The WatersThe Watersabove The Pre-Flood Period From Adam to Noah.
London Flood Risk Management Strategy Adam Hosking
-
Upload
national-institute-for-coastal-and-harbor-infrastructure -
Category
Environment
-
view
105 -
download
3
Transcript of London Flood Risk Management Strategy Adam Hosking
Thames Estuary 2100 London’s Flood Risk Management StrategyPresented by
Adam Hosking Practice Director Water Resources & Ecosystem Management, CH2M
3
• Watershed & Coastal Cell Plans
• Large scale– Physical systems & driving forces
– Integrated response and planning
• Long term view– Climate change
– Sustainable approaches
– Whole life costs
UK Strategic Flood Risk Management Framework
5
Thames Estuary 2100
Why?Provide continued protection for 1.25 million people and £200 billion worth of property from tidal flood risk on the River Thames, over the next Century.
7
• Over 4000 Assets• 9 Major Barriers• 350km linear defences• 300+ active structures
TE2100 – Protection System
Thames Barrier, UK
• Operational since 1982• 520 meters long• 10 gates : 4 navigable 61 meters
rising sector gates, weighing 3,300 tonnes; 2 No. 31.5m wide RSG plus 4No. 31.5m falling radial gates
• Gates are filled with water when submerged and empty as they emerge from the river
• Cost: £534 million (£1.3 billion at 2001 prices)
• Level of protection: 1 in 1,000 year
12
Climate change scenarios Increases in peak 1000-year surge tide level and sea level rise component
5
5.5
6
6.5
7
7.5
8
8.5
9
9.5
2000 2020 2040 2060 2080 2100 2120Date
Sea level (m AOD) at Southend
Medium High SL rise Medium High total High ++ SL rise High ++ totalDefra SL rise Defra total (= SL rise) High + SL rise High + total
Latest DEFRA SL rise
Increases in peak 1000-year levels at Southend under 5 different climate change scenarios
TE2100 Climate Change Scenarios
14
• Four approaches (High Level Options) to manage water levels through the century:– Traditional Engineering (HLO 1)
– Floodplain Storage (HLO 2)
– New Barrier (with/without Thames Barrier) (HLO 3)
– New Barrage (HLO 4)
• The limits to adaptation study identified the thresholds at which each option would no longer provide an adequate standard of protection to London
Estuary-‐Wide Planning for an Uncertain Future
1717TEA-ZZ-ZZ.ZZ-TP-PM-ZZ-000005 ISSUE DATE: 07/08/2015
UNCONTROLLED WHEN PRINTED
Geomorphology – Impacts on Flood Protection
19
1m0m 4m3m2mMax water level rise:
New barrier, retain Thames Barrier, raise defences
Raise Defences
New barrier, raise defences
New barrage
HLO 1
HLO 3a
HLO 3b
HLO 4
HLO 2
The plan considered a combination of approaches
Existing system
Improve Thames Barrier and raise d/s defences
Over-rotate Thames Barrier and restore interim defences
Flood storage, improve Thames Barrier, raise u/s & d/s defences
Flood storage, over rotate Thames Barrier, raise u/s & d/s defences
Flood storage, restore interim defences
TE2100 H++Defra UKCIP MH TE2100 H+
20
Strategy Findings
• With an adaptable plan rising water levels can be managed through this century and into the next
• Continue to maintain/improve existing FRM structures –barriers, gates, levees
• Spatial and emergency planning essential part of future FRM
• New inter-tidal habitats before 2030 to offset SLR impacts
• The Thames Barrier should continue to provide protectiontowards the end of the 21st century
• Barriers and/or barrage are essential under all future scenarios to manage surges and SLR
21
Thames Estuary Asset Management 2100 (TEAM2100)
• CH2M appointed as Delivery Partner
• Top 40 UK Government Major Project
• At £300 million -‐ the Environment Agency’s largest single flood risk programme
• Efficiency target of £100 million over 10 years
22
TEAM2100
Work Scope – 10 year programme:• Asset Management• Asset Investigations• Appraisal• Detailed Design• Construction• Programme Management and
Scheme Optimisation• Programme Controls• Partnership Funding
To Deliver:• Improved Asset Management –
ISO55000• Reduced Flood Risk• Integrated Solutions• Great Efficiencies• Lessons/Best Practice for Future
FCRM Delivery
25
• Whole Life Cost and Deterioration Modelling• Sensors creating a smart estuary
TEAM2100
AM Approaches – Whole Life Approach
27
Foreshore erosion forming cavity under wall
AM Approaches – Monitoring Duke Shore Wharf-‐ Mass concrete wall undermined by foreshore erosion
Operatives removing silt from gate Alpha leaf cell A.Operatives require ear defenders & protective clothing.
Heavy silt material on floor of gate leaf removed using jet wash.
33
TEAM2100
Status
• Achieved ISO55000 AM Accreditation• Whole life cost modelling to change estuary asset
management approach -‐ £1000m WLC saving?• £50m savings identified on large realignment schemes,
accelerate schemes• £33m programme in 2017• £15m efficiency savings in 2017