LMPP Final Presentation_FINAL1

56
obg.com Nicole Link Theodore McNeal Neil Page Xiong Peng Clinton River Wastewater Treatment Plant (WWTP)

Transcript of LMPP Final Presentation_FINAL1

Page 1: LMPP Final Presentation_FINAL1

obg.com

Nicole Link Theodore McNeal Neil PageXiong Peng

Clinton River Wastewater Treatment Plant (WWTP)

Page 2: LMPP Final Presentation_FINAL1

Clinton River Watershed Council 2

Clinton River Watershed

Page 3: LMPP Final Presentation_FINAL1

• 760 square miles• 80 miles from the headwaters to

the outlet at Lake St. Clair• Includes portions of Wayne,

Lapeer, Macomb, Oakland and St. Clair counties

• Land uses include industrial, urban, suburban and agricultural

• Contains 63 communities• 1.5 million people live within the

watershed• Most populated watershed in

MichiganClinton River Watershed Council 3

Clinton River Watershed

Page 4: LMPP Final Presentation_FINAL1

Area of Concern (Environmental Protection Agency)

• Degraded fish & wildlife populations• Beach closings and other restrictions• Degradation of aesthetics

Combined sewer overflows are the largest source of pollutants by CRWC

http://detroit.cbslocal.com

4

Environmental Impacts

Page 5: LMPP Final Presentation_FINAL1

• Beach Closings• Loss in tourism• No Swimming• Restrictions on fishing

©Clinton River Watershed Council greatlakeseco.org

Google.com

5

Social Concerns

Page 6: LMPP Final Presentation_FINAL1

• Diverts 30 percent of Oakland County’s effluent collected from twelve different cities from the Detroit Water and Sewage Department

• The wastewater is treated to meet the National Pollutant Discharge Elimination System (NPDES)

• Includes the construction of an Administration/Environmental Awareness Center

• Educate local communities of the treatment processes used

• Promote awareness of sustainable water reuse

Project Overview

Clinton River Watershed Council 6

Page 7: LMPP Final Presentation_FINAL1

• LMPP Consultants is to provide the following engineering services listed below:

• Construction Engineering• Environmental Engineering• Structural Engineering• Water Resources Engineering

• Constraints are the following:

• Geotechnical Engineering• Transportation Engineering• Inlet and Outlet Design

7

Engineering Services and Constraints

Page 8: LMPP Final Presentation_FINAL1

8

Site Selection and Alternatives

Page 9: LMPP Final Presentation_FINAL1

• Madison Heights, Oakland County, MI (Site 3)

• Bounded by I-75, W Twelve Mile Rd and John R Rd

• Located on Ajax Drive

Project Location

Influent

Effluent

Existing Interceptor

9

Page 10: LMPP Final Presentation_FINAL1

• Site is currently used as a police impound lot, a recreational vehicle storage lot and composite site

• The site is located in an industrial area showing no zoning conflicts

• The adjacent land is owned by DTE Energy Chestnut Station which will provide electrical services to the WWTP

• The site requires clearing and milling of the existing parking lot areas

10

Existing Site Locations

Page 11: LMPP Final Presentation_FINAL1

11

Site Plan

Page 12: LMPP Final Presentation_FINAL1

• Locate and select sources of wastewater influent processed in the proposed WWTP

• Locate and select receiving bodies of water for the proposed WWTP effluent

• Determine NPDES Permit limits for the project site

• Determine the “best” treatment process for the project

• Develop equipment location and size• Develop a treatment plant master plan that

details the prospects for future expansion• Report all requirements to the project

stakeholders in the Environmental Engineering Technical Report

12

Environmental Engineering Scope

Page 13: LMPP Final Presentation_FINAL1

13

Treatment Plant Process Diagram

Page 14: LMPP Final Presentation_FINAL1

2.5

 

NPDES Permit LimitsAverage Daily Maximum

Concentration (mg/l)

pH (S.U.) 9Dissolved Oxygen 5Total Residual Chlorine 0.85CBOD5 40Total Suspended Solids 45Fecal Coliform (CFU/100 ml) 200Ammonia-Nitrogen 6Total Phosphorus 4

Desgin Flows MGD m̂ 3/day m̂ 3/sAverage flow 50 190,000 2.2peak flow 125 475000 5.5

