Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
-
Upload
jose-divas -
Category
Documents
-
view
223 -
download
0
Transcript of Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
1/120
National Cheng Kung University (NCKU)
International Program in Civil
Engineering and Management (ICEM)
Masters Thesis
Linkage between Scheduling Process Maturity and Schedule
Performance of Construction Projects
Student: Jos Mari Divas
N66987123
Advisor: Andrew S. Chang
July, 2011
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
2/120
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
3/120
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
4/120
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
5/120
i
ABSTRACT
Delays are often found in construction projects in spite of numerous research
aimed at improving schedule performance. Studies address the factors affecting
project success and establish good practices to help in scheduling process. Some argue
the schedule problems are lack of support between management and project
participants, and the misuse of the scheduling methods and techniques, while others
state that is because of an existing gap between theory and practice.
This research studies the relationship between scheduling process maturity and
schedule performance. It first reviews the factors that are of critical influence on
schedule performance. A questionnaire was designed based on four parts composed of
these schedule factors: schedule theory, management theory, project participants and
project environment. The questionnaire was sent out and collected 93 sets of data from
owners, consultants and contractors in both Belize and Taiwan.
The analysis results reveal the views of project participants regarding various
scheduling aspects. Contractors replies have a better linkage with schedule
performance. Basic scheduling processes are most frequently and well used by project
participants while having a moderate relationship with schedule performance. The
scheduling formality of the project participants has a moderate relationship with project
delays. Advance scheduling processes are seldom used because they are not familiar
to participants are seldom practiced.
Keywords: Schedule theory, project management, schedule management, scheduling
process, schedule performance.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
6/120
ii
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
7/120
iii
93
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
8/120
iv
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
9/120
v
ACKNOWLEDGEMENTS
I would firstly like to give praise to Jehovah god for patience, guidance and
wisdom.
Secondly, thanks to the International Cooperation and Development Fund (ICDF)
for the opportunity to study in Taiwan at National Cheng Kung University. My
appreciation also goes to the faculty at Civil Engineering and Management, not
forgetting my thesis advisor, Professor Andrew Chang, for his kind guidance
throughout the investigation process. I would also like to extend my gratitude to my
classmates for helping with Chinese lessons.
I also want to thank my family and loved ones for the unconditional support
specially my mother, Gloria Estela Flores.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
10/120
vi
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
11/120
vii
TABLE OF CONTENT
ABSTRACT ............................................................................................................... I
........................................................................................................................ IIIACKNOWLEDGEMENTS ...................................................................................... V
TABLE OF CONTENT .......................................................................................... VII
LIST OF TABLES ................................................................................................... IX
LIST OF FIGURES .................................................................................................. X
CHAPTER 1 INTRODUCTION................................................................................ 1
1.1 Motivation ............................................................................................... 2
1.2 Research Objectives ................................................................................. 3
1.3 Research Scope and Limitation ................................................................ 4
CHAPTER TWO LITERATURE REVIEW ............................................................... 9
2.1 Schedule Theory .................................................................................... 10
2.1.1 Planning, Scheduling and Control................................................ 10
2.1.2 Scheduling Methods and Techniques ........................................... 13
2.2 Management Theory .............................................................................. 15
2.2.1 Project management .................................................................... 15
2.2.2 PM Process and Benchmarking ................................................... 16
2.3 Project Participants Capabilities ............................................................. 18
2.3.1 Human Factors ............................................................................ 18
2.3.2 Skills, Training and Experience ................................................... 19
2.4 Project Environment .............................................................................. 19
2.4.1 Owners Sophistication ................................................................ 20
2.4.2 Project Complexity ...................................................................... 20
2.4.3 Schedule Specification ................................................................ 22
2.4.4 Culture ........................................................................................ 23
CHAPTER THREE FACTORS AFFECTING SCHEDULING PROCESS .............. 25
3.1 Scheduling Process Problems ................................................................. 25
3.1.1 Personnel..................................................................................... 26
3.1.2 Procedures ................................................................................... 28
3.1.3 Problems in Developing Countries .............................................. 29
3.2 Initial Survey in Belize........................................................................... 32
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
12/120
viii
3.2.1 Preliminary Results ..................................................................... 33
3.2.2 Informalities in the Industry ........................................................ 36
CHAPTER FOUR SURVEYING SCHEDULE PRACTICE LEVELS ANDRESULTS ................................................................................................................ 39
4.1 Establishing Schedule Practice Levels .................................................... 39
4.1.1 Effort to establish the scheduling practice .................................... 39
4.1.2 Maturity Level Assignment ......................................................... 41
4.2 Questionnaire Design ............................................................................. 42
4.2.1 General Information .................................................................... 42
4.2.2 Project Environment .................................................................... 43
4.2.3 Scheduling Process ...................................................................... 44
4.2.4 Schedule Performance ................................................................. 45
4.3 Survey Process and Results .................................................................... 46
4.3.1 General Information .................................................................... 47
4.3.2 Project Environment .................................................................... 51
4.3.3 Scheduling Process ...................................................................... 57
4.3.4 Schedule Performance ................................................................. 64
CHAPTER FIVE LINKAGE ANALYSIS OF SCHEDULING ASPECTS ............ 71
5.1 Linkage Strategy ......................................................................................... 71
5.1.1 Relationships to be Identified ...................................................... 71
5.1.2 Regressionandcorrelation analysis ............................................. 73
5.2 Relationship Identification ..................................................................... 74
5.2.1 General Information-Schedule Process and Performance ............. 75
5.2.2 Project Environment Scheduling Process .................................. 78
5.2.3 Project Environment Schedule Performance ............................. 82
5.2.4 Scheduling Process Schedule Performance ............................... 85
CHAPTER SIX CONCLUSIONS AND RECOMMENDATIONS ........................ 89
6.1 Conclusions ........................................................................................... 89
6.2 Recommendations .................................................................................. 90
REFERENCES ........................................................................................................ 93
Appendix A: Initial Survey Questions about Scheduling Problems ................. 97
Appendix B: Questionnaire (English Version) ................................................... 98
Appendix C: Questionnaire () .............................................................. 101Appendix C: Summary of Questionnaire Survey Results ................................ 104
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
13/120
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
14/120
x
LIST OF FIGURES
Fig. 1.1 Gap between schedule theory and practice .................................................... 3
