LNG research and calibration facility Dr Peter...
Transcript of LNG research and calibration facility Dr Peter...
LNG research and calibration facility Dr Peter Lucas
August 22, 2017
The results described in this paper have been obtained with funding received
from the EMRP. The EMRP is jointly funded by the European Commission and
participating countries within Euramet and the European Union.
LNG distribution chain
4-9-2017 LNG workshop
Delft, August 2017 2
Bunkering/ refueling stations/ ships
Ships Trucks and busses
Receiving terminal
Sea transport
Road transport
Ocean tanker
Pipeline gas
Remote industry
Large scale
> 20,000 m3
Small and mid scale
< 20,000 m3
Small and mid scale LNG
• Truck refueling, estimates
• 0.02 million tonnes per annum
• 1,557 vehicles in Europe (214,000 vehicles in
China)
• ~15 Refueling stations in Europe (2,460 in China)
• Ship bunkering, estimates
• 0.2 million tonnes per annum
• 86 LNG fueled ships in operation (87% in Europe),
96 in order
• Transport by road and sea, estimates
• 1.0 million tonnes per annum
• To remote gas grids and industry
4-9-2017 3
Blue corridors (source NVGA Europe)
LNG workshop
Delft, August 2017
Measurement of LNG
Large scale
• Measurement of energy
• GIIGNL custody transfer handbook
• Tank gauging (process control with USM)
Small scale
• Measurement of mass
• Various MID approved CMFs available
• OIML R117-1
• MPE system 1.5 %
• MPE flow meter 1.0 %
• Calibration based on water
4-9-2017 4 LNG workshop
Delft, August 2017
Measurement of LNG – mid scale
Transport by road: weighing bridges (Netherlands)
Transport by sea: similarly as for large scale LNG (Netherlands)
• GIIGNL custody transfer handbook
• Tank gauging (process control with USM)
• Bunkering (?)
Advantage of using flow meters
• Quicker (more cost effective)
• Lower uncertainty (especially for small batches)
But
• No MID approved CMFs available
• No traceability, calibration on water accepted?
• Future uncertainty target more stringent than OIML R117-1?
4-9-2017 5 LNG workshop
Delft, August 2017
Extrapolation models for LNG metering
4-9-2017 6
Water versus LNG
Water versus LIN
LNG workshop
Delft, August 2017
• Calibration results for LIN (2012) and LNG (2013)
• 2” CMF (straight and bend tube)
• Calibration uncertainty ~0.2%
Mid scale LNG research and calibration facilty
4-9-2017 7
Flow Rate 5 – 200 m3/h
Expandable to 400 (1000) m3/h
Target uncertainty 0.15 % on mass (0.2% on volume)
Line pressure 1 – 10 barg(g)
Temperature -123 °C to -175 °C
Composition Measured, not controlled
Traceable to primary standard
Closed loop/ no boil-off
LNG workshop
Delft, August 2017
Heat exchangers
4-9-2017 10
LIN/ LNG heat
exchangers to avoid
‘boil-off’
LNG workshop
Delft, August 2017
Working standards cold box
9/4/2017 11
Cold N2 “waste” from
LIN/LNG heat exchanger • Four CMFs in parallel with Qmax of 50 m3/h
• Maximum flow rate 200 m3/h
• Cold box, refrigerated with N2 waste from
heat exchanger
• Traceable to master meters (traceable to
scale)
LNG
LNG workshop
Delft, August 2017
Pumps
4-9-2017 12
• Initially two of three
pumps installed
• Frequency controlled
LNG workshop
Delft, August 2017
Nitrogen warmer
4-9-2017 13
Nitrogen warmer to
avoid release of cold
Nitrogen
“Warm” Nitrogen
Cold N2 “waste” from
LIN/LNG heat exchanger
LNG workshop
Delft, August 2017
Meter Under Test section
• All vacuum insulated piping
• Initially a 2” and 4” line will be realized
LNG workshop
Delft, August 2017
Temperature measurements
• Robust
• Stresses due to cooling down/ heating up
• Flow induced vibrations
• Thin, fast response to temperature change
• Very small heat inleak from ambient
• Removable sensor for laboratory calibration
• Overall uncertainty 0.1 ºC at -162 ºC
4-9-2017 15 LNG workshop
Delft, August 2017
New design
4-9-2017 16
Co design
Fixed-cup
Sensor stem
Gas cavity
Thermowell tip LNG workshop
Delft, August 2017
Planning and future work
Completion Facility
- Installation remaining skids
- MUT section September
- Analyzers September/ October
- PSL Q1 2018
- Electrical completion (expected finish November)
- Mechanical completion (expected finish November)
- Commissioning (expected finish January/ February 2018)
Research
• Systematic research into flow meter performance
• Feasibility study on how to increase the flow rate up to 1000 m3/h
• Smart sensor development, testing and validation
4-9-2017 17
LNG workshop
Delft, August 2017
Questions? http://lngmetrology.info/ Dr Peter Lucas [email protected]
Peter Lucas:
nl.linkedin.com/in/lucaspeter
VSL group:
http://lnkd.in/Bif3Sy
VSL Fluid Flow Metrology group:
http://lnkd.in/DF2zJx
Flow metering error small scale LNG
4-9-2017 19
• Calibration results for LIN and LNG (2013)
• 2” CMF (straight and bend tube)
• Calibration uncertainty ~0.2%
VSL primary
standard LNG
flow