Longwall Improvement at Kestrel Mine

9
Longwall Improvement at Kestrel Mine 2010 Longwall Conference, Hunter Valley 2010 Longwall conference slides.pdf Brief personal profile For those of you I have not met my name is John Coughlan and I am the acting General manager of operations at Kestrel mine. I am privileged to be here today to address this conference. Introduction Kestrel mine is located 50km north of Emerald in central Queensland’s Bowen basin. The mine was purchased by Rio Tinto in 1999 and is one of 6 mines operated by Rio Tinto Coal Australia (RTCA). The German Creek seam is mined and mix of predominantly coking and thermal coal is produced. We are currently in the construction phase of an extension to the mine, to be known as Kestrel south Kestrel is the only underground coal mine in the RTCA suite of mines. Presently there are 3 development sections, a long wall section, coal clearance to a 3 stage wash plant and a rail load out. We ship approximately 4 million tonnes per year. The facility is self contained and can be illustrated in a typical longwall mine value chain. At Kestrel we are fortunate in that we have 2 available longwall systems each comprising a Bucyrus shearer, 146 x 860t supports, AFC, BSL and monorail and each has a name plate capacity of 2,500 tonnes per hour. These components are of various ages however the supports are original, approaching 20 years in age.

Transcript of Longwall Improvement at Kestrel Mine

Page 1: Longwall Improvement at Kestrel Mine

Longwall Improvement at Kestrel Mine

2010 Longwall Conference, Hunter Valley

2010 Longwall

conference slides.pdf

Brief personal profile

For those of you I have not met my name is John Coughlan and I am the acting General

manager of operations at Kestrel mine. I am privileged to be here today to address this

conference.

Introduction

Kestrel mine is located 50km north of Emerald in central Queensland’s Bowen basin. The

mine was purchased by Rio Tinto in 1999 and is one of 6 mines operated by Rio Tinto Coal

Australia (RTCA). The German Creek seam is mined and mix of predominantly coking and

thermal coal is produced. We are currently in the construction phase of an extension to the

mine, to be known as Kestrel south

Kestrel is the only underground coal mine in the RTCA suite of mines. Presently there are

3 development sections, a long wall section, coal clearance to a 3 stage wash plant and a

rail load out. We ship approximately 4 million tonnes per year. The facility is self contained

and can be illustrated in a typical longwall mine value chain.

At Kestrel we are fortunate in that we have 2 available longwall systems each comprising a

Bucyrus shearer, 146 x 860t supports, AFC, BSL and monorail and each has a name plate

capacity of 2,500 tonnes per hour. These components are of various ages however the

supports are original, approaching 20 years in age.

Page 2: Longwall Improvement at Kestrel Mine

In 2007 an improvement programme for the Kestrel mine was initiated. The programme

concentrated on three broad areas of development, longwall and CHPP. Given this is the

longwall conference we will take this opportunity to discuss the longwall improvement.

Context

In 2007 there were several factors that provided the impetus, or “burning platform”, to

improvement.

The mine recently had a new general manager appointed who had some firm views on

longwall operations; the longwall should provide the “drumbeat for the operation”, the

longwall should be treated as fixed plant not mobile and finally lean thinking and tools could

be applied to better manage process associated with longwall activities.

At this time Rio Tinto was undergoing a global change to the way assets are managed and

introduced a number of asset management protocols. In the first instance these protocols

were to drive a change to planned maintenance and increased reliability as a platform to

then initiate further refinement and optimisation of maintenance practices. Increased

reliability will then feed into higher operational hours.

Rio Tinto was completing the feasibility and seeking approval for funds for the Kestrel Mine

Extension. This is an ambitious project utilising a state of the art 375m longwall to underpin

a high production low cost mine at Kestrel into the future. Achieving operating parameters

such as cut hours and availability assigned to the new system while operating the existing

system would underpin confidence in the investment decision.

An assessment was carried out with the help of consultants, Deloittes. This assessment

identified the broad areas of opportunity available to deliver improvement and provided a

framework for the improvement initiatives.

Safety

First and foremost, to be judged successful any change introduced for improvement has to

deliver safety improvement.

Page 3: Longwall Improvement at Kestrel Mine

Kestrel continues to set challenging objectives with regard to the health and safety of its

employees. We do this as a part of the industry in Queensland and as part of the broader

Rio Tinto group.

We strive to implement a strategy to develop a culture of trust and transparency driving

improved behavioural safety in an environment compliant to regulation and RT HSE

standards. Through the period 2007 to now we have directed effort into creating

safe people – articulating behaviours and setting expectations

safe work – continued risk assessment and standardisation of work

safe equipment – improving equipment features to eliminate hazards

safe environment – using standards, training and contractor management

to enable the above

Whilst we have improved from 2007 to today, we are yet to make a step change to the next

level. We have “plateaued”. We are performing well within the Queensland underground

coal, and opencut, sector. However our challenge is to be regarded as performing well

within the Rio Tinto group. We have some distance make up the field where internally

some of our RT peers experience incident rates less than 50% those of Kestrel.