Fig. 1.2 Research Process .......................................................................................... 6Fig. 2.1 Schedule theory and practice aspects ............................................................ 9Fig. 2.2 Planning and Scheduling Phases (AACE, 2006) ......................................... 11Fig. 2.3 Scheduling Process (PMI, 2007) ................................................................. 11Fig. 2.4 Scheduling model (PMI, 2007) ................................................................... 13Fig. 2.5 Links among processes in a phase (PMBOK, 2004) .................................... 16 Fig. 2.6Project processes and knowledge areas (PMBOK, 2004) ............................ 17 Fig. 2.7Drivers of project complexity (Vidal and Marle, 2008) ............................... 21Fig. 3.1 Scheduling process problems ...................................................................... 26Fig. 3.2 Critical factors affecting project schedules .................................................. 33Fig. 3.3 Most common scheduling tool .................................................................... 33Fig. 3.4 Pre-job meeting for reviews of project scope .............................................. 34Fig. 3.5 Project Participant that affect Project Schedule ........................................... 34Fig. 3.6Are delays inevitable .................................................................................. 35Fig. 3.7Schedulers as part of project ....................................................................... 35Fig. 3.8Attention to scheduling ............................................................................... 36Fig. 3.9 Consensus of scheduling ............................................................................. 36Fig. 3.10 Average update cycle ................................................................................ 36Fig. 3.11 More challenging phase ............................................................................ 36Fig. 4.1 Schedule Practice Levels ............................................................................ 41Fig. 4.2 Respondent organizations ........................................................................... 47
Fig. 4.3 Relative size of organization ....................................................................... 48Fig. 4.4 Positions of respondents ............................................................................. 49Fig. 4.5 Number of years of experience ................................................................... 49Fig. 4.6Scheduling as part of the respondents job description ................................ 50Fig. 4.7Source of scheduling knowledge ................................................................. 51Fig. 4.8Average project duration ............................................................................. 52Fig. 4.9 Project complexity increasing efforts to project schedules........................... 52Fig. 4.10 Owners view on project schedule ............................................................. 53Fig. 4.11 Owners knowledge and experience effect on project scheduling .............. 54Fig. 4.12 Project participants view of project planning and scheduling ................... 55Fig. 4.15 Specifications similarity for projects ......................................................... 56
Fig. 4.15 Schedule requirements affecting scheduling process ................................. 57Fig. 4.16Types of scheduling method often used ..................................................... 58 Fig. 4.17Type of scheduling tool often used ............................................................ 59Fig. 4.18Use of WBS for planning .......................................................................... 59Fig. 4.19 Use of sequencing relationship other than finish-start on PDM .............. 60Fig. 4.20 Use of CPM techniques for project schedule ............................................. 61 Fig. 4.21 Use of resource loading on project schedules ............................................ 62Fig. 4.22 Use of earned value analysis ..................................................................... 62Fig. 4.23 Update cycle ............................................................................................. 63Fig. 4.24 Calculations of time to complete upon project updating ......................... 64Fig. 4.25 Average schedule delay ............................................................................. 64
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
15/120
xi
Fig. 4.26Cost spent toward project schedules .......................................................... 65Fig. 4.27Scheduling as a result of good planning .................................................... 66Fig. 4.28Opinions of project schedule improving communication ........................... 67Fig. 4.29 Schedules being used for project time control ........................................... 68 Fig. 4.30 Overall satisfactions with current scheduling practice ............................... 68
Fig 5.1 Scheduling aspects tested for relationships .................................................. 72
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
16/120
xii
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
17/120
1
CHAPTER 1 INTRODUCTION
The need for scheduling in the project management can be argued from
economical, technical and continued control points of view (Cole, 1991). Research
has shown that where scheduling is fairly and consciously practiced throughout the
project life cycle, the project results in favorable schedule and cost performance
(Griffith, 2005). However, schedule practices are still deficient in the construction
industry. One main reason is that there is a gap between the schedule theory and
general practice.
Project schedule is essentially a management tool used as basis for decision
making by project participants. They reflect the schedule baseline and the subsequent
changes as project progresses (Hartley, 1993). The main objective of schedules is to
provide a roadmap that represents how and when the project will deliver the products
defined in the project scope (PMI, 2007). Schedules provide a holistic view of the
project while communicating the project scope both vertically and horizontally to all
participants (PMI, 2007; Sappe, 2007).
Schedules can be an effective management tool when good practices are utilized in
the scheduling process. However this depends on competence and level of maturity of
project participants. According to Kerzner (2009), maturity implies that the proper
foundation of methods, tools, techniques, and processes exist. It generally comes from
experience gained from exposure to several types of project.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
18/120
2
1.1 Motivation
Construction projects are getting more complex and difficult (Chan et al, 2004)
hence the need for the use of project scheduling cannot be over emphasized. In spite of
the vast amount of research related to scheduling, most research is related to advances
in methodologies and techniques, while others research the factors affecting schedule
performance (Herroleon, 2005). However, the scheduling process involved and
schedule performance are seldom linked.
One of the most widely researched topics in project schedule performance is the
concept of project success and the criteria to measure it (Iyer and Jha, 2006). Chan et
al., (2004) categorized the factors affecting project success into four groups:
project-related, procurement-related, project management and project
participant-related factors.
In spite of all these efforts, projects are still suffering delays and going over budget.
Dos Santos (2002) reveals that part of the problem stems from the partial application of
theory, gap in knowledge amongst practitioners and the lack of support from the
organizational structure. Additionally, high reliability cannot be achieved when the
schedule preparation process is separated from the project operational reality (Son and
Rojas, 2011). Together this implies that the lack of linkage between applicable theory
and current practices make schedule practice inefficient.
Figure 1.1 shows the existence of a gap between the schedule theory and reality or
practice. The theoretical aspects are scheduling and management theory, while the
project participants and the project environments compose the reality of the schedule
practice.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
19/120
3
Fig. 1.1 Gap between schedule theory and practice
Efforts are being established to better bond and link these four aspects. The Project
Management Institute (PMI) has added a college of scheduling as part of its
organization (Galloway, 2006). This was done in an effort to standardize and achieve
consistency in its application, requirements for schedule development, and use in the
construction industry. PMI developed the Practice Standard for Scheduling Manual
to regulate the scheduling practice (Galloway, 2006), in addition to providing the
Project Management Book of Knowledge (PMBOK) which serves as a guide to project
management.
1.2 Research Objectives
The objective of this research is to analyze the linkage between scheduling process
maturity and schedule performance in the construction industry. This research aims to
find a linkage by evaluating responses from a survey in areas of project environment,
scheduling process and schedule performance. As a secondary objective, by
assigning numeric levels to the responses it will be possible to define the general
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
20/120
4
schedule maturity level of the respondents. The responses level will indicate which
areas are in more need of attention by the respondents. In return recommendation can
be given on specific areas to increase the scheduling process maturity.
Additionally the level maturity can be used to compare and rank the level of
schedule maturity between the two countries and surveyed groups of project
participants. The results of such research should enable individual to promote
schedule maturity and schedule consciousness in construction project. This will
enhance the scheduling process and consequently should improve performance.
Though scheduling process maturity may be linked to schedule performance, this is
limited to the commitment and competence of the scheduler and other direct project
participants.
1.3 Research Scope and Limitation
This research intends to surveys the scheduling practices of construction
professionals in the Belize and Taiwan. The analysis and results provide insight of the
scheduling process maturity currently being practiced. The research objective and
method outline the process of this research and provides the objective aimed to
achieve.
During this investigation some limitations were encountered. Some of these
limitations are:
- Sample size: though the number of total responses totals 93, this includesresponses for both Belize and Taiwan. The responses are not even
distributed among owners, consultants, and contractor, and though the
responses represent the scheduling practice in both countries, is some areas
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
21/120
5
the sample size is too small to find a significant relationship between the
schedule process and the schedule performance. The results of this
research may be used only as reference material in identifying the level of
maturity of Belize and Taiwan given the size of the sample size
- Lack of prior research: previously, linking the respondents capabilities withthe schedule usage was researched. However linking the schedule process
with schedule performance has not yet been researched, therefore this
research is more exploratory, than explanatory.