• NPDES Permit limits are based on comparable limits at the Warren WWTP

(Davis, 2010) 14

Treatment Plant Design Data

Page 15: LMPP Final Presentation_FINAL1

N

Aeration Tanks

Tertiary Treatment Facility

Secondary Settling

Primary Settling

Future Expansion

15

Treatment Plant Plan View

Page 16: LMPP Final Presentation_FINAL1

Aeration Tanks Tertiary Treatment FacilitySecondary

SettlingPrimary Settling

(Davis, 2010)

16

Treatment Plant Sections

Page 17: LMPP Final Presentation_FINAL1

• Architectural & Structural Layouts• Gravity and Environmental Load

Calculations:• Dead Loads• Live Loads• Wind Loads• Snow Loads• Seismic Loads

• Identification and Design of Lateral Force Resisting System

• Roof / Flooring System Design• Analysis using Structural Design

Software• Member Design (Beams, Columns,

Etc.)• Shear and Moment Connection Details

Typical Beam to Column Flange with Moment Connection

17

Structural Engineering Scope

Page 18: LMPP Final Presentation_FINAL1

Administration/Environmental Awareness Center 18

Architectural Layouts - Floor Plans

Page 19: LMPP Final Presentation_FINAL1

Administration/Environmental Awareness Center

West Elevation

East Elevation

19

Architectural Layouts – Building Elevations

Page 20: LMPP Final Presentation_FINAL1

Administration/Environmental Awareness Center 20

Environmental Load Diagram – Wind Loads

Page 21: LMPP Final Presentation_FINAL1

Administration/Environmental Awareness Center 21

Environmental Load Diagram – Snow Loads

Page 22: LMPP Final Presentation_FINAL1

22

Structural Model – Administration/Environmental Awareness Center

Page 23: LMPP Final Presentation_FINAL1

23

Structural Model – Tertiary Treatment Building

Page 24: LMPP Final Presentation_FINAL1

Administration/Environmental Awareness Center 24

Gravity Load Application – Live Loads

Page 25: LMPP Final Presentation_FINAL1

Tertiary Treatment Building 25

Gravity Load Application – Dead Loads

Page 26: LMPP Final Presentation_FINAL1

26

Structural Layouts – Framing Plans

Second Floor Roof

Administration/Environmental Awareness Center

Page 27: LMPP Final Presentation_FINAL1

Stormwater Management Plan • Area of 12 acres• 10-year storm rainfall (3.13 inch)• 115,000 runoff• 1550 feet PVC sewer• Michigan LID for facility designs

27

Water Resources Engineering Scope

Page 28: LMPP Final Presentation_FINAL1

28

Drainage Area One

Page 29: LMPP Final Presentation_FINAL1

Extensive Green Roofs

29

Page 30: LMPP Final Presentation_FINAL1

Vegetated Swales

30

Page 31: LMPP Final Presentation_FINAL1

Rain Garden

31

Page 32: LMPP Final Presentation_FINAL1

Drainage Area Two and Three

32

Page 33: LMPP Final Presentation_FINAL1

Storm Sewer Profiles

33

Page 34: LMPP Final Presentation_FINAL1

Underground Retention Pond

• Capacity of 120,000

34

Page 35: LMPP Final Presentation_FINAL1

• Sustainability Management Plan

• Cost Management Plan• Logistics Plan• Safety Management Plan

• Scope Management Plan

• Site Management Plan

• Schedule Management Plan

• Permitting/Approval Plan

Project Management Plan includes:

35

Construction Engineering Scope

Page 36: LMPP Final Presentation_FINAL1

LEED 2009 Reference Guide for Green Building Design and Construction: New Construction and Major

Renovations

USGBC.org

Accepted to achieve: LEED Certified

LEED Category PointsSustainable Sites 22Water Effi ciency 10Energy and Atmosphere 2Materials and Resources 4Indoor Environmental Quality 7Innovation In Design 3Total Points 48

36

Leadership in Energy and Environmental Design

Page 37: LMPP Final Presentation_FINAL1

Based on a case study outlined in the Detroit Water and Sewerage Department Technical Feasibility of Satellite Treatment, 2003 proposed a new 56.3 million gallon per day WWTP along the Clinton River had a projected cost of $225.9 million resulting in a $4.01gallon per day. The Clinton River WWTP is a 50 MGD facility resulting in an initial conceptual estimate of $200 million.

$200,000,00037

Conceptual Project Cost

Page 38: LMPP Final Presentation_FINAL1

Estimated using “The Handbook Biological Wastewater Treatment.”

