Health sector programme

Introduction of energy efficient technologies into the Lithuanian hospitals providing perinatal and neonatal health care services - 19 MCHF

ProgressActivities related to preparation of technical projects,

technical supervision and other engineering services: • procurement documents for 2 tenders agreed with CPMA

(Kaunas Clinics, Klaipėda)• 8 public procurements announced (Vilnius Maternity Home (2),

Kėdainiai, Kaunas Clinics, Klaipėda, Panevėžys (2), P. Mažylis)• 8 contracts signed (Panevėžys (2), Kėdainiai (2), Klaipėda, Kaunas

Clinics, P. Mažylis, Vilnius Maternity Home)• 4 technical projects prepared (Kėdainiai, Panevėžys,

P. Mažylis, Vilnius Maternity Home )

Progress report 2013

ProgressActivities related to works:

• procurement documents for 3 tenders agreed with CPMA (Mažeikiai, Children‘s Hospital, Vilnius Maternity Home)

• 3 tenders announced (Mažeikiai, Children‘s Hospital, Vilnius Maternity Home)

• 1 works contract signed (Tauragė)

• 2 hospitals completed the implementation of contracts (without additional funding for modernization of internal power supply system) (Pasvalys, Vilnius City Clinical Hospital)

Activities related to programme management:

• additional energy-saving activities introduced into the scope of the programme (SC decision on 27 May, preliminary SECO approval on 4 July)

• additional hospitals included (Vilkaviškis, Raseiniai, Visaginas, Alytus, Šiauliai)

Progress report 2013

Health sector programme

Improvement of perinatal and neonatal health care services in Lithuania - 26,6 MCHF

Progress

Medical equipment• 13 contracts signed in 2013 (16 contracts signed in total).• 11 tenders lots (out of 27) failed as submitted proposals

did not meet the specific requirements defined in the ToRs. 5 of them re-launched, others are being reviewed.

• Procurement documents for 5 new tenders were submitted for coordination with the CPMA (3 approved).

• Procurement procedures for 7 tenders are on-going.• Delivery of equipment started in March and is being

continued.

Progress report 2013

Progress

Other procurements

• Tender on technical supervision services for development of computer data base launched in April 2013, envelopes opened on 15 May 2013. 2 proposals received. Evaluation on-going

• Contract on improvement of qualification and development of guidelines and protocols signed on 27 June 2013

• 2 hospitals are preparing tender documents for technical projects

• Technical projects (for repair works) for 2 hospitals are under preparation

• 1 hospital completed the preparation of technical project, tender documents for procurement of the repair works are being developed

• 1 hospital is starting implementation of works

Progress report 2013

Progress

Partnership plan• Partnership agreement with Geneva hospital signed in

February 2013.• Conference of neonatologists lectured by Lithuanian and

Swiss specialists organised in May 2013.• Coordination meeting to discuss the measures of the

partnership agreement to be implemented in 2013 – 2014 organised in May 2013.

Programme management

• Last partnership agreement with Santariškės Clinics signed in March 2013.

• 2 new beneficiaries included into the scope of the programe (Vilkaviškis, Raseiniai). Preparation of partnership agreements is in process.

• Facebook page for both health programmes created.

• Audit of the management and control system of health programmes has been conducted in July 2013.

Progress report 2013

Progress report 2013

Research and development sector • Research and development programme - 9,052 MCHF• Aim – to support joint research and institutional

partnerships projects

Progress

Open call for proposals:• Last 3 projects started implementation in January 2013 (8

projects started in 4Q/2012)• 11 consortium agreements were signed, 1 project on

institutional partnership was terminated• Implementation of the joint research projects is on-going

without any significant delays

Progress report 2013

Progress

Programme management:• Training seminar for beneficiaries was organised in

January 2013 (33 participants)• Audit of the Programme management and control system

was performed by the Internal Audit Unit of the Ministry of Education and Science in May – June 2013.

• Internal documents for the programme implementation were developed by the EA:• Procedure for Amendments and Breach of the Project

Implementation Agreements was prepared in January 2013

• Procedure for Performance of the on-the-spot checks was prepared in August 2013.

Progress report 2013

Scholarship Fund• Scholarships for advanced degree and post-graduation

programmes (mainly PhD) in Switzerland – 4 MCHF

Progress • 4th Call for proposals: 24 proposals evaluated, 13 –

approved for financing (total amount allocated – 1.035.750 CHF).