- Methodology used in data collection: the main focus of this research isbased on the questionnaire sent to Belize and to Taiwans project
participants. A better approach would have being to self fill out the
questionnaire in face to face interviews this would probably have yielded
better results.
1.4Research Method and ProcessThe main research methods used were an initial survey of semi-open question
interviews and a questionnaire survey. The initial survey rendered a picture of the
scheduling practices problems in Belize. The initial survey was followed by a Likert
scaled questionnaire. The questionnaire was developed after schedule literature
review and analysis of the initial survey. This questionnaire was distributed to owners,
consultants, and contractors both in Belize and Taiwan. The respondents selected
from Belize were all those listed in the Association of Professional Engineers of
Belize. While in Taiwan the respondents that have certain relationships with NCKU
were asked to participate in this survey.
The questionnaire was divided into four parts. The first part addresses
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
22/120
6
background of the respondents: their job positions, types of organization, and sources
of scheduling knowledge and whether scheduling is a major or minor job. The second
covers the project environment in which scheduling is practiced. This includes the
views of the project participants toward project planning and scheduling, project
complexity and scheduling specifications issues. Part three addresses the scheduling
process practiced in the industry. This includes the scheduling tools and methods in
developing and controlling of schedules. The final part covers the of project schedule
performance: the average delays, cost spent, and the overall satisfaction the respondent
have of scheduling practice.
This research process can be summarized into five general steps as seen in Figure
1.2.
Conclusion and recommendation
Step 1
Step 2
Step 3
Step 4
Step 5
Literature review and initial survey
Identification of the problems related to scheduling
process
Questionnaire design and survey
Data analysis and linkage
Fig. 1.2 Research Process
1.5Thesis StructureThis thesis contains six chapters. Chapter 1 is the introduction of this thesis which
contains the motivation, research objectives and research scope and limitation and
research methodology. Chapter 2 contains a summary of the literature read and
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
23/120
7
reviewed for the development of this thesis. Chapter 3 presents an analysis of the
general schedule problems encountered in Belize. Chapter 4 describes the
questionnaire design and development. Chapter 5 presents the results and the efforts
using correlation to establish a linkage between the scheduling process and the
schedule performance. Finally, Chapter 6 presents the conclusion and
recommendation of this research.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
24/120
8
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
25/120
9
CHAPTER TWO LITERATURE REVIEW
Researches has shown that scheduling practice involves integration of
scheduling methods and techniques, management procedures and guidelines, the
experience of the project participants, and the skills to adapt to existing project
environment. Figure 2.1 shows these schedule aspects.
ParticipantCapabilities
ProjectEnvironment
ScheduleTraining
SchedulingExperience
SchedulingSkills
OwnersSophistication
ProjectComplexity
SchedulingSpecification
Culture
Schedule aspects
ScheduleTheory
ManagementTheory
Planning,SchedulingControl
SchedulingMethods andTechniques
ProjectManagement
ProjectManagementProcess andBench Marking
Fig. 2.1 Schedule theory and practice aspects
This chapter reviews the four aspects of schedule theory and practice as
shown in Figure 2.1. Section 2.1 reviews schedule theory, Section 2.2 management
theory, Section 2.3 project participants, and Section 2.4 the Project-Related
environment.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
26/120
10
2.1 Schedule Theory
Much has been written about project scheduling dealing with the mechanics of
creating the schedule document itself (Hartley, 1993). This happened as extensive
documentation requiring the need for planning and schedule methodologies (Cole,
1991).
Scheduling has been around for sometimes. Henry Gantt first used bar chart as
a mean to represent and sequence activities in early 1900s (Kerzner, 2009). Bar
charts are advantageous in that they are easily understood and represent a picture of
the project in progress. When a project becomes larger and complex, the bar chart
has a disadvantage (Kerzner, 2009). This gives way to the CPM and PERT scheduling
methods which were introduced in the late 1950s, and since then they have been
vastly researched (Herroelen, 2005). Nonetheless, after their establishment, the
basic principles of project scheduling and control have gone unchanged for the major
parts. However, their application in the construction industry has still not received
100% acceptance or consistency (Galloway, 2006).
2.1.1 Planning, Scheduling and Control
The American Association of Cost Engineers (AACE, 2006) provides various
definitions for scheduling. A time-sequence of activities and events that represent
and operating timetable, specifying the relative beginning and ending times of
activities and the occurrence of events is a better suited definition. Figure 2.2
define Planning and Scheduling as per AACE (2006).
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
27/120
11
Planning and Scheduling Phases
Planning ScheduleDevelopment
Scheduling Control
Fig. 2.2 Planning and Scheduling Phases (AACE, 2006)
Scheduling commonly starts at the planning phase and continues to the
execution as a control system. Furthermore it has its place and time after project
completion, usually in court when conflicts arise regarding the completion time
(Gould and Joyce, 2009). Nonetheless for schedules to be rendered useable for
planning, executing, monitoring and communication, it should adhere to standard
practices (PMI, 2007).
Project Start
SelectingScheduling
Method
Instances ofProject
Schedules
Enter ProjectScecific Data
SelectScheduling
Model
ProjectSchedule
Updateand
Status
ProjectComplete
Fig. 2.3 Scheduling Process (PMI, 2007)
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
28/120
12
As Figure 2.3 shows, the scheduling process includes selecting a scheduling
method and tool, incorporating project specific data to develop a project specific
project schedules (Fig. 2.4) (PMI, 2007)
A schedule model should include five major processes in developing the
project schedule (PMBOK, 2004): activity definition, activity sequencing, activity
duration estimating, schedule development, and schedule control. Once developed,
the schedule model is regularly updated to reflect progress and changes, in areas such
as scope of logic (PMI, 2007).
Given that the construction industry is dynamic in nature, project planning
cannot be consider as a straight-through process but rather it is best thought of as a
planning cycle (Chan et al., 2004). Project planning starts early and continues
throughout the various phases of the project life cycle. Planning encompasses
defining the project objectives and determination of activities, selection of methods,
resources and establishing responsibilities to accomplish completion as required
(AACE, 2006). The methods, tools and techniques play important role in both the
planning and scheduling phases. This selection depends on the project
characteristics, the participants involved and the environment (Hartley, 1993).
The purpose of the schedule development is to implement the project schedule
by converting the project plan into a logical arrangement and sequence of activities.
During the schedule development phase, the project activities are refined, activity
durations are determined, activity relationships and sequencing are detailed, and key
milestones are confirmed. Resource and cost may be included in the schedule
activities (AACE, 2006). Construction managers need to develop a schedule for
directing and controlling resources (Lu and Lam, 200).
The PMBOK(2004) considers that schedule control is concerned with
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
29/120
13
influencing the factors that create schedule changes to ensure that changes are agreed
upon, provided that the schedule has changed, and managing the actual changes
when and as they occur.
Nothing goes according to plan, and schedules have to be modified.
Excessive change orders can cause changes in the planned schedules and,
consequently, cause significant disruption to construction projects (Long et al., 2003).
Thus the reason exists to keep a good control on project schedules. Proper planning
and control are usually among the top five factors required to avoid project delays
(Tumi et al, 2009).
2.1.2 Scheduling Methods and Techniques
Selecting scheduling methods occurs in the early part of the scheduling process.
