AMPHENOL Twisted/Flat Readout Cable– Preamps on FEC, Not on the LST Module

– 7 Crates for Z Signals and 6 Crates for Phi Signals– Output Digital Signal to DAQ via Optical Fibers

• CRATE Features– VME Standard 6U High (26.5 cm); 55 cm Wide, 55 cm Deep– 7 Crates for Z Signals and 6 Crates for Phi Signals– All Input/Output Cables are Connected from the Front

Page 17: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 17

Amphenol Readout Cable

MicroribbonTwitst/Flat Cable

17 Twisted Pairs Shielded & Jacketed

Diameter at Round Section: 0.75 cm

48 Phi Cables / Sextant 72 Z Cables / Sextant

Enough Room in Two 5 cm x 12 cm Cable Boxes / Sextant

Page 18: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 18

Examples of Conduits for Phi Signal Readout

Page 19: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 19

Rack Locations

• Keep the Racks Close to LST Modules– Deterioration of Raw Signal over Distance– Higher Background Noise Pick Up over Distance

• Space Considerations– Allow Access to Other Parts of BABAR Detector, Endcap

Doors, Earthquake Braces, etc.– Cooling Fans / Air Circulation– Removal and Insertion of FEC Cards

Page 20: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 20

Electronic Rack Locations on the Forward Side

Drawing fromR. Principe

Page 21: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 21

Electronic Rack Locations on the Backward Side

Page 22: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 22

Space Check with Mockup Crates

Page 23: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 23

Installation Schedule

• Racks & Fixtures Design, Fabraication, and

Installation before July Shutdown

• New Cable Trays and Conduits installed while

RPCs are being removed

• GAS Tubes and HV Cables will be laid down One

Layer at a time, following LST module install schedule

Page 24: LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.

October 21, 2003 P.Kim 24

SUMMARY

• NO SPACE PROBLEM EXPECTED UNDER BASELINE DESIGN

• LOTS OF WORK TO DO, BUT WILL BE ABLE TO MEET IFR INSTALL SCHEDULE FOR 2004/2005