• 2,62 MCHF allocated during the four calls (1.152.277 CHF left for the last two calls).

• 5th (additional) Call for proposals launched on 2 September 2013.

Progress report 2013

Individual project • The creation and implementation of the system for video

transmission, recording and storage in courts - 1,77 MCHF• Overall objective – to create a system which allows arranging

remote court sessions, recording and preserving materials of these sessions in the electronic form

Progress• Draft tender documents for procurement of necessary hardware and

software submitted for the Swiss non-objection on 19 March 2013.• Tender launched on 15 May 2013.• Opening of the submitted proposals was held on 19 July 2013 (3

proposals received). • 1st meeting of the Evaluation Commission was held on 6 August

(compatibility with the qualification requirements was analysed). • On 20 August the suppliers submitted the requested additional

information on qualification. Tender proposals are being analysed.• Last meeting of the Public procurement commission organised on 3

September 2013.

Block grant• NGO Fund - 5,553 MCHF• Overall aims:

o to promote civil society’s contribution to economic and social cohesion as an important actor of development and participation

o to contribute to the further development of the NGO sector in Lithuania

Progress

Implementation of the Fund• 85 sub-project implementation agreements signed in

January – February 2013 (2 applicants refused from the allocated grant).

• 12 additional applications were approved for financing by the SC on 16 April 2013: • 10 sub-project implementation agreements signed in

June, 2013,• 2 sub-project implementation agreements signed in July

2013.• 1 sub-project completed in August 2013.

Progress report 2013

Progress

Fund management• 3 training seminars for the final beneficiaries conducted in

January 2013 (145 participants)• 89 procurement plans and 15 amendments to the plans

verified and confirmed by the EA in February – August 2013 • 237 payment claims verified by the EA in February – August

2013• 396 tender documents of the sub-projects verified by the EA

in February – August 2013 • 12 on-the-spot checks conducted by the EA in March -

August 2013

Progress report 2013

Operational plan (September 2013 to December 2014)

Improvement of perinatal and neonatal health care services in Lithuania

Medical equipment

• To submit tender documents (on stationary ultrasonic devices) for the Swiss non-objection (September 2013)

• To launch 2 new tenders in October 2013, 2 in December 2013, 2 in March 2014

• To re-launch 6 tender lots in October – December 2013.

• To sign 4 contracts in November – December 2013, 15 contracts in 2014 (4 in January, 3 in February, 3 in March, 1 in April, 2 in June, 2 in December).

• To continue the delivery of equipment to beneficiary hospitals

Operational plan (September 2013 to December 2014)

Improvement of perinatal and neonatal health care services in Lithuania

Computer database

• To sign the contract on technical supervision services (November 2013)

• To develop the computer database:

• To submit the tender documents for the review of CPMA (January 2014)

• To launch the tender (April 2014) and to sign the contract (June 2014)

Preparation of Technical projects and supervision

• To announce the tender (Kaunas clinical hospital – November 2013, Marijampolė – January 2014)

• To conclude the contract (Kaunas clinical hospital – March 2014, Marijampolė – May 2014)

• To prepare technical projects (Klaipėda – October 2013, Kaunas Clinics – December 2013, Kaunas clinical hospital – June 2014, Marijampolė –August 2014)

Operational plan (September 2013 to December 2014)

Improvement of perinatal and neonatal health care services in Lithuania

Repair works

• To announce tender (Panevėžys – September 2013, Klaipėda, Telšiai,

Mažeikiai – January 2014, Kaunas Clinics, Trakai – February 2014, Kaunas

clinical hospital, Marijampolė – November 2014 )

• To sign contract (Panevėžys – January 2014, Klaipėda, Telšiai, Mažeikiai –

May 2014, Kaunas Clinics, Trakai – June 2014)

• Complete works (Vilnius City Clinical Hospital - November 2013, Vilnius

Maternity Home – March 2014, Panevėžys – June 2014, Klaipėda, Telšiai,

Mažeikiai – October 2014, Trakai – June 2014)

Guidelines, protocols and professional competence improvement

• To prepare 23 methodologies (1/3 of total 70) till December 2013 (other till

end of 2014) and to conduct first training activities in 1Q/2014 (after

approval of first methodologies)

Vehicles

• Tender documents will be coordinated with CPMA (November-December

2013)

Operational plan (September 2013 to December 2014)

Improvement of perinatal and neonatal health care services in Lithuania

Programme management• To implement planned publicity measures (EAs, IB)• To organise „Journalist‘s breakfast“/opening event(s) (IB,

EA) in order to present the essential news on programme implementation

• To sign partnership agreements between the EA and newly included hospitals (Raseiniai, Vilkaviškis) (October - November 2013)

Partnership plan• To sign partnership agreements with Basel (3Q/2013) and

Zurich (4Q/2013) hospitals • To implement activities according to the partneship plan.