The scheduling methods provide the framework within which the scheduling model is
developed with its specific tool and techniques applicable to manipulate the project
information, as seen in Figure 2.4 (PMI, 2007).
Scheduling
Method
Scheduling
Tools
Schedule
Model
Project
Information
Output
ProjectSchedule
Fig. 2.4 Scheduling model (PMI, 2007)
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
30/120
14
The PMBOK (2004) states the usual and accepted scheduling method: the
ADM (AOA) and PDM (AON). Hinze (2008) also mentions the LOB for repetitive
vertical and horizontal construction, and the bar chart as the popular method of
sequencing activity at an initial stage of the scheduling process.
Most efforts in research have been directed to the developing of
methodologies and techniques for optimizing resources for single project. However
practice has shown that many of these methodologies have proven to have limitations
and in real cases project managers often find themselves managing up to four projects
on average (Herroleon, 2005).
The use of project scheduling techniques early in the project correlates with
better project outcome (Griffith, 2005). These techniques are clearly defined during
the schedule development stage. PMBOK (2004) mentioned the CPM, PERT and
GERT as mathematical analysis techniques to calculate the delivery dates of the
activities. Thought some scheduling techniques are better than others, all have their
advantages and disadvantages (Kerzner, 2009).
The scheduling tool is used to assemble the schedule model and provide
means of adjusting various parameter and components that are typical during
modeling process. The scheduling tool contains the scheduling components and the
rules for relating and using the components to represent the process for completing a
project. This is easily visualized by running scheduling software tool (PMI, 2007),
though other tools have the form of forms and templates (PMBOK, 2004).
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
31/120
15
2.2 Management Theory
Modern project management appeared during World War II and was initially
used for large military and construction projects (Vidal and Marle, 2008). Though its
growth and acceptance has changed significantly since its appearance, these changes
continue into the twenty-first century (Kerzner, 2009).
2.2.1 Project management
Project involves doing something that has not being done before and is unique
(PMBOK, 2004). Project management (PM) is the planning, organizing, directing,
and controlling of company resources for a relatively short-term objective that has
been established to complete specific goals and objectives (Kerzner, 2009).
PMBOK (2004) describes PM as the application of knowledge, skills, tools and
techniques to project activities to meet the project requirements established. Others
perceive management by project as temporary organizations for the performance of
complex processes, such as contracts for external clients (Garies and Huemann,
2000).
PM has gone through three major development phases (Kerzner, 2009).
Initially line manager used the concept of over-the-fence management to manage
project. Executives began searching for new management techniques and
organizational structures that could be quickly adapted to a changing environment.
Thereafter, companies in general consensus begun to realize that PM was a necessity
not a choice.
Projects are getting bigger and invariably more complex than ever (Baccarini,
1996), and the project team is required more than ever to more competent in PM.
Corporate organizations are in favor of PM tools and practices that are well suited for
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
32/120
16
todays rapidly changing industry. This however poses a question, how well is the
organization using these tools and practices. To answer to this question the Project
Management Process Maturity (PM2) model measures the relative PM maturity level
of an organization (Kwak and Ibbs, 2002).
2.2.2 PM Process and Benchmarking
PMBOK (2004) define the PM processes in five groups. PM processes are:
- Initiating: authorizing the project or phase.- Planning: defining and refining objectives and selecting the best of the
alternatives courses of action to attain the objectives that the project was
undertaken to address.
- Executing: coordinating people and other resources to carry out the plan.- Controlling: ensuring that project objectives are met by monitoring and
measuring progress regularly to identify variance from plan so that
corrective action can be taken when necessary.
- Closing: formalizing acceptance of the project or phase and bringing it toan orderly end.
Fig. 2.5 Links among processes in a phase (PMBOK, 2004)
InitiatingProcesses
ClosingProcesses
ControllingProcesses
ExecutingProcesses
PlanningProcesses
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
33/120
17
Each of the five PM processes in Figure 2.5 includes nine knowledge areas as
shown in Figure 2.6.
Fig. 2.6Project processes and knowledge areas (PMBOK, 2004)
Despite the broad usage of PM tools and practices, organizations are often
confused and uncertain about their current application of such tools. The five-level
PM2 model has become the basis to evaluate and position an organization current PM
maturity and level of sophistication. The model motivates organizations and
people to accomplish higher and more sophisticated PM maturity by a systematic and
incremental approach. It also provides and guides the necessary processes and
requirements to achieve a higher PM maturity level. It allows an organization to
determine the strength and weakness of current PM practices and focus on the weak
PM practices to achieve higher PM maturity.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
34/120
18
2.3 Project Participants Capabilities
Project participants related problems that reflect the deficiency in project
scheduling appears in various forms. The often cited problems or reasons for
project failure that are related to the participants are: inadequately trained and/or
experience project managers; poor leadership; failure to adequately identify,
document and track project requirement; poor planning process; inadequate or
misused methods; inadequate communication, including project tracking and
reporting (Herroelen, 2005). Therefore it is absolutely necessary that practitioner be
competent, capable and possesses knowledge in management, this can only be
achieved by training, possessing former experience and planning skills.
2.3.1 Human Factors
There are few things more disheartening than to see an untouched, project
schedule rolled in a corner or even being used as wall paper in a project office. This
is a usual occurrence of good intentions, but failed scheduling efforts (Hartley, 1993).
Project participants must be proactive and committed to meet time and cost
requirements as planned. In order to achieve project success the project team is
required to possess motivating, organizing and planning skills (Chan et al., 2009). Be
able to coordinate resources and labor through continued involvement in the project.
The adaptability of project participants to changes in the project plan is essential (Iyer
and Jha, 2009).
Iyer and Jha (2009) stated that a competent project manager has the technical
and monitoring capabilities for effective leadership. Furthermore, the project
manager should be able to delegate authority and responsibilities to the project team
and all other project participants involved in the project execution. Project
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
35/120
19
managers competence is related to the skills, training and experience that he
possesses.
2.3.2 Skills, Training and Experience
Every participant has skills and knowledge that may be useful in developing
the project plan (PMBOK, 2004). Given that all construction projects are different,
the use of skills play a significant role in identifying the aspects that add value to
project scheduling (Chan et al., 2004). Iyer and Jha (2006) emphasized the
importance of project planning and suggested that project planning be carried out by
skilled individuals.
Many organizations acknowledge the need to improve the level of knowledge
and skills in the construction community by providing training in the form of
continuing education, workshops, lunch and other learning programs (Buziak, 2008).
Training of highly regarded that PMI has recently added a college of scheduling
(PMICOS) as part of it organization (Galloway, 2006b).
The key to project success is to apply knowledge, experience and intuition to
the project plan, and then attempt to execute according to plan (PMI, 2007). Chan et
al. (2004) mentioned that previous related experience is key to project success.
Project participants experience is the backbone for the development of planning and
scheduling (AACE, 2006).
2.4 Project Environment
Project scope is widely accepted to be a contributing factor to the project
success. It is thought to be a useful indicator of the expected project construction
timeline. The attributes related to the project scope are: type of project, nature of
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
36/120
20
project, complexity, and project size (Chan et al., 2004).
