    DESIGNINGANDDEVELOPING

    PROJECTS (PART. I)Through

    Logical Frame-work Approach (LFA)

  • 7/29/2019 Logical Framework Approach for project development

    2/14

    GENERAL OBJECTIVE

    To improve our skills in designing and developing

    projects for our NGOs

  • 7/29/2019 Logical Framework Approach for project development

    3/14

    ESPECIPHIC OBJECTIVE(S)

    To introduce the basic steps of the Logical

    Framework Approach (LFA) for:

    Understanding our environment and the elements

    involved with our work

    Finding Problems/Issues/Conflicts and the best way

    they can be addressed with our capacities (Strategy).

    Helping us (and others) clearly identify the Objectives,Justifications and Beneficiaries of our projects/solutions.

    Evaluating our progress and correcting our mistakes

  • 7/29/2019 Logical Framework Approach for project development

    4/14

    STAGESOFA PROJECT

    1. Identification

    2. Feasibility Study

    3. Project Design

    4. Detailed Planification

    5. Development / Follow Up

    6. Project Revision

    7. Evaluation

  • 7/29/2019 Logical Framework Approach for project development

    5/14

    WHEREAREWESTANDING (CRITERIA)?

    Who are us? (Individuals, Collectives, NGOs,

    Institutions, etc.)

    What (and why) are we doing here (background,

    responsabilities, interests, expectations)?

    What is my/our availability (time, initial resources,

    skills)

  • 7/29/2019 Logical Framework Approach for project development

    6/14

    UNDERSTANDINGOURENVIRONMENT

    Finding the Stakeholders (Participants)

    Which (group of interest) are related to the situation we want to

    engage?

    What are their problems, interests (orneeds) and points of view.

    How do they relate to each other?

    What is their potential in a foreseeable future (both Positive,

    Negative)

    Which group needs support?

    Which interests and points of view are we going to prioritize?

  • 7/29/2019 Logical Framework Approach for project development

    7/14

    UNDERSTANDINGOURENVIRONMENT

    Identifying the problem we want to address

    State only the existing problems (no the future/possible

    ones).

    A problem is a negative state not the lack of

    something. (i.e. The education is deficient)

    Identify the main problems (observation and brainstorm)

    Select a Focal problem

  • 7/29/2019 Logical Framework Approach for project development

    8/14

    THETWOTREES

    The youngpopulation is

    migrating

    There are poor jobopportunities after

    school

    The youngpopulation is not

    educated enough toaccess the jobopportunities

    There is noequipment in theeducation centers

    High education isnot accessible

    The teachers arenot prepared

    There is a lack ofsocial services and

    leisure spaces

    The is very fewavailable budget in

    the publicinstitutions

    Focal Problem

    Effects

    Causes

    There is a reductionin the rate of

    migration amongthe young people

    There are enoughsocial and leisure

    services

    The youngpopulation is findinga job after finishing

    their studies

    The youngpopulation is well

    educated andtrained

    The educationcenters are well

    equipped

    There is availableaccess to good

    education

    The teachers arewell prepared and

    updated

    Problems Objectives

  • 7/29/2019 Logical Framework Approach for project development

    9/14

    CHOOSINGA STRATEGY (WHATAREOUR

    OPTIONS?)

    Which options do we have in order to transform

    each part of the problems tree into the objectives

    tree?

    Can we organize this options by areas (i.e.

    Budget, Training, Counseling, Art and Culture,

    etc.)?

    In which of this areas we have the best chance of

    success according to our criteria?

  • 7/29/2019 Logical Framework Approach for project development

    10/14

    DESIGNINGOURPROJECT

    The Project Matrix

    The PM will be the result of our planification process.

    It will be a useful reference during the implementation

    and evaluation of our project.

    Keeps the objectives, strategies and tasks visible.

  • 7/29/2019 Logical Framework Approach for project development

    11/14

    DESIGNINGOURPROJECT

    The matrix is a double-entry chart with four columns andfour lines. The columns are (left to right):

    1) Logic of intervention.

    2) Indicators;

    3) Sources of verification. (Methods and sources to beused while analyzing the Indicators); 4) Hypothesis and external factors. (Out of our control,

    stated in a positive way) The lines are (Top to down)

    General Objective (GO)

    Especiphic Objective (EO) Results (Clear and visible facts enough to reach the EO, it

    is possible to reach them through the project activities)Activities and inputs. (Tasks that the people working in the

    project will have to do.)

  • 7/29/2019 Logical Framework Approach for project development

    12/14

    THE PROJECT MATRIX

    Logic ofIntervention

    Indicators(Direct/Indirect/Behavior/E

    nvironment/etc.)

    Sources ofverification(External)

    Hypothesis/ExternalFactors

    General

    Objective

    (From the focal

    problem)

    (How are we

    going to

    objectively

    measure our

    advance?)

    From which

    sources we can

    validate our

    indicators?

    Especiphic

    Objective

    (Time +

    Beneficiaries)

    (How are we

    going to

    objectively

    measure our

    advance?)

    From which

    sources we can

    validate our

    indicators

    (beneficiary

    related)?

    Which external

    conditions will

    allow our results

    reflect in the

    achievement of the

    objective?

    ResultsR.1,R.2,R.3,

    Etc

    (How are we

    going to

    objectively

    measure our

    advance?)

    From which

    sources we canvalidate our

    indicators

    (evaluation

    activities)?

    On which external

    factors we dependto achieve this

    results?

    Activities-

    Inputs

    R.1, R.2, R.3,

    Etc (stated as

    process)

    (Inputs and

    needed

    resources)

    Costs Which pre-conditions have to

    be met in order tostart the project?

  • 7/29/2019 Logical Framework Approach for project development

    13/14

    HOWTOREADTHE PM?

    IFTHEINPUTSAREAVAILABLE,

    THEN, THEACTIVITIESWILLBE

    DONE.

    IFTHEACTIVITIESAREDONE,

    THENTHERESULTSWILLBE

    PRODUCED.

    IFTHERESULTSARE

    PRODUCED, THENTHE

    ESPECIPHICOBJECTIVE

    WILL

    BEMET.

    IFTHEESPECIPHIC

    OBJECTIVEISMET, THENIT

    WILLCONTRIBUTETOTHE

    GENERAL OBJECTIVE.

    Global

    Objective

    EspeciphicObjective

    Results

    Activities

    Available

    Resources

    ExternalFactors

    External

    Factors

    ExternalFactors

    Pre-existing

    conditions

  • 7/29/2019 Logical Framework Approach for project development

    14/14

    THANKYOU!End of the Planification Stage