Structure and organisation

Early changes made at an organisational level centred on creating 24 hours per day of

opportunity to cut coal. This was not available to the longwall operations.

Split start times were created to create access to sufficient skilled labour – operator,

maintenance and statutory – to supplement operations through a shift change. The roster

makes use of 12.5 hour shifts so nominal shift starts at 6:00 and 7:30 on day and night shift

were implemented to maintain people at the face for a period at either end of day and night

shift, while other crew members travelled either in or out of the panel. A “hot” handover at

the face provides face activity continuity and is self-sustaining as an incumbent crew

cannot leave until the replacement crew arrives.

Page 4: Longwall Improvement at Kestrel Mine

Support crew composition was adjusted to provide the skills and people through this

window period. This meant that when required the support personnel could be at the face

cutting and when not they could be performing other support tasks.

Longwall planned stoppages were organised around a single time in the week to conduct

maintenance and support activities for the longwall and clearance system. This day is

developed around pulling up early at a predetermined time, executing the tasks in the day

to a “locked in” plan and then cutting at least one shear at 5:00pm to set up for the following

shift. Planning and execution of the maintenance component for this day follows the

discipline established by the work management process.

The rebuild process for the alternative longwall system had a full and comprehensive

review. The emphasis of the rebuild changed from fix to overhaul and project management

discipline is applied through the scoping, implementation and finalisation of each rebuild

step. Much of the scoping has been conducted through RAMBO and defect elimination

methods, highlighting tasks previously not undertaken eg replacement of valve gear and

the removal of all the redundant system to be worked on at the surface.

Reliability

The asset management protocols mandated by Rio Tinto have been in place since 2007

with their intent to increase reliability. These protocols provide discipline to the:

management of maintenance work – identify, plan, schedule, implement, complete,

analyse

reduction of contamination – for example improving support pressures

o improving the quality of water to 7 micron to protect valve gear

o emulsion plant to prepare emulsion and deliver to pump at a pre-determined

quality

elimination of defects – for example reduced DA ram failure by increasing rod

diameter from 100 to 120mm

operation for reliability – for example analysing the best cut sequence to 60:40

Page 5: Longwall Improvement at Kestrel Mine

maintenance tactics – determining task frequency and opportunity to carry out work

in the cutting cycle

The approach to reliability in our longwall operations was further promoted through the

attendance of operations and maintenance leaders at a Ron Moore reliability workshop

where the message was clear – reliability is not a maintenance accountability. This

initiated a site longwall reliability workshop involving operations, electrical and mechanical

personnel facilitated by an asset management professional from RTCA. A process where

barriers were identified, prioritised and turned into objectives derived a series of

subsequent actions to be implemented. These actions comprised process, administrative,

logistics, repair and standardising tasks.

A particular effort has been put into management of maintenance work through the work

management process. This is the RT asset management protocol that required a discipline

to be installed. The Kestrel outcomes in this process are measured and benchmarked with

all RT operations in what are called the global metrics. This has created a significant step

for maintenance work to move away from a reactive domain to a planned domain.

Cutting practice

A study was carried out on the cutting modes to determine the extent of discretion being

applied over the parameters on a crew basis and through observation of load ratings how

this variation placed stress on the operating system. This study determined a 60:40 push

to maingate parameter and change management was used to install this practice across

the 4 operating crews.

The key to the change management was the use of a trial across the crews of the various

parameter sets; 80:20, 70:30 and 60:40. Each parameter was used by all crews for a week

and data was obtained during this time. This meant each crew had first hand experience in

each parameter set, could observe what was taking place and understand the assessment

of each technique. The study concluded the 60:40, while not giving the best instantaneous

productivity as the best cutting pattern with regards to safety of the operators, reliability of

equipment, distribution of load and productivity of the mine.

Page 6: Longwall Improvement at Kestrel Mine

Kestrel took a more energetic approach to automated cutting during this time. There was

some automation facility available in the form of an inclinometer system and Bucyrus

software. However there was little confidence in the facility and take up of it had been

unenthusiastic.

Moves to change the perception of automation and capitalise on the benefits consisted of 2

strategies; (i) upgrade the technology to a reliable and accurate system and (ii) educate

and train the operators to sufficiently grow their confidence in the use and benefits of

automation.

Technological changes included an upgrade from the inclinometer to an IMAR system with

associated software adjustments. At this time the mine also implemented a broad ranging

SCADA change through CITECT capability. Now real time information was more readily

accessible and the capacity to monitor automation, and other, activities was improved from

the previous macro-view capability. Further assistance in monitoring is now available

through the provision of push reports detailing activities and time.