Construction projects are unique and temporary in nature and so their
management. This uniqueness in project activities often requires consumption of
initial time getting used to the project and the demands of the project scope. Though
the commitment of the all the project participants is essential to project completion,
the sophistication (competence) of the owner weighs in project schedule success (Iyer
and Jha, 2006).
2.4.1 Owners Sophistication
Taking timely decisions, regular monitoring and feedback of the project progress
is some of the characteristics of the owners competence (sophistication). It has
been found that in projects where the owners are technically competent and
financially strong good project performance is achieved. On the other hand,
incompetent owners proceed with projects without proper planning and are not able to
recruit competent personnel to look after their interests (Iyer and Jha, 2006).
Indecisiveness or slow decision by owners is also of great concern to both consultants
and contractors in respect to timely completion of projects (Odeh and Battaineh,
2002). All this results in an unsuccessful outcome as far as schedule is concerned
(Iyer and Jha, 2006).
2.4.2 Project Complexity
The construction process may be considered the most complex undertaking in
any industry. The construction industry has displayed great difficulty in coping with
the progressive increase in complexity of construction projects (Baccarini, 1996).
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
37/120
21
However complexity of project schedule is different from the complexity of the
project itself. The complexity of the project schedule indicates high interconnection
between activities. When the resources needed for the project are widely spread, the
project is considered complex. Project complexity can be an important criterion in
the selection of an appropriate project organization form. Conversely, the complexity
of a project can affect the projects objectives of time, cost, and quality; it is
frequently used as a criterion in the selection of a suitable project procurement
arrangement (Nassar and Hegab, 2006).
Project complexity can be characterized through some factors that can be
classified into four categories as see in Figure 2.7. The project size is a project
complexity factor. Identifying the parameters that characterize the size of the
project system gives a first list of drivers of project complexity. A project system
must be over a minimum critical size to be considered a complex system. Factors
that are contemplated for the project size are: the duration of project, number of
activities, resources, decisions, departments, investors, objectives, stakeholder and the
largeness of scope.
Project Complexity
Project interdependence
Elements of contextProject Variety
Project Size
Fig. 2.7Drivers of project complexity (Vidal and Marle, 2008)
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
38/120
22
Project variety relates closely to the diversity of the number of emergent
properties (factors) and is a necessary condition for project complexity. The factors
underlined are: diversity of staff experience, and variety of financial resources,
organizational interdependencies, organizational skills, stakeholders, resources
manipulated, project components, technical skills and dependencies.
Project interdependence is likely the greatest driver of project complexity.
Components of complexity will depend on and influence each other, making it
problematic in project scheduling. The following components make up the
interdependencies within a project system: interdependencies between the
components of the product, resource and raw material interdependencies,
specification interdependencies, amongst others.
Project complexity cannot be neither analyzed nor managed without
considering the elements of project context. The project context cannot be
transferred from project to project with different institutional and cultural
configuration. Elements of contextuality are: competition, culture, environment
complexity, local laws and regulation, public agenda and existing technological
innovation.
2.4.3 Schedule Specification
A critical step in the execution of a construction project is the selection of
planning and scheduling specification clauses to be included in the construction
contract (Ballast and Popesco, 2001). According the PMI (2007), a specification is a
document that specifies, in a complete, precise, verifiable manner, the requirements,
design, behavior, or other characteristics of a system, component, product, result or
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
39/120
23
service and, often the procedures for determining whether these provisions have been
satisfied.
Currently the scheduling specifications have become over burdened with the
challenge of addressing the entire range of roles now encompassed by the activity of
scheduling. As a result, scheduling specification advancements over the years have
been extremely uneven, resulting in contract specification with schedule provision
ranging from two sentences to two dozen pages. This lack of standards and wide
variety of scheduling methodologies are the reasons for establishing standards and
best practices (Levin, 2006).
2.4.4 Culture
Culture is important to determine and analyze the ways of perception,
evaluation and application of techniques and technology in society (Kuruoglu and
Ergen, 2002). Culture is the totality of socially transmitted behavior patterns, arts,
beliefs, institution, and all other products of human work and thought. Every project
must operate within a context of one or more cultural norms. This area of influence
includes political, economic, demographic, educational, ethical, ethnics, religious,
and other areas of practice, belief, and attitudes that effects the way people interact
(PMBOK, 2004).
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
40/120
24
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
41/120
25
CHAPTER THREE FACTORS AFFECTING SCHEDULING
PROCESS
Schedule delays and cost over runs are not a recent phenomenon (Son and
Rojas, 2011). The dynamic and unique nature of construction projects makes it
difficult to plan, schedule and control. Most research in factors affecting scheduling
has been taken up by developed countries. The difference in context, the
applicability in developing countries may not be the same and is therefore in need of
exploration (Iyer and Jha, 2006). Kuruoglu and Ergen (2002) explained that
developing societies do not approach problems the same ways developed societies do.
Though this may be partly due to cultural differences, other factors have significant
effects.
This chapter explores the common problems affecting the scheduling process
and provides a background of the problems. A brief summary of an initial survey is
presented about the schedule phenomena in the Belizean construction industry.
3.1 Scheduling Process Problems
Project schedules by nature are evolutionary documents and contain varying
amounts of detail. As a project progresses, more information is available and the
schedule is appropriately refined to reflect the available data (Hartley, 1993).
Planning and scheduling cannot be though as a one-time task, but rather a process
throughout the life of the project (PMBOK, 2004).
The dynamics of the project, the characteristics of the participants and the
nature of the environment constitute the factors that constantly influence changes and
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
42/120
26
the schedule performance. However, Hartley (1993) commented that successful
planning and schedule development and control process is inherently affected by a
scheduling system. This scheduling system consists of the characteristics of
personnel and procedures that cause problems in the scheduling process as shown in
Figure 3.1. This will determine how well the schedule will serve as an efficient
management tool (PMI, 2007).
Personnel Procedures
Lack of commitment,
competence and
coordination
Lack of experience and
knowledge
Lack of communication
Poor Management
Improper Planning
Improper use of
scheduling methods
and techniques
Lack of standards and
schedule specification
Improper use and
knowledge of software
Fig. 3.1 Scheduling process problems
3.1.1 Personnel
Lack of commitment, competence, and coordination
Project managers competence, commitment of the project participants,
owners competence and coordination among project participants predominantly
contribute towards success of the project. Competence enables the project
participants to make appropriate decisions on time including corrective actions if
necessary. Commitment motivates the team toward successful and on-time
completion of the project. While, coordination keeps the flow of information,
resources and skills among the various participants engage in a project (Jha and Iyer,
2007).
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
43/120
27
Lack of experience and knowledge
Individuals with construction knowledge and experience should carry out the
early project planning so that interference between design and construction can be
avoided (Nima et al., 2002). Hartley (1993) stated that without the involvement of
skilled and experienced personnel, scheduling is doomed to fail.
There are many short comings when schedule personnel are inexperienced.
The most common of this is unrealistic planning (Nima et al., 2002) and unrealistic
base-lined schedules (Son and Rojas, 2011). This is mainly because todays
schedulers have been taught a mechanized approach to scheduling that downplays or
even ignores the planning process (Ponce de Leon, 2008).
Lack of communication amongst project participants
Lack of communication is always listed as one of the short comings for poor
project schedule performance. Communicating involves the exchange of information.