Operational plan (September 2013 to December 2014)

Introduction of energy efficient technologies into the Lithuanian hospitals providing perinatal and neonatal

health care services

Programme management• To procure publicity, audit, translation services (EAs)• To implement planned publicity measures (EAs, IB)• To organise „Journalist‘s breakfast“/opening event(s) (IB)

in order to present the essential news on programme implementation

• To sign project implementation agreements with the additional hospitals (October 2013)

Programme direct costs

Operational plan (September 2013 to December 2014)

Research and development programme

Programme manegement

• To complete and approve the internal Procedures for Estimation of joint research projects (IB) (November - December 2013).

• To conduct interim financial audit (by March 2014).

Implementation of Objective• To continue implementation of the joint research projects• To conduct expert evaluation of the projects’ annual reports

(January - February 2014)• To check the submitted payment claims, interim

implementation reports, tender documents

Operational plan (September 2013 to December 2014)

Individual project (on video conferencing system)

1 scenario (if the winner of the tender will be selected):

• In case the winner will be selected in mid-September, the contract should be signed in mid-October 2013 (planned duration: 134 days). Contract should be completed (equipment installed) in February – March 2014.

• To approach the Swiss side with a request to extend the project duration (September-October 2013).

• To start preparation for procurement of leaflets, stickers, organisation of the final conference and financial audit (October 2013).

• To conduct financial audit activities (2 months after the completion of the project activities, could be June - July 2014).

• To organise the closing conference (February 2014).

Operational plan (September 2013 to December 2014)

Individual project (on video conferencing system)

2 scenario (if the winner of the tender will not be announced):

• To approach the Swiss side with a request to extend the project duration (September-October 2013).

• To update the draft tender documents for procurement of hardware and software and agree with the CPMA (November 2013)

• To re-submit the draft tender documents for procurement of hardware and software to the Swiss side for no-objection (December 2013)

• To re-launch the tender on procurement of hardware and software (January 2013)

• To sign the contract (March – April 2014)

• To organise the closing conference (September - October 2014)

• To conduct financial audit activities (January – February 2015)

Operational plan (October 2012 to December 2013)

NGO Block grant

• To continue implementation of the sub-projects

• To continue verification of procurements plans, payment claims, tender documents

• To conduct on-the-spot checks (about 100 in the 1st half of 2014)

• To complete sub-projects‘ implementation (3Q/2014)

• To organise the final conference (4Q/2014)

Expenditures and Reimbursementsin 2013-2014

Swiss contribution, thousands CHF

Programme 2013 2014Eligible

expenditures

Reimbursement

Eligible expenditu

res

Reimbursement

1st health sector programme (Introduction of energy efficient technologies)

3.377.734,06

434.569,43 7.087.092,02

6.751.808,98

2nd health sector programme (Improvement of perinatal and neonatal health care services)

7.535.032,23

73.732,08 9.313.184 12.147.245,81

Research and development

964.545,94 1.138.324,26 3.202.400 2.393.390

Individual project (on video conferencing system)

1.672.405,51

79.933,42 26.350 1.670.050,25

NGO Fund 1.418.604,42

1.481.817,37 3.907.104,45

3.300.000

Technical Assistance Fund (TAF)

109.029,75 62.661,67 200.967,01 109.029,75

Total 15.077.351,91

3.271.038,2323.737.097,48

26.371.524,79

Thank you

Ministry of Finance of the Republic of Lithuania

Lukiškų str. 2, LT-01512 Vilnius, LithuaniaTel. + 370 5 239 0000, Fax + 370 5 279 1481

E-mail: [email protected]

Central Project Management Agency

S. Konarskio str. 13, LT-03109 Vilnius, LithuaniaTel. +370 5 251 4400, Fax. +370 5 251 4401

E-mail: [email protected]