LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA) NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11 Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | FOTOGRAF LOKASI : SECTION C FOTOGRAF 1: ZON 2 – NPS 1 Forcemain (18/7/18) Aktiviti: Pemasangan Paip Forcemain kaedah ‘Open Cut’ (1300 mm DN) FOTOGRAF 2: ZON 2 – NPS 1 (3/7/18) Aktiviti: Kerja-kerja sivil dan struktur

Transcript of LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf...

Page 1: LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | F O T O G R A F LOKASI : SECTION C FOTOGRAF

LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA)

NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11

Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018)

1 | F O T O G R A F

LOKASI : SECTION C

FOTOGRAF 1: ZON 2 – NPS 1 Forcemain (18/7/18) Aktiviti: Pemasangan Paip Forcemain kaedah ‘Open Cut’ (1300 mm DN)

FOTOGRAF 2: ZON 2 – NPS 1 (3/7/18) Aktiviti: Kerja-kerja sivil dan struktur

Page 2: LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | F O T O G R A F LOKASI : SECTION C FOTOGRAF

LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA)

NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11

Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018)

2 | F O T O G R A F

LOKASI : SECTION C

FOTOGRAF 3: ZON 2 – MB 9-08 Jacking Pit (18/7/18) Aktiviti: Kerja-kerja ‘Pipe Jacking’ dari MB 9-08 to MB 9-07 (375 mm DN)

FOTOGRAF 4: ZON 2B – MB 9-12/6 Jacking Pit (18/7/18)

Aktiviti: Kerja-kerja ‘Pipe Jacking’ sedang dijalankan dari MB9-12/6 ke MB9-12/5 (375 mm DN)

Page 3: LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | F O T O G R A F LOKASI : SECTION C FOTOGRAF

LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA)

NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11

Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018)

3 | F O T O G R A F

LOKASI : SECTION B

FOTOGRAF 5: ZON 2 – JPS Crossing Jacking Pit (18/7/18)

Aktiviti: Pembinaan lurang (Cofferdam)

Page 4: LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | F O T O G R A F LOKASI : SECTION C FOTOGRAF

LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA)

NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11

Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018)

4 | F O T O G R A F

LOKASI : SECTION C

FOTOGRAF 6: ZON 3A – NPS 4 (15/7/18) Aktiviti: Kerja-kerja Pembinaan Pump

FOTOGRAF 7: ZON 3A – MB 6-42 (12/7/18) Aktiviti: Pmbinaan Lubang

Page 5: LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | F O T O G R A F LOKASI : SECTION C FOTOGRAF

LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA)

NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11

Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018)

5 | F O T O G R A F

LOKASI : SECTION C

FOTOGRAF 8: ZON 3A – MB 5-25A (20/7/18) Activity: Pembinaan Lubang

FOTOGRAF 9: ZON 3A – MB 6-47 Jacking Pit (28/6/18)

Aktiviti: Kerja-kerja ‘Pipe Jacking’ dari MB 6-47 to MB 6-46 (1050 mm DN)

Page 6: LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | F O T O G R A F LOKASI : SECTION C FOTOGRAF

LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA)

NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11

Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018)

6 | F O T O G R A F

LOKASI : SECTION C

FOTOGRAF 10: ZON 3B – MB 1-17/7 (15/7/18) Aktiviti: Pembinaan lurang

FOTOGRAF 11: ZON 3B – MB 1-37 (14/7/18)

Aktiviti: Pembinaan Lubang

Page 7: LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | F O T O G R A F LOKASI : SECTION C FOTOGRAF

LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA)

NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11

Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018)

7 | F O T O G R A F

LOKASI : SECTION C

FOTOGRAF 12: ZON 3B – MB 1-14 Jacking Pit (12/7/18) Aktiviti: Kerja-kerja ‘Pipe Jacking’ dari MB 1-14 to MB 1-13 (450 mm DN)

FOTOGRAF 13: ZON 3C – MB 4-02 Jacking Pit (3/7/18) Aktiviti: Kerja-kerja ‘Pipe Jacking’ dari MB 4-02 to MB 4-03 (375 mm DN)

Page 8: LOKASI : SECTION Cpapan1.com/upload/gallery/2018/LFB-32.pdf · 2018. 10. 8. · Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018) 1 | F O T O G R A F LOKASI : SECTION C FOTOGRAF

LOJI RAWATAN KUMBAHAN SERANTAU DAN RANGKAIAN PAIP PEMBETUNGAN DI PAPAN, DAERAH KINTA- PAKEJ 1: NETWORK (REKA BINA)

NO. KONTRAK : KeTTHA/JPP/PAPAN1/RMK 10/15/K11

Laporan Fotograf Bulanan No.32 (sehingga 25/7/2018)

8 | F O T O G R A F

LOKASI : SECTION C

FOTOGRAF 14: ZON 3D – NPS 2 (5/7/18) Aktiviti: Kerja-kerja sivil dan struktur