The sender and receiver are responsible for clear, unambiguous and complete
diffusion of information (PMBOK, 2004). Projects schedules are the medium
through which information is presented for the clear execution of the project. To
attain maximum benefits, the continual use of the project schedule by all project
participants is necessary.
Poor management
Participants often experience some sort of schedule pressure which often
causes out-of-order work to be corrected (Nepal et al., 2006). PM solutions need to
be flexible so that schedules can weather out these and other turbulences. Poor
management fails to integrate and respond to difficulties that may arise. Combining
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
44/120
28
superior scheduling solutions with strong project management, close communication
among project participants and standardization of technology and procedures make a
good model for success (Sappe, 2007).
3.1.2 Procedures
Improper planning
Construction projects involve large group of activities to achieve the goals in
the project scope. These activities require vast amount of resources, having them
available at the right time and in the proper quantity is a challenge, which project
managers are constantly faced with. Additionally resources are not always provided
at construction sites upon demand because some of them are scarce in the market
(Kim et al., 2005). Some of these challenges can sometimes be mitigated or even
avoided with proper planning. Ponce de Leon (2008) concurs with this by stating
that the one common thread linking the majority of schedule slippage is having
inadequate collaborative planning. Planning is the essence of project management, the
aim of which is to achieve a defined objective within defined temporal and financial
constraints (Long et al., 2004). Glenwright (2004) also agrees that the main issue
plaguing scheduling planning and development is not doing enough planning of the
details of the contract execution.
Improper use of scheduling methods and tools
The drivers of success are not in the relative advantage of one scheduling
algorithm over the other, but in how your project scheduling process uses the tools
and methods available to the projects best advantage (Griffith, 2005). When properly
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
45/120
29
used, scheduling methods and tools force the project team to break down the project
into discrete activities, estimate the duration of each, and think through the possible
and preferable sequencing of the activities (Griffith, 2005).
Inefficient standards and specification
I cant stress enough the correlation between standardization and success,
writes Richard Sappe (2007). A comprehensive planning and scheduling specification
system can aid in the planning and job sequencing of financing, workforce, material
and equipment (Ballast and Popescu, 2001).
Schedule provisions are necessary for a number of issues (Levin, 2006).
They contain information regarding the qualification of the scheduler, the scheduling
methods, tools and techniques that are to be used. They establish the ground rule for
owner-supplied materials or actions required in given events. Additionally, schedule
specifications transfer risk to the respective project participants.
Incompetent use of software
Many of the schedules were modeled in scheduling software packages, but the
activities were not networked together systematically (Griffith, 2005). Many
researchers have found out the scheduling software in many instances is used mainly
for representation purposes and not for communicating the project deliverable and
time of deliverables (Herroleon, 2005).
3.1.3 Problems in Developing Countries
Good project performance or project success is not common in the
construction industry. Hence, many professionals and scholars have been motivated
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
46/120
30
to take extensive efforts to meet this challenge (Long et al., 2004).
Previous research has found that the major problems contractors in developing
countries are faced with can be classified into four groups. They are: problems
imposed by the industry, problems of inaccurate information, failure to meet
obligations on the part of project participants, and problems imposed by their own
short comings (Odeh and Battaineh, 2002). Ogunlana et al. (1996) stated that the
construction industry problems in developing countries are nested in three layers:
inadequacies in the industry infrastructure, problems caused by owners and
consultants, and problems caused by the contractors incompetence.
Inadequacies of the infrastructure
Lack of management skill and technical personnel is one of the most noted
shortcomings of the industry in developing countries. The few individuals that
practice project management are at the mercy of uncertainty of resource shortage and
a fluctuation of work force with variable productivity. The productivity may be
attributed to the lack of improper training and associations that regulates the
acceptable productivity yield (Odeh and Battaineh, 2002).
Accurate estimation needs accurate information in terms of quality, flow and
availability (Long et al., 2004). It is commonly perceived that the contractor is
ultimately responsible for the schedule performance, but the project involves owners,
designers and other people who are also responsible for the problems.
Schedule specifications are often inconsistent, confusing and poorly written,
and the owners construction management staff lacks the expertise to verify
compliance. Therefore causing a lack of respect to the schedule specification and
standard that are usually part of the contract requirement (Warhoe, 2009)
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
47/120
31
Problems caused by owners and consultants
Owners are unwilling to delegate authority to consultants to do the project
management (Odeh and Battaineh, 2002). This causes managing the contract
ineffectively. This may be the outcome of the general practice where designers
/consultants and construction management is usually not well defined. Owners are
constantly causing interference, setting unrealistic contract duration, delaying
payments for completed works (Long et al., 2004). Owners and consultants with
slow decision making and limited support in project management plague the general
construction practice.
Problems caused by contactors
Contractors are reluctant to use scheduling techniques and to update schedules on
a regular basis (Odeh and Battaineh, 2002). Despite the fact that contractors are
required to submit schedules on most work, the schedules are often summary that are
hard used and updated. The inadequate contractor experience is the most common
known phenomenon which is caused by the selection carried out by the consultants
and owners when considering the lowest bidder as candidate for the project (Long et
al., 2004). Contractors lack management skill and are reluctant to invest in planning
and control or to hire construction managers. It is common to find that most on-site
manager are experienced civil engineers but with little training or education in
management.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
48/120
32
3.2 Initial Survey in Belize
The purpose of this initial survey was to get an initial understanding of
scheduling practice in Belize, a developing country. A questionnaire of 10 questions
related to factors affecting project scheduling process was designed (Appendix A).
These questions were derived from references such as AACE (2006), Buziak (2008),
and Iyer and Jha (2006). The questions were formatted to allow the respondents the
freedom to comment. This was done to enable to grasp an idea of the practice in
project scheduling in the Belizean construction industry.
Belize is a young nation that progressively is making improvements in its
construction industry. Nonetheless, it can be said that there is much to be done.
The construction industry over the last decade accounted for approximately 25% of
the GDP; however the industry is suffering from extreme delays due to many
shortcomings. Some efforts have being made and Belize now has a certified body of
professionals in the construction industry. There is still quiet more to be done in
establishing best practice, standards and regulations.
Many respondents contacted were willing to grant an interview. However,
contractors were more skeptical about granting an interview. It was realized later
that the reluctance was due to their lack of management knowledge.
A total of 15 professionals were surveyed, amongst were contractors, owners and
architects. These individuals represent a picture of the current practice in the
construction industry in Belize, given that the least years of experience was 4 and the
most was 20, with an average of about 12 years.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
49/120
33
3.2.1 Preliminary Results
The first question was to pinpoint the critical factors in the practice. Many of
the interviewees claimed that the main issue affecting project schedule is the lack of
project management and scheduling by the contractors. Figure 3.2 shows that 41%
of the interviewed agrees with this.
Fig. 3.2 Critical factors affectingproject schedules
Fig. 3.3 Most common schedulingtool
Most contractors are individuals with some experience as tradesmen and
entrepreneurial skills. These individuals often run into problems such as under pricing,
establishing unrealistic deadlines and often breaching initial contract agreement.
This, however, does not imply that there are not capable professionals, but reflects the
attitude of contractors toward planning and scheduling.
