Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study...

37
Lonmin Plc INTERIM RESULTS 2008

Transcript of Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study...

Page 1: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Lonmin Plc INTERIM RESULTS 2008

Page 2: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

2

Today’s Presentation

• Overview

• Financial results

• Operational Excellence

• Safety

• Recent Performance

• Mining Review

• Growth

• Sustainability

• Summary

Page 3: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

3

Overview

• Record financial results in a strong price environment:

• Revenue up 44% to US$907 million

• Underlying EBIT up 63% to US$371 million

• Underlying earnings per share up 63% to 132.5 cents

• Safety performance continues to improve

• Refined production of 282,650 ounces of Platinum and 536,128 ounces of total PGMs

• Production impacted by four day Eskom power outage, safety shutdowns and absenteeism

• New mining team embedded and implementing plans to optimise mining performance

• Steady progress on development projects:

• Completion of pre-feasibility studies for Limpopo phase 2 and Pandora

• Significantly increased attributable indicated resource for southern section of Akanani to 8.8 million PGM ounces (3 PGE+Au)

• Interim dividend increased by 7% to US$0.59 per share

Page 4: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

4

Power

• Four day shutdown at end of January – loss of 15,000 saleable ounces of Platinum

• Operated at 90% of normal consumption for February and March

• Eskom confirmed increased limit to 95% on 24 April, which improves operational flexibility

• Implemented active energy consumption management across the operations with concentrator maintenance planned to align with peaks in power use

• Rolled out energy saving campaigns business wide

• Steep electricity price increases are likely for industry

• Investigating other longer term options for provision of power

• Eskom to review provision of power for industry growth projects in June

Page 5: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

5

Markets

• Future PGM market fundamentals look sound

• Security of power and water supply will be fundamental for industry growth

• Global Emissions Legislation agenda and robust Far Eastern economic growth will drive demand

• Possible demand issues:

• Rhodium – Palladium substitution

• Thrifting and inter-PGM metal substitution

• Potential shrinkage of Platinum jewellery sector

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

Q107 Q207 Q307 Q407 Q108 Q208

$ pe

r oz

Lonmin PGM Basket Price

Page 6: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Financial Results

Alan FergusonChief Financial Officer

Page 7: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

7

Summary of Results

6 months to31 March 2008

US$m

6 months to31 March 2007

US$m

Variance(%)

Revenue 907 631

229

228

36.1

132

235

36%

(2.0)

81.5

44

EBIT 368 61

Underlying EBIT 371 63

Underlying EBIT margin (%) 40.9 13

Profit before tax 396 200

Underlying profit before tax 399 70

Underlying tax rate 35% -

Basic EPS (cents) 181.1 -

Underlying EPS (cents) 132.5 63

Page 8: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

8

EBIT Variances

(1)

(22)

(134) (3)

229

239

45 15

368

228

371

100

150

200

250

300

350

400

450

500

550

H107Reported

Special H107Underlying

PGM Price Base Metals PGMVolume

PGM Mix Costs H108Underlying

Special H108Reported

$mill

ion

Page 9: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

9

Year on Year Cost Variance Analysis

536 16 3 87

6 10 12 402

100

150

200

250

300

350

400

450

500

550

600

H107 underlyingcosts

SHEC Exploration andBusiness

Development

Shared Services ProductiveCosts

Depreciation andAmortisation

ForeignExchange

H108 underlyingcosts

$m

Page 10: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

10

Cost per PGM Ounce Sold

2008 2007 Variance(Rand / oz) (Rand / oz) (%)

Group:

Mining - Marikana 3,247 2,134 52%Mining - Limpopo 6,125 4,405 39%Mining (weighted average) 3,366 2,270 48%Concentrating - Marikana 638 408 56%Concentrating - Limpopo 2,193 1,171 87%Concentrating (weighted average) 684 454 51%

Process Division 604 722 (16)%Shared Business Services 838 685 22%Stock movement (489) (83)

C1 cost per PGM ounce sold before base metal credits 5,003 4,048 24%

Base metal credits (493) (867)

C1 cost per PGM ounce sold after base metal credits 4,510 3,181 42%Amortisation 496 367 35%

