LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21,...
-
Upload
samara-harbour -
Category
Documents
-
view
217 -
download
2
Transcript of LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21,...
LST Mechanical Design Review
Utility Routing, Cableways & Crate Locations
Peter KimOctober 21, 2003
October 21, 2003 P.Kim 2
OVERVIEW• SPACE ISSUES
– Where Do All the Cables Go?– Cable Routing inside the Sextant– Cable Routing Around the Detector– Cable Routing to Outside Shielding Wall
WITHOUT DISTURBING OTHER COMPONENTS
• Some RPC Infrastructure Remains– Top/Bottom Sextants installed in 2004, Side Sextants
in 2005 – Cylindrical RPC & ENDCAP RPC Operational after
2005
October 21, 2003 P.Kim 3
Current IFR/RPC System
• High Voltage– CAEN HV Supply in Elec. Hut outside the Shielding Wall– HV Distribution Boxes positioned around BABAR Detector– 8 kV HV Cables to RPC Modules behind the Corner Plates
• Gas System– Gas Manifold/Bubblers/Flowmeters in Racks above BABAR– Teflon/Polyflo Tubes feed RPC Modules behind the Corner
Plates
• Signal Readout– Preamps on RPC Modules – Twisted Pair Flat Ribbon Cable carries Signal to FEC in Racks
around BABAR Detector; Processed Signals go to DAQ via Optical Fibers
October 21, 2003 P.Kim 4
RPC HV Cable Routing
Gas Supply
HV Cables
Drawing from R. Principe
Shielding Wall
October 21, 2003 P.Kim 5
BABAR CABLE TRAYS
LST will use North Tray
TRAYS are Busy, but Space available for LST HV/Gas Lines
October 21, 2003 P.Kim 6
RPC Gas Tubes
TEFLON Gas Supply Tubes TEFLON / POLYFLO Connections
Backward SideFront SideTEFLON
POLYFLO
October 21, 2003 P.Kim 7
A Sextant full of RPC
From R. Boyce’sTalk this Morning
October 21, 2003 P.Kim 8
LST High Voltage System• HV Distribution (Baseline Design)
– HV Supply located above Electronic Hut outside Shielding Wall– One HV Cable (10-wire or 20-wire Kerpen) for each LST Module– Total of 564 Cables (94 Cables in each Sextant)– No Distribution Boxes near BABAR: Long Cables (25-40 m) from HV Supply to LST Modules
• Cable Trays & Cableways– HV Cables need to be Separated from Other Supply Lines– New Cable Tray under the Shielding Wall– New Cableways to run HV Cables Around BABAR Detector
• Inside Each Sextant– Top/Bottom Sextants: Use Open Space Either Side of CENTER PLATE – Side Sextants: Use existing RPC Signal Cable Box in the Middle
October 21, 2003 P.Kim 9
High Voltage Supply
BABARDetector
Electronic Hut
RPC HV Supply
LST HV Supply
October 21, 2003 P.Kim 10
BABAR Viewed From South
Center Plate
Corner Plate
Side PlateRemoved
October 21, 2003 P.Kim 11
Closeup View of Side Sextant
Side Plate Goes Back in Here
October 21, 2003 P.Kim 12
Open Box
Signal Readout Cable Box(2” Wide, 5” Deep)
Signal Readout Cable Box(2” Wide, 5” Deep)
Space Available forLST HV/Gas Lines(6” Wide, 5” Deep)
October 21, 2003 P.Kim 13
High Voltage Cable
KERPEN 6 kV HV Cable
Zero Halogen, Frame Retardant Polymer Sheath
Diameter: 9.1 mm for 10-conductors 10.7 mm for 20-conductors
Minimum Bending Radius = 6 x Diameter Tinned copper, Flexible stranded Conductors (0.16 mm diameter)
October 21, 2003 P.Kim 14
LST Gas System• Gas Distribution
– Reuse Rack space on Top of BABAR, currently occupied by RPC Crates
– New Gas Manifolds, but Reuse RPC Bubblers/Flow meters– LST Gas is NON-FLAMMABLE
• Reuse RPC Teflon Tubes– Need to install 60 more lines (228 for RPC; 288 for LST)– RPC Tubes going to the Front Side need to be Rerouted (LST Gas Tubes go to Backward Side only)
• Polyflo Tubing– Teflon/Polyflo Connections – Two Bundles of 24 Polyflo Cables (Input/Output Lines) enter Sextants in the Middle
October 21, 2003 P.Kim 15
HV-GAS Supply for LST
October 21, 2003 P.Kim 16
LST Electronics Readout
• BASELINE DESIGN– Z-Strip Signal Read out from the Back Side 1152 Channels per Sextant– Phi Signal Read out from the Front Side 758 Channels per Sextant– AMPHENOL Twisted/Flat Readout Cable– Preamps on FEC, Not on the LST Module
– 7 Crates for Z Signals and 6 Crates for Phi Signals– Output Digital Signal to DAQ via Optical Fibers
• CRATE Features– VME Standard 6U High (26.5 cm); 55 cm Wide, 55 cm Deep– 7 Crates for Z Signals and 6 Crates for Phi Signals– All Input/Output Cables are Connected from the Front
October 21, 2003 P.Kim 17
Amphenol Readout Cable
MicroribbonTwitst/Flat Cable
17 Twisted Pairs Shielded & Jacketed
Diameter at Round Section: 0.75 cm
48 Phi Cables / Sextant 72 Z Cables / Sextant
Enough Room in Two 5 cm x 12 cm Cable Boxes / Sextant
October 21, 2003 P.Kim 18
Examples of Conduits for Phi Signal Readout
October 21, 2003 P.Kim 19
Rack Locations
• Keep the Racks Close to LST Modules– Deterioration of Raw Signal over Distance– Higher Background Noise Pick Up over Distance
• Space Considerations– Allow Access to Other Parts of BABAR Detector, Endcap
Doors, Earthquake Braces, etc.– Cooling Fans / Air Circulation– Removal and Insertion of FEC Cards
October 21, 2003 P.Kim 20
Electronic Rack Locations on the Forward Side
Drawing fromR. Principe
October 21, 2003 P.Kim 21
Electronic Rack Locations on the Backward Side
October 21, 2003 P.Kim 22
Space Check with Mockup Crates
October 21, 2003 P.Kim 23
Installation Schedule
• Racks & Fixtures Design, Fabraication, and
Installation before July Shutdown
• New Cable Trays and Conduits installed while
RPCs are being removed
• GAS Tubes and HV Cables will be laid down One
Layer at a time, following LST module install schedule
October 21, 2003 P.Kim 24
SUMMARY
• NO SPACE PROBLEM EXPECTED UNDER BASELINE DESIGN
• LOTS OF WORK TO DO, BUT WILL BE ABLE TO MEET IFR INSTALL SCHEDULE FOR 2004/2005