The second question surveyed the use of scheduling tools. Figure 3.3 shows
majority of the respondents use MS Project as their preferred scheduling tool.
This majority of the interviewees are in design and consulting firms. The 21%
represents the contractors who often use MS Excel table or other writing tools. This
indicates that scheduling knowledge is mostly within the consultants, which may
create a barrier for communication by using scheduling tools between project parties
Question 3 surveyed the use of pre-job meeting practices. These pre-job
17%
6%
12%
24%
41%
Information
Control
Participants'
Resources
Management
21%
7%
71%
Others
P3/6
Ms Project
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
50/120
34
meetings for reviews of project scope are very important. Griffith (2005) comments
this provides a check to ensure accuracy and opportunity for functional personnel to
very their plans and expectation. However, Fig. 3.4 shows that this is not a common
practice and reinforces the fact that there is a lack of communication.
Fig. 3.4 Pre-job meeting for reviewsof project scope
Fig. 3.5 Project Participant thataffect Project Schedule
When question 4 was answered, Figure 3.5 shows that the owners and
contractors cause most of the delays. This question emphasizes that scheduling
knowledge on the part of the contractors is one of the causes for deficient schedule
performance. Additionally, designers/consultants and contractors suggest that
owners demand often cause delays. Owners cause schedules to be constantly
adjusted and no-value activities are sometimes done out of sequence in order to
maintain a workforce, as consequence of delays in payments of work completed.
This causes an increase in project cost due to rework in the tasks that are
out-of-sequence.
This trend has caused project participants to accept delays as part of project
operations. Contractors blame owners of indecision, lack of timely payment and
excessive change orders, while owners and designers blame contractors of lacking
management and scheduling knowledge to execute and deliver a project in time. Fig.
3.6 shows the responses to question 5, which asks how delays are seen.
75%
25%
no
yes
19%
38%
6%
38%
Suppliers
Sub/Contractor
Designer/Consultants
Owners
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
51/120
35
Fig. 3.6Are delays inevitable Fig. 3.7Schedulers as part of project
Schedulers are necessary for large companies with multimillion dollar projects
but are a commodity for others: hence the reason for project engineer/schedulers to
be employed by small to medium companies (Buziak, 2008). This means that the
project engineers should be knowledgeable to carry out project planning and
scheduling.
Fig. 3.7 shows it is not common for construction companies to hire schedulers as
part of their project team. It is common practice for engineers that are heading a
project to provide a project schedule. This makes it necessary for engineers in
Belize to possess some scheduling knowledge. These are the responses relate to
question 6.
Question 7 was a direct question of the attention focus toward project schedule.
Figure 3.8 shows that 42 % scored themselves low, 25 % as medium and 33% as high.
However, Figure 3.9 (question 8) shows a consensus that project scheduling is
essential for proper project management. Nonetheless, many claim that there is a
lack of commitment, cooperation and support from other project participants, agreeing
with Jha and Iyer (2007).
67%
33%
No
yes
83%
17%
No
Yes
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
52/120
36
Fig. 3.8Attention to scheduling Fig. 3.9 Consensus of scheduling
Control and maintenance of scheduling dictates that schedules should be
frequently updated. Question 9 queried the average frequency that update is carried
out on project schedule. Figure 3.10 shows that 67% of the updates occur at
intervals greater than one month.
Fig. 3.10 Average update cycle Fig. 3.11 More challenging phase
Time management has two basic phases, planning and scheduling. Question 10
asked which is found to be more difficult. Figure 3.11 shows that 91 % claim
planning to be more challenging. Majority replied that planning is more time
consuming and more difficult due to lack of historical data and industry standards.
This is true for young engineers, and more experienced engineers claimed that they
collect personal data that help them with future projects.
3.2.2 Informalities in the Industry
After the survey results are presented, a culture toward project scheduling, the
lack of management knowledge, and lack of schedule specification and standards are
summarized below.
33%
25%
42%
8-10
5-7
1-4
17%
83%
No
Yes
67%
17%
17%
> 1mth
2wks - 1mth
< 2wks.
9%
91%
Schedulin
g
Planning
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
53/120
37
Planning and scheduling are viewed as waste of time. This is because the
industry is overwhelmed with a variety of uncertainty. Amongst these uncertainties
are the shortage of supplies and fluctuation of skilled labor. Therefore, prior
planning, although practiced, is considered a useless commitment of time and efforts.
Many experienced contractors do plan prior to construction, but it is rather an ad hoc
activity. This ad hoc planning lacks many of the processes described in the PMBOK
(2004) in order to make it effective.
Most project participants that are indirectly involved with project execution
acknowledge project scheduling. However, bulk of the construction is done mostly
by experienced contractors in technical aspect of construction without schedule
management knowledge. This leads to improper planning, scheduling and control of
projects.
Most project scheduling specifications are often copied and pasted from past
projects. These are seldom updated and enforced by the owners consulting team.
This affects the efforts that contractors put into scheduling. Not having updated and
enforced scheduling specifications lead to incomplete and unusable schedules. The
levels of details presented are minimal and cannot be used to monitor and control the
project progress.
On the interviews held, the interviewees claimed that there is no documentation
for them to rely on. No set standards for the requirements, variation of views of the
importance, and the informality of the schedules influence the contractors not to use
project schedules. The limited number of professionals and the availability of an
arbitration system for contract breach disputes have made schedule delays an
acceptable part of the construction industry.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
54/120
38
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
55/120
39
CHAPTER FOUR SURVEYING SCHEDULE PRACTICE
LEVELS AND RESULTS
After having discussed the problems and factors that affect scheduling practice in
Chapter 3, a questionnaire was developed in this chapter to survey the scheduling
process and performance to determine the level of practice and point out those areas
that need more attention. Section 4.1 explains the need for establishing scheduling
practice levels, Section 4.2 describes the questionnaire design, and Section 4.3
explains the questionnaire survey results.
4.1 Establishing Schedule Practice Levels
Benchmarking and determining the levels of expertise in an organization is not a
new idea. A five stage model to determine or benchmark the quality of an
organization was first presented in the late 1970s (Kwak, 2001). This was later
followed by the introduction of a continuous process improvement practices for better
quality management in an organization (Kwak and Ibbs, 2002). This idea can be
used to determine the levels of practice for project scheduling process.
4.1.1 Effort to establish the scheduling practice
Projects are dynamic, unique and temporary that makes the scheduling practice
difficult (PMBOK, 2004). One schedule model cannot work for all projects. Each
project in itself determines what tools and techniques are more adequate (Hartley,
1993). This causes project managers and schedulers in both the public and private
sectors to range across an organizational spectrum, in different levels of scheduling
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
56/120
40
knowledge and practice. Many have argued that defining the practice level can help
to improve performance (Barber, 2004).
As evidence of the effort to determine and position an organizations level of
knowledge and practice in PM, the PM2 model has been introduced (Kwak and Ibbs,
2002). Additionally the conformance index scoring using scheduling components as
described in the PMIs (2004) Practices Standard for Scheduling, reflects the
maturity and levels of scheduling practice of scheduling practitioners.