C2 cost per PGM ounce sold 5,006 3,548 41%

6 months to 31 March

Page 11: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

11

Free Cash Generated

6 months to31 March 2008

US$m

6 months to31 March 2007

US$m

Operating Profit 368 229

Working Capital Depreciation and other items

(100)47

4449

Net cash inflow from operating activitiesNet interest, finance costs and tax paid

315(156)

322(160)

Trading cash flowCapital expenditureProceeds from disposal of assets held for saleMinority dividends paid

159(139)

1(51)

162(105)

3(21)

Free cash flow (30) 39

Closing net debt (506) (665)

Page 12: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Operational Excellence

Page 13: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

13

Continuing Safety Improvement

Industrial Fatalities

FY04 8

FY05 6

FY06 6

FY07 3

HY08 1

0

5

10

15

20

25

HY04 HY05 HY06 HY07 HY080

50

100

150

200

250

300

350

400

450

LTIF on HY cumulative basis (per million man-hours worked) Severity Rate on HY basis (number of days lost per million man hours worked)

Lost

Tim

e In

jurie

s pe

r milli

on m

an h

ours

wor

ked

Severity Rate

Page 14: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

14

Marikana – Underground Production

N.B. Excludes production from Pandora Joint Venture ground

0

500

1000

1500

2000

2500

3000

3500

Q106 Q206 Q306 Q406 Q107 Q207 Q307 Q407 Q108 Q208

UG

Ton

nes

Hoi

sted

(000

's)

22.533.544.555.56

UG

Mill

ed H

ead

Gra

de (5

PGE+

Au)

g/t

Underground Tonnes Mined Underground Milled Head Grade

Page 15: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

15

Mechanised Performance

0

50

100

150

200

250

300

350

Q107 Q207 Q307 Q407 Q108 Q208

Tonn

es m

ined

(000

's)

0

2

4

6

8

10

12

14

% o

f und

ergr

ound

pro

duct

ion

Tonnes Mined % of Marikana underground prod

Page 16: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

16

Marikana Concentrators

0

50

100

150

200

250

300

Q106 Q206 Q306 Q406 Q107 Q207 Q307 Q407 Q108 Q208

Sale

able

Met

al in

Con

cent

rate

(Pt o

z - 0

00's

)

60

65

70

75

80

85

Rec

over

y R

ate

(%)

Saleable Metal in Concentrate (Pt oz) Underground Recovery Rate (%)

Page 17: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

17

Smelter & Refineries

Refined Metal Production• Smelter

• Number One furnace inspection and repair successfully completed

• Further upgrade planned for Q109

• Refineries

• Continuing upgrade of BMR to reach consistent throughput of 37 tonnes per day

• PMR continues to perform well

• 70,000 Pt oz stock build-up in H1 – anticipate release in H2

0

100

200

300

400

500

600

Q106 Q206 Q306 Q406 Q107 Q207 Q307 Q407 Q108 Q208

Prod

uctio

n (o

z - 0

00's

)

Pt Pd Au Rh Ruth Iri

Page 18: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Mining Review

Chris SheppardExecutive Vice President, Mining

Page 19: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

19

The Right Senior Team In Place

• Frank Russo-Bello – Vice President, Conventional - joined from AngloGold Ashanti

• Dave Wright – Vice President, Mechanised - formerly Mine Manager at Rio Tinto’s Palabora mine