38

Project Cost

Page 39: LMPP Final Presentation_FINAL1

$72 million36%

$102 million51%

$26 million13%

Infrastructure (36%)

Electrical, Mechanical and Technical Components (51%)

Construction Management (13%)

39

Project Cost Distribution

Page 40: LMPP Final Presentation_FINAL1

Calculated using “RSMeans Building Cost Data 2013” based on the unit price including both equipment and site work for the building only.

40

Administration/Environmental Awareness Center Cost

Page 41: LMPP Final Presentation_FINAL1

Staging area located next to the office trailer and safety board is dedicated to house the subcontractor’s office trailers.

I-75

41

Logistics Plan

Page 42: LMPP Final Presentation_FINAL1

42

Project Design Schedule2012

STRUCTURAL

DESIGN

ENVIRONMENTAL

WATER RESOURCES

CONSTRUCTION

PROJECT DEVELOPMENT

CONSTRUCTION

2013

Page 43: LMPP Final Presentation_FINAL1

CERTIFICATE OF OPERATION

A/E BUILDING

PLANTGRIT WITH PUMP

2014 20152013

AERATION

SECONDARY ANDTERTIARY

FOUNDATIONSTEEL

ENCLOSURE

INTERIORSFIRST FLOOR

SECOND FLOOR

PRIMARY

SITEWORK

43

Project Construction Schedule

Page 44: LMPP Final Presentation_FINAL1

Schematic Design Complete 11/21/2012Design Development Complete 2/1/2013Building Permit Approved 3/8/2013Start Construction 4/15/2013Construction Documents Complete 4/19/2013Admin. Building: Topped Out 8/23/2013Admin. Building: Building Watertight 1/10/2014Admin. Building: Certificate of Occupancy

2/28/2014

Tertiary Building: Building Watertight 3/14/2014Plant Operational 3/27/2015

44

Project Milestones

Are we

there

yet?

Page 45: LMPP Final Presentation_FINAL1

Thank you for your time!

Q & A45

Page 46: LMPP Final Presentation_FINAL1

Site 1: Rochester

Page 47: LMPP Final Presentation_FINAL1

Site 2: Waterford

Page 48: LMPP Final Presentation_FINAL1

Axial Load Diagram

Structural Analysis – Administration/Environmental Awareness Center

Page 49: LMPP Final Presentation_FINAL1

Bending Moment Diagram

Structural Analysis – Tertiary Treatment Building

Page 50: LMPP Final Presentation_FINAL1

Deflection Diagram

Structural Analysis-Tertiary Treatment

Page 51: LMPP Final Presentation_FINAL1

Deflection Moment Diagram

Structural Analysis- Administration/Environmental Awareness Center

Page 52: LMPP Final Presentation_FINAL1

Unity Check Analysis

Structural Analysis-Administration/Environmental Awareness Center

Page 53: LMPP Final Presentation_FINAL1

Unity Check Analysis

Structural Analysis-Tertiary Treatment Building

Page 54: LMPP Final Presentation_FINAL1

• An erosion and sedimentation control plan during construction

• Install low-flow and low-flush fixtures in restrooms• A commissioning plan to verify the project’s energy-

related systems are installed, calibrated and perform to the design requirements

• Comply with Advanced Buildings Core Performance Guide

• Do not use CFC-based refrigerates in HVAC systems• Dedicate a minimum of 175 square feet for

collection and storage of recycling materials• ASHRAE 62.1-2007 to mechanically, naturally and

mixed-mode ventilated spaces• Prohibit smoking in the building

LEED Category: Prerequisites

Page 55: LMPP Final Presentation_FINAL1

• Build within ½ mile of a residential area and basic services and with pedestrian access Public transportation access

• Provide bicycle storage and changing rooms• Provide preferred parking to employees with low-

emitting and fuel efficient vehicles• Provide minimum code required parking lot• Provide a stormwater management plan to protect

from excess erosion and reuse of stormwater runoff • Provide best management practices to treat

stormwater • Use concrete paved surfaces and plant vegetation

for shading hardscapes• Install vegetated roof • Utilizes “dark sky” light fixtures

LEED Category: Sustainable Sites

Page 56: LMPP Final Presentation_FINAL1

• Plant native and drought resistant plantings to not require potable water for irrigation

• Treat 50 percent of wastewater on site• Use low flow fixtures and equipment throughout

the project

LEED Category: Water Efficiency