Content• Requested Hardware and future Location • Conceptual System Considerations• Schedule • Budget /Spending Profile• Manpower/ Resources
1/10/2014
LIU-PS ABT review 3
What hardware (modification) is needed?
1/10/2014
LIU-PS ABT review 4
What hardware (modification) is needed?
• KFA 53 is a complete new kicker system: • Vacuum tank • Delay line magnet• Pulsed/Controls Cables• Generators (PFL) • Controls • Infrastructure (building, cable ducts, electrical
installation, etc.)
1/10/2014
LIU-PS ABT review 5
Received Requirements
• As fast as KFA-45 (rise time 46 ns 1-99%).• Max. deflection angle at 2 GeV: 1.3 mrad.• Beam stay clear aperture: 140x53 mm . • Magnet to be placed in SD53.
1/10/2014
LIU-PS ABT review 61/10/2014
KFA-45 KFA-53650 mm available (magnet to be displaced)
Available Space (Tunnel)
LIU-PS ABT review 71/10/2014
LIU-PS ABT review 8
Available Space(Surface) Reference: KFA-45
1/10/2014
KFA 45: Bat. 365 75+25m²KFA-53: Approx. 50+20?m²
LIU-PS ABT review 9
• KFA45 area is crowded already (although controls consolidation could free up some space)
• Cables to SD53 would be too long.
1/10/2014
LIU-PS ABT review 10
Where to put the Pulse Generator?
1/10/2014
KFA45KFA53
51m
365
356
131
225
362
LIU-PS ABT review 11
Space• 365-1-405: No space available. Cables too
long (should be <50m).• 362: seems to small.(extension?) Cables too
long.• 365: (east end). Seems ok but TE-EPC
owned.• 356: possibly best location but TE-EPC
owned.• If none of the above is possible: New building
between 365 and 356.
1/10/2014
LIU-PS ABT review 12
Concept and Main Parameters
1/10/2014
LIU-PS ABT review 13
Basic Concept for Magnet (I)• Delay line magnets. • Leave aperture for possible impedance
shielding efforts (+6mm=59mm). • Adapt magnet to rise time requirements in
SC mode.
• Hence KFA 45 modules will not fit anymore (53mm).
1/10/2014
LIU-PS ABT review 14
Basic System Concept (II)• Beam rigidity at 2 GeV is 9.29 Tm;• Magnetic length is ~650 mm; • 1.3 mrad kick requires ~850 A;• Usage of RG220 cables desired; • Thus max. 40kV ops max. 33kV nominal 27
kV. -> 27kV/0.85kA -> ~30 Ω system impedance.
1/10/2014
LIU-PS ABT review 15
Basic System Concept (III)• 2 delay line magnets to be housed in new
vacuum tank. • Usage of known 60 Ohm low loss cable ( 2
in parallel). • TX cables loaded with ferrites for pulse
shaping.• Refurbishment of 2 EPA generators. • CX 1154 Switches. • Hydraulic group (ELENA type)
1/10/2014
LIU-PS ABT review 16
Main Parameters (TDR)
Parameter unit valueDeflection angle (nominal) mrad 1.3ʃ B.dl (max) T.m 0.0187Deflection angle (max) @ 2 GeV mrad 2System impedance Ω 15PFL voltage (max) kV 40Magnet aperture (w × h) mm × mm 140 × 59Beam aperture (w × h) mm × mm 140 × 53Kick rise time (1-99) % ns 46Kick fall time (99-1) % ns 92Kick length (max) ns 2600Kick flat-top ripple % ± 3Post kick ripple % ± 1.5
1/10/2014
Parameter unit KFA53 (SC) KFA45 (term.) KFA45 (SC)
Deflection angle (nominal) mrad 1.3 4.3 4.3ʃ B.dl (max) T.m 0.0187 0.0314 0.0601
Deflection angle (max) @ 1.4 GeV mrad 4.395 8.4
Deflection angle (max) @ 2 GeV mrad 2 3.38 6.5
System impedance Ω 15 26.3 26.3PFL voltage (max) kV 40 80 80
Magnet aperture (w × h) mm × mm 140 × 59 150 × 53 150 × 53
Beam aperture (w x h) mm × mm 140 × 53
Kick rise time (1-99) % ns 46 46 82Kick fall time (99-1) % ns 92 96 92Kick length (max) ns 2600 2600 2600Kick flat-top ripple % ± 3 ± 2 ± 3Post kick ripple % ± 1.5 ± 1.25 ± 1.5
LIU-PS ABT review 17
Schedule
1/10/2014
LIU-PS ABT review 18
LS2 Draft Schedule - LIU-PS activities (as presented in Chamonix by J. Coupard)
Consolidation work not included!