Several tactics were used to educate and train operators. A champion for the technology

was identified and introduced – a move prompted from a previous paper presented at this

conference. The champion has been rotating though the crews on 2 month blocks. The

role of the champion has been to teach the technology, provide feedback and confidence

that the technology works, educate the operators in the broader quality aspects of cutting –

using the roof as the target, speed for operations, arms for quality – in a manner that was

more what to do not how to do it. This involvement with the crews was made easier when

the operation scaled back from 4 operating crew to 2 in response to the GFC in 2009. The

concentrated effort on these 2 crews, and that they always returned to their workplace,

meant they were proficient when the operation went back to 4 crews. The effort then went

into the other 2 crews.

The Bucyrus model was brought to site. Operators were able to experience automation

usage in a simulated environment.

Page 7: Longwall Improvement at Kestrel Mine

Now 18 months on there is widespread acceptance of the automation. We are now in the

process of rotating a skilled trainer across all the crews to standardise the “how to do it”

aspect. Our push reporting now shows that we have 80% of the cutting being conducted in

the automation mode.

Process improvement

A number of longwall processes were addressed through improvement projects.

Lean was introduced to Kestrel at this time and after visits to RTA to look at how it can

work, application of 5s, visual workplace and standardised work became widespread in the

operation. Information boards were designed for the longwall group and these became the

focus area for crew briefings and progress tracking, both performance against plan and

issues resolution. Waste elimination projects such as the overhaul trolley were undertaken

– a trolley that houses tools, parts and enables isolation of a single chock.

We introduced a CITECT system improving the access to realtime data and feedback

across operational crews. Reports and system status are immediately available at the

maingate and transformer computers. These reports are available across the network. In

addition we are developing the capability of LVA beyond simply a geotech aid.

The retraction process was reviewed with a view to QCO – reduce the time from last shear

to first shear. While the sequencing of tasks was analysed to determine the best allocation

and use of labour, capital was invested in the form of a second transformer and pump

station. This has enabled a “leap frog” approach to be applied and time savings of up to 8

hours have been achieved.

The commissioning of each installed longwall system post install has been defined as a

process. This starts with a dry phase where there is a run through from power off to power

on with no picks in coal. A disciplined process is then applied to the wet commissioning as

increased numbers of shears are achieved as prescribed checks are completed. The key

to this stage is that the checks take precedence over the shears, containing the urge to

“just get going” and underpin reliability later in the block.

Page 8: Longwall Improvement at Kestrel Mine

Along the way

In January 2008 we had the floods in Emerald. While this did not directly endanger the

mine, the mine was indirectly affected by cut roads preventing workforce access and water

quality.

Access was maintained to the mine using chartered aircraft and a rotation of mine critical

staff and officials. This kept the mine open, ensured that any critical issues could be

managed and set a platform for remobilisation once the flood situation eased. However our

real test came when the longwall was initiated.

At this time we were commissioning the longwall system in the 305 block. The existing

filtration of raw water could not handle the changed water quality, with higher levels of

sedimentation, leading to continued valve failure in the chocks. In the short term the mine

resolved this using an IMT approach - coupled with some constraint theory (throw

everything at the bottleneck eg charter a plane to bring a full changeout of valves from and

OEM) - by changing out most of the valves in the system, installing a potable water supply

and then proceeding with the purchase and installation of a bulk emulsion plant (we may

have been a bit behind the field on this one)

In 2009 the coking coal market depressed rapidly with the global financial crisis. The

Kestrel response to this was to throttle the mine output in direct proportion to confirmation

of sales. In the longwall a cutting programme was developed using 2 crews out of 4, the

operating principle being that the longwall would run hard for a period then stop rather than

advance continually at a slower rate. The improved reliability and chock performance

enabled this strategy.

Labour not required in the longwall through the non-cut periods was reallocated, essentially

replacing contract labour. Personnel were deployed to development sections, CHPP and

the chock overhaul project. Full manning resumed later in the year – most people returned.

Page 9: Longwall Improvement at Kestrel Mine

Where are we now

H1 2010 has seen the manifestation of improvement in the operation and changeover of

the longwalls. The improvement can be seen in the ytd achievements;

cutting hours achieved per week

days per 1st 100 meters cut in a block

annual expected metres retreat

annual expected ROM tonnes

annual expected saleable tonnes

There have been no significant roof events since the support system improvements were

made.

The future

While we have made these changes to date through the efforts of a very dedicated team,

there remain a number of challenges to contend with.

The remaining blocks in the 300 series show an increase in cross grade as these blocks

progress up dip. This is increasing wear and stress on the drives, chains, racks and

trapping shoes.

As we progress up dip we mine in closer proximity to an overlying aquifer. There is a

likelihood of water ingress into the workings so drainage and pumping mitigation factors are

being implemented.

We continue on our automation journey.

We are going to install, commission and bring up to steady state operations a new 375m

unit at Kestrel South.