Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group...

14
Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG

Transcript of Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group...

Page 1: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

Load Profiling Working GroupRMS Presentation

8/01/2002by

Ernie PodrazaReliant Energy Retail Group

Chair PWG

Page 2: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

2

Initial Validation Process Update

• Targets– Complete Profile ID assignment changes.– Due date was 6/15/02.

• Part of resettlement of True-ups.

• Beginning 7/31/01 trade day.

Page 3: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

3

Initial Validation Process Update

• TDSP Transaction Submittal Status

Updated as of 3 PM, 7/31/02.

Process Subprocess TNMP AEP/third party ONCOR Reliant

To Change 814_20 34,000 19,000 210,493 425,764Inactive * 0 0 0 0

Active 34,000 19,000 210,530 425,764Complete 814_21 (WQ) 33,656 18,856 210,498 424,821

Incomplete 814_21 (U) 344 144 32 943% Complete 99.0% 99.2% 100.0% 99.8%

TDSP

Page 4: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

4

Initial Validation Process Update

• ERCOT Validation Analysis of Sample

Updated as of 4 PM, 7/31/02.

Population Res WR Bus LFZip Not in

Decision TreeZip Assn to Wrong Zone

CPL 767698 0.5650% 0.4100% 0.0021% 0.0735%Center Point Energy 1776376 14.5350% 12.3750% 0.0001% 0.3366%TNMP 208964 5.2100% 36.1750% 0.2149% 0.0014%Oncor 2791474 0.5150% 0.5803% 0.0080% 0.2176%WTU 207410 0.8800% 0.2718% 0.1475% 0.6215%TXU-SESCO 44693 0.4801% 0.6483% *** ***

*** Included with TXU Population

Summary of Load Profile ID Validation Results29-Jul-02

Exception Rate

Page 5: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

5

Initial Validation Process Update

• Summary of PWG Completion Criteria

Updated as of 4 PM, 7/31/02.

Summary of criteria to begin Resettlements:TNMP AEP ONCOR Reliant

1. Sample 99% Accuracy for Initial Validation for Res. &Bus. Profiles by TDSP. N Y Y N2. 99% of the 814_20s transactions from Initial validationscorrectly loaded into the ERCOT billing system. Y Y Y Y3. 99% Zip Codes in the Decision Tree

Y Y Y Y4. 99% Zip to Weather Zone mapping

Y Y Y Y

TDSP

Page 6: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

6

Initial Validation Process Update

• TDSP Profile Change Efforts To Date– More than 700,000 814_20 transactions submitted.

– A huge amount of work has been completed.• Internal software development changes.

• Algorithm development and refinement.

• Approximately 12 Initial Validation Sub-team meetings.

• Frequent communication with ERCOT.

– High Confidence level that the algorithms are correct.

– Discrepancies have been identified.

Page 7: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

7

Initial Validation Process Update

• Issues– Difficult to distinguish initial validation

transactions from normal business transactions so tracking the status is difficult.

– Validation error percents may not reflect the final legitimate discrepancies.

– Final discrepancies are being worked currently.

Page 8: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

8

Initial Validation Process Update

• Root Cause of Discrepancies– Profile Group (Residential or Business) not matching

ESI ID type.

– Some data not in sync between TDSP and ERCOT.• Meter read dates in particular.

– Interpretation of assignment of profile id on customer level vs. premise level.

Page 9: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

9

Initial Validation Process Update• Current Status as of 7/31/02

– ERCOT• June 29 validation run.

– Some improvement in error percents.

• Discrepancies identified.• Ongoing daily reviews with TDSPs. • Will have another validation update after new 814_20s.

– TDSP • Reliant and TNMP must run refined algorithms over population. • Resubmitting needed for 814_20 transactions.

– Reliant may have as many as 100,000 more perhaps this week.– TNMP may have as many as 70,000 more.

• On going daily reviews with ERCOT to reconcile discrepancies.

Page 10: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

10

For RMS Vote

• PRR Extension of IDR Proxy Day Method

Page 11: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

11

For RMS Vote

• PRR Extension of IDR Proxy Day Method

Page 12: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

12

For RMS Vote

• Process: IDR EstimatesEstimate

Using WSProxy Day

No EstimatesNecessary

EstimateUsing NWSProxy Day

Create EstimateUsing

Default Profile

DataAvailable

WeatherSensitive?

IDRESI-IDs

Yes

No

Yes

ProxyDay

Report

No

EstimateCreated?

EstimateCreated?

Yes

Yes

No

No

Store Estimatewith ERCOTStatus Code

HistoricalInterval

Data

LodestarWeather

Data

IDREstimates

Report

Profiles

Page 13: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

13

For RMS Vote• MARKET NOTIFICATION OF SYSTEM CHANGE

PIP Number(s): N/A

PRR Number(s): N/A

Change Description:Changes to IDR data estimation using the BUSIDRREQ profile

Protocol Section(s): 11.3.3 Interval Consumption Data Estimation

Implementation Date: July 26, 2002 (Trade Day)

Description of System Change:

Effective Friday July 26, 2002, each interval for the BUSIDRRQ load profile will be multiplied by a factor of 0.758. This profile will be used in settlement only when an IDR ESI ID has no 15-minute interval data available for the period that covers the past 8 weeks. This change to the BUSIDRRQ load profile was approved by the Profiling Working Group during the IDR Default Profile Workshop held on July 15, 2002.

Page 14: Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.

14

For RMS Vote

• PRR Extension of IDR Proxy Day Method – From last 8 weeks to last 12 months.

– 11.3.3.3 Non-Weather Sensitive (NWSIDR) Proxy Day Method• For ESI-IDs designated as NWSIDR, ERCOT will use a method for proxy day

determination. This method incorporates the following.

1) If there is no historic interval data available according to (1) above, the IDR data will be estimated using the default profile assigned to the ESI ID for the trade day.

2) Use the most recent proxy day for which data is available as the estimate for the target Operating Day. From historical ESI-ID-specific interval data, choose the most recent occurrence of the appropriate day of the week (Su, M, T, W, Th, F, Sa) corresponding to the day of the week of the Operating Day (Holidays are treated as Sundays) within the most recent 12 months of the trade day;