• Recruiting new Vice President, Mining Services

• Mark Munroe – Senior Manager, Mining - joined from DRDGold

• Christo Horn, Senior Manager, Mechanised Operations - formerly with Amplats

• Complementing existing team

Page 20: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

20

SWOT Analysis

Strengths

• Relatively shallow versus peers

• Up and down dip mining method

• Experienced conventional workforce

• Leading safety performance

• New committed and experienced senior leadership team

Weaknesses

• Life of mine plan has scope for optimisation

• Planning, production control and forecasting systems

• Ore reserve development in certain areas

• Communication with workforce

• Management of labour attendance

Threats

• Interruption of utility supply

• Skills shortage and retention of critical skills

• Implementation of mechanisation

• Cost escalation

Opportunities

• Develop site specific mining extraction strategy

• Optimise ore body from half level perspective

• Increased productivity and cost reduction

• Mechanisation

• Enhance union relationship

Fundamentally high quality ore body – lots of opportunity for improvement

Page 21: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

21

Optimised Mining Extraction Strategy

• Developing sustainable, site specific, mining extraction strategy

• Optimising NPV and cash flow

• Provide foundation for complementary concentrator and processing strategy

• Fully optimised plan to be completed by end of Q209

Page 22: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

22

Increase Productivity and Reduce Costs

• Optimisation of half levels

• Conventional “recipe” completed and half levels mapped

• Optimisation fully completed over next 24 months

• Re-focussing on development

• K3 will deploy HPE drill rigs in May

• MME drill rigs in place at Rowland

Page 23: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

23

• Project Bokamoso at K3 implemented to determine best practice completes end FY08

• Best practice rolled out mine wide end FY09

• New short term planning protocol being rolled out across the operations

Upgrade Management Operating System

Page 24: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

24

• Introduction of critical skills crews to provide flexibility

• Communication campaign

• Enforcement of disciplinary action

• Already seeing favourable trends in attendance and production

Address Non-Attendance

Page 25: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

25

Mechanisation

• Focus on improvement opportunities in H2

• Better planning and forecasting of ramp up schedule per suite

• Optimisation of mechanised half levels

• Match of operator availability to arrival of suites

• Enhanced training to develop new operators in house

• Equipment availability and maintenance

• Continuous operations

• Creation of Mechanisation Centre of Excellence to develop best practice and ensure implementation of lessons learned

Page 26: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

26

Mining Review - Summary

• Substantial upside potential from Marikana and Limpopo ore bodies

• Aligned and committed senior team in place

• Clear process and plan in place to deliver productivity and cost improvements

• Mechanisation is the future for Lonmin

Page 27: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Growth

Brad MillsChief Executive Officer

Page 28: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

28

The Future of Lonmin in South Africa

Limpopo

Marikana

Akanani

N 0 100 km

Northern Operations

• Continued progress with Akanani and Limpopo

• Developing plans for smelting and refining complex to service Akanani and Limpopo

Marikana Operations

• Starting to transition from shallower to deep shafts

• Options for optimisation of smelting, refining & concentrating capacity

Pandora

Akanani Resources

Resources 22.0

All Resources & Reserves figures are on a Total Attributable basis in million PGM ounces (3PGE + Au)

44.5Reserves

102.3Resources

Marikana Resources & Reserves

44.5Reserves

102.3Resources

Marikana Resources & Reserves

0.04Reserves

7.9Resources

Pandora Resources & Reserves

0.04Reserves

7.9Resources

Pandora Resources & Reserves

6.7Reserves

24.1Resources

Limpopo Resources & Reserves

6.7Reserves

24.1Resources

Limpopo Resources & Reserves

Page 29: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

29

Progress Update and Key Milestones

Marikana• K3 UG2 sub-decline project approved by Board• May 2008 – Complete shaft equipping at K4, to be followed by ore reserve development• Hossy and Saffy ramp-up continues• Q4 2008 – BMR expansion to 37 tonnes per day to be completed

Limpopo Expansion• April 2008 – Completed pre-feasibility study • May 2008 – MOA signing for provision of water to the project • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month• Timing of project dependant on feed required for optimised smelting and refining capacity

Akanani• May 2008 – MOA signing for provision of water to the project • Q4 2008 – Pre-feasibility study to be completed

Page 30: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Sustainability

Page 31: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

31

Sustainability Strategy

Lonmin and communities uniting to liberate the potential of current and future generations to experience quality of life

• Focusing on:

• alleviating poverty

• creating flexible housing

• improving the wellness of our employees

• building an education system

• empowering a flourishing local economy

• creating respect for the natural environment

• empowering communities to solve problems through self-governance

• supporting the development of art & culture

Page 32: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

32

H1 Progress

• Education• Sanitation systems in 3 schools benefiting 1,500 learners

• Supporting nutrition programme in 15 schools

• Health• Over 8,000 employees tested for HIV through the VCT

programme

• 885 employees now receiving ART treatment

• 34 workplace and 56 community based HIV/Aids peer educators now trained

• Housing• Hostel conversions continue – 12% now converted

• Final planning permission to build 500 new homes in Marikana

• Community• Supplier development – 13 contracts awarded to date with

value of US$25 million

Page 33: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

33

Summary

Creating a culture of operational excellence: • High quality ore bodies in existing operations – abundant opportunities for improvement