1/10/2014
• installation slot (PS tunnel) currently from August 2018 to mid November 2018 (3.5 month)
LIU-PS ABT review 19
Planned Schedule
1/10/2014
KFA-53
2014 LIU-TDR (done)
EOY 2014 Functional Specification available.
EOY 2014 Site for generator found. Cable routing confirmed. Cable choice confirmed.
Mid 2015 Detailed system design & Technical Specification available (approved).
EOY 2015 Integration done.1st drawings available. Long lead items ordered.
Q1/2016 All Drawings available. Production for “in-house” subcomponents started.
Q3/2016 Magnet and generator assembly starts.
Q2/2017 Assembly finished - Lab testing of complete system.
Q3/2017 Generator building available.
Q4/2017 Installation of Generator and PFL.
Q3/2018 Installation of magnet and cables
Q1/2020 HW/Beam commissioning
LIU-PS ABT review 20
Budget
1/10/2014
LIU-PS ABT review 21
Budget breakdown
• Total Budget is currently 1.940 MCHF.• Detailed breakdown to be done. • Costs for building or adaption work of
existing building not included so far.
1/10/2014
LIU-PS ABT review 22
Metrics per year in kCHF
APT Node LIU-PS 9.3 : New kicker design
Description Manufacture and commission KFA53
APT wu 113135
Wu responsible [email protected]
Budget code 99253
Metrics per year in kCHF
Year 2013 2014 2015 2016 2017 2018 2019 2020 Total
PV 116 423 633 618 150 1940
EV 0
New PV 0 423 749+250 618+50 150 1940+300
Spending Profile KFA53
Preliminary estimates for (minimum) building adaption work in red..
1/10/2014
Additional 10kCHF planned for commissioning (2019) in APT wu 113136
LIU-PS ABT review 23
Manpower / Resources
1/10/2014
LIU-PS ABT review 24
Manpower/Resources• No detailed manpower planning available yet.
• Conceivable that additional manpower is needed.
• Integration/design effort to be estimated and requested at design office.
• Assembly area for magnet and generator will be 867 (within controlled zone).
• HV-Test cage for system testing needed in 2017.
1/10/2014
LIU-PS ABT review 25
Other: Consolidation of KFA-45
• A refurbishment of the KFA-45 controls is envisaged as very similar KFA-53 controls needs to be developed anyway.
• The replacement of the KFA-45 SF6 cables is foreseen.
• Extension of cable shed for spare cable drum to be discussed.
1/10/2014
LIU-PS ABT review 27
Conclusions• KFA 53 requirements received. • Conceptual design for LIU-TDR delivered. • Functional Specification to be written until
December.• Resources estimate and Budget/Manpower
planning to be done.• Technical Specification to be delivered in mid
2015. • Delivery of KFA-53 magnet and generator as
foreseen in 2018.
1/10/2014
LIU-PS ABT review 28
Outlook w.r.t lessons learned during LS1
• KFA53 project goes in parallel with many other consolidation and LIU projects.
• Injector restart after LS1 showed many unplanned events and subsequently unscheduled interventions (source sometimes outside ABT responsibility!).
• Also commissioning of renovated systems showed that time for correction of non-conformities was necessary.
• Staged approach of accelerator ramp up looks excellent in theory but for hardware sections it means that troubleshooting for already running CPS overlaps with PS/SPS commissioning whilst there is still installation work in the LHC ongoing. This has to be covered by the same manpower.
• With combined efforts it was manageable for LS1 but it will be a totally different challenge to deliver and commission several completely new (and additional) systems beside the usual start up business (and changing staff).
1/10/2014
1/10/2014 LIU-PS ABT review 29
Reserve slides
1/10/2014 LIU-PS ABT review 30
LIU-PS ABT review 31
362• KFA28 and storage• Tx cables >50m • More a shed than a building (in case of usage to be completely
rebuild?)
1/10/2014
LIU-PS ABT review 32
365
1/10/2014
• Within TE-EPC responsibility.• Ok for Tx-cable length. • Extension possibility for cable
shed.
LIU-PS ABT review 33
356
1/10/2014
• Within TE-EPC responsibility.• OK for Tx-cable length. • Extension possibility for cable
shed.
LIU-PS ABT review 34
KFA 45
1/10/2014