In the efforts to establish a scheduling practice standard, the Project Management
Institute College of Scheduling (PMICOS) has two publications that discuss time
management: the Project Management Book of Knowledge (PMBOK) and Practice
Standard for Scheduling. In the PMBOK (2004), chapter 6 is devoted to the time
management processes, which are required to ensure a timely completion of the
project. The Practice Standard for Scheduling (PMI, 2007) describes the methods
related to scheduling that are generally recognized as good practice for most project
most of the time. It contains the schedule components that ought to be used to make
the scheduling model useful as a planning and control tool.
The American Association of Cost Engineering (AACE) has published various
Recommended Practices that delineate the responsibilities of scheduler, level of
details, methodology for schedule oriented claims and analysis (AACE, 2006). All
the above literature describes the required knowledge, process, and methods and
responsibilities that a scheduler should possess and practice. This literature
complements each other by having and sharing the same relevant principles related to
time management requirements.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
57/120
41
4.1.2 Maturity Level Assignment
In order to assess the maturity level of practice, reference was made to the
methodology used by the PM2 model described by Kwak and Ibbs (2002). The PM2
model has five levels of maturity, level one being the lowest and five being the
highest. Figure 4.1 shows the different PM2 levels with their corresponding PM
maturity.
Initial
Level 1
Planned
Level 2
Managed
Level 3
Integrated
Level 4
Sustained
Level 5
Adhoc PM
Process
Basic project
Planning
Standard Project
Tracking
Advanced Project Planning
and Management
Continous PM Process
Improvement
Level 1
Level2
Level3
Level 4
Level 5
PM2
LevelsScheduling Practice Levels
Very formal
Planning and scheduling methods are mostly
used and scheduling control is mostly done
Very informal
Planning and scheduling techniques almost
never used and no schedule control execution
Informal
Planning and scheduling techniques seldom
used with no schedule control.
Moderately formal
Planning and scheduling methods are
sometimes used with some schedule control
Formal
Planning and scheduling methods are often
used alone with schedule control
Fig. 4.1 Schedule Practice Levels
Numeric level assignment to qualitative responses enables such to be quantitative.
The questions in parts B, C, and D in the questionnaire (Appendix B) give the
respondents 5 options to choose from. The answers are in a Likert scale form which
surveyed the agreement, frequency, formality, and importance of the factors
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
58/120
42
of the scheduling practice. To the five options provided, each progressive as the
level of the Likert scale from low to high, or 1 to 5, respectively, indicating the level
of maturity. This is similar to the PM2 model that was developed by Ibbs and Kwak
(2002).
Figure 4.1 shows the similarity between the PM2 and scheduling practice
maturity levels. Note that the scheduling maturity practice levels correspond to
those of the PM2 model. To evaluate the levels of any sample, the averages of each
part (B, C and D) will be indicative of such. Moreover, these averages can be further
average to indicate an overall level of performance. Note that Figure 4.1 shows that as
the practice maturity level increases, so does the formal level of planning and
scheduling methods and techniques practiced.
4.2 Questionnaire Design
A questionnaire was developed to target construction project participants in
Taiwan and Belize (Appendix B). These participants involve contractors, consultants
and owners working in the public and private sectors of the construction industry.
The design of this questionnaire took into consideration the literature regarding
the scheduling practice. The questionnaire consists of four parts: general
information, project environment, scheduling process and scheduling performance.
The general information of the respondents was collected to correlate the experience
and area of work to the level of schedule practice.
4.2.1 General Information
This part covers general information of the project participants surveyed. The
questions are related to the type and size of organization, and the position the
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
59/120
43
respondent holds in the organization. It also covers the years of experience, how
scheduling knowledge was obtained and whether scheduling is a major part of their
job description. These questions are required to determine the quality of
knowledge available and how well it is being used and in which sector of the industry
is being more successful in implementing scheduling process.
4.2.2 Project Environment
This part covers the project environment in which scheduling process is
developed and utilized for monitoring and control. It has eight questions, the first
two questions address the size and complexity of the projects, the following four
address how project participants view project scheduling. The last two questions
survey the use of scheduling specifications.
The first question attempts to identify the size of projects that are normally
practiced in term of duration. This will provide a measure for the need of scheduling
practice that is required. The second question addresses how project complexity
affects the effort and time that are required for scheduling. This is because project
complexity usually demands an exceptional level of management (Baccarini, 1996).
Jha and Iyer (2007) have stated that commitment of project participants,
including the owner, is dominating factor for schedule compliance. Therefore
questions 3 through 6 addresses how the project participants view the use of
scheduling as a management tool in their project management.
Question 7 is directed to find out whether scheduling specifications are carefully
designed for each project. Schedule specifications are important for they contain the
necessary information regarding the type of schedules, the update cycle and specify
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
60/120
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
61/120
45
ask, when will the project be completed? As a control tool the time and cost
information of the work performed is essential. To address this, question 9 was
included as part of the scheduling process section.
4.2.4 Schedule Performance
This part discusses the delays that are common in the industry, the cost spent on
scheduling and level of satisfaction the practitioner have toward the current practice.
Project delays are one of the biggest problems construction firms are facing today
(Tumi et al., 2009). This makes it noteworthy to assess the schedule performance in
order to assess it in a particular industry. Question 1 asks the delays that each
individual has experienced. The delays are measured as a percentage of the
baseline schedule: this will provide a more indicative ratio, rather than measuring the
delays in unit time, which would be dependent of the duration of the project.
Using schedule tools and techniques on projects does require investment of time
and money. Practitioners assert that using these practices drive a better outcome that
outweighs the cost to implement (Griffith, 2005), thought in its initial stage the
returns are not high (Ibbs and Reginato, 2002). Therefore, question 2 surveys the
actual cost that is being spent for working on schedules.
Project scheduling management has two phases: planning and scheduling. The
successful schedule development is only as good as the planning efforts. Improper
planning and scheduling has been identified as one of the causes of delays in the
construction projects (Long et al., 2004). Question 3 queries the developed schedule
based on initial planning. Project schedule defines the scopes of work of a project
which can be used to communicate the deliverables required to complete the project.
-
7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects
62/120
46
The use of the project schedule as a tool to improve communication is queried in
question 4.
Change is inevitable and every project will experience it (PMI, 2007). The use
of the project schedule as control tool is dependent on accurate reporting and tracking
of the baseline. Nonetheless this is dependent on the schedule capabilities of the
project team. Question 5 addresses the degree to which project schedules are used
for time control. Overall, the last question surveys the level of satisfaction that the
respondent has toward project schedule.
4.3 Survey Process and Results
The questionnaire was first designed in English (Appendix B) and then translated
to Chinese (Appendix C). This was done in order to survey the professionals
project schedule maturity of both Belize and Taiwan.
The questionnaire was made available to the professionals of the Belizean
construction industry via e-mails containing an attached Word file and a link to a web
page. Some of the responses were e-mailed back whilst others were directly
uploaded to the online web page. Of the 70 questionnaire that were sent to Belize, a
total of 29 responses were collected. Ten of the responses were e-mailed, whilst the
remaining 19 were uploaded directly to the web page, this account to 41% of the
questionnaires sent. None of these responses were discarded.
The Chinese translated questionnaire web link was also e-mailed to professionals
of Taiwan in addition to the hard copies that were made available at seminars and
visits. Taiwanese responses were divided in to three groups: owners, consultants and