• Remain focussed on improving operational performance

• Continued implementation of mechanisation strategy

Capturing and building growth: • Continuing to shape the future of Lonmin in South Africa

• Optimising mining performance at Marikana

• Developing significant Northern Bushveld presence in longer term

• Determining size of processing capacity to match mine growth

• Future PGM market fundamentals look sound and will support significant additional growth

Building long term sustainability: • Progress made in education, health, housing and supplier development

FY2008 sales guidance of 775,000 Platinum ounces

Page 34: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Questions

Page 35: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Appendix

Page 36: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

36

Unit Cost and EBIT Reconcilliation

Total revenue $m 907

Absorbed operating costs:

Normal operations ("C1") PGMs sold K oz 524Cost per ounce (gross) R/oz (5,003)Cost Rm (2,624)

Other operations PGMs sold K oz 33(Toll-refined and joint venture) Cost per ounce (gross) R/oz (9,892)

Cost Rm (325)

Total Total PGMs sold K oz 557Avg Cost per ounce (gross) R/oz (5,291)Total absorbed cost Rm (2,949)

FX R:$ 7.04Total absorbed cost $m (419)

Unabsorbed costs:Operating overheads $m (19)Corporate $m (36)Exploration $m (16)Total unabsorbed costs $m (71)

Operating amortisation $m (46)

EBIT (underlying) $m 371

Page 37: Lonmin Plc Morgan Stanley Basic Metals Conference 2005 • Q2 2010 – Complete feasibility study looking at mine producing 360,000 tonnes per month • Timing of project dependant

Interim Results - 2008

37

Disclaimer

• This presentation, which is personal to the recipient and has been issued by Lonmin.

• This presentation includes forward-looking statements. All statements other than statements of historical fact included in this announcement, including without limitation those regarding Lonmin's plans, objectives and expected performance, are forward-looking statements. Lonmin has based these forward-looking statements on its current expectations and projections about future events, including numerous assumptions regarding its present and future business strategies, operations, and the environment in which it will operate in the future.

• Forward-looking statements generally can be identified by the use of forward-looking terminology such as 'ambition', 'may', 'will', 'could', 'would', 'expect', 'intend', 'estimate', 'anticipate', 'believe', 'plan', 'seek' or 'continue', or negative forms or variations of similar terminology. Such forward-looking statements involve known and unknown risks, uncertainties, assumptions and other factors related to Lonmin, including, among other factors: (1) material adverse changes in economic conditions generally or in relevant markets or industries in particular; (2) fluctuations in demand and pricing in the mineral resource industry and fluctuations in exchange rates; (3) future regulatory and legislative actions and conditions affecting Lonmin's operating areas; (4) obtaining and retaining skilled workers and key executives; and (5) acts of war and terrorism.

• By their nature, forward-looking statements involve risks, uncertainties and assumptions and many relate to factors which are beyond Lonmin's control, such as future market conditions and the behaviour of other market participants. Actual results may differ materially from those expressed in forward-looking statements. Given these risks, uncertainties, and assumptions, you are cautioned not to put undue reliance on any forward-looking statements. In addition, the inclusion of such forward-looking statements should under no circumstances be regarded as a representation by Lonmin that Lonmin will achieve any results set out in such statements or that the underlying assumptions used will in fact be the case.

• Other than as required by applicable law or the applicable rules of any exchange on which Lonmin's securities may be listed, Lonmin has no intention or obligation to update or revise any forward-looking statements included in this presentation after the publication of this presentation.

• This presentation is for information only and does not constitute or form part of any offer or invitation to sell, or any solicitation of any offer to purchase, any shares in Lonmin or any other securities, nor shall it or any part of it nor the fact of its distribution form the basis of, or be relied upon in connection with, any contract or investment decision related thereto.