Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

download Linkage between Scheduling Process Maturity and Schedule  Performance of Construction Projects

of 120

Transcript of Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    1/120

    National Cheng Kung University (NCKU)

    International Program in Civil

    Engineering and Management (ICEM)

    Masters Thesis

    Linkage between Scheduling Process Maturity and Schedule

    Performance of Construction Projects

    Student: Jos Mari Divas

    N66987123

    Advisor: Andrew S. Chang

    July, 2011

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    2/120

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    3/120

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    4/120

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    5/120

    i

    ABSTRACT

    Delays are often found in construction projects in spite of numerous research

    aimed at improving schedule performance. Studies address the factors affecting

    project success and establish good practices to help in scheduling process. Some argue

    the schedule problems are lack of support between management and project

    participants, and the misuse of the scheduling methods and techniques, while others

    state that is because of an existing gap between theory and practice.

    This research studies the relationship between scheduling process maturity and

    schedule performance. It first reviews the factors that are of critical influence on

    schedule performance. A questionnaire was designed based on four parts composed of

    these schedule factors: schedule theory, management theory, project participants and

    project environment. The questionnaire was sent out and collected 93 sets of data from

    owners, consultants and contractors in both Belize and Taiwan.

    The analysis results reveal the views of project participants regarding various

    scheduling aspects. Contractors replies have a better linkage with schedule

    performance. Basic scheduling processes are most frequently and well used by project

    participants while having a moderate relationship with schedule performance. The

    scheduling formality of the project participants has a moderate relationship with project

    delays. Advance scheduling processes are seldom used because they are not familiar

    to participants are seldom practiced.

    Keywords: Schedule theory, project management, schedule management, scheduling

    process, schedule performance.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    6/120

    ii

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    7/120

    iii

    93

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    8/120

    iv

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    9/120

    v

    ACKNOWLEDGEMENTS

    I would firstly like to give praise to Jehovah god for patience, guidance and

    wisdom.

    Secondly, thanks to the International Cooperation and Development Fund (ICDF)

    for the opportunity to study in Taiwan at National Cheng Kung University. My

    appreciation also goes to the faculty at Civil Engineering and Management, not

    forgetting my thesis advisor, Professor Andrew Chang, for his kind guidance

    throughout the investigation process. I would also like to extend my gratitude to my

    classmates for helping with Chinese lessons.

    I also want to thank my family and loved ones for the unconditional support

    specially my mother, Gloria Estela Flores.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    10/120

    vi

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    11/120

    vii

    TABLE OF CONTENT

    ABSTRACT ............................................................................................................... I

    ........................................................................................................................ IIIACKNOWLEDGEMENTS ...................................................................................... V

    TABLE OF CONTENT .......................................................................................... VII

    LIST OF TABLES ................................................................................................... IX

    LIST OF FIGURES .................................................................................................. X

    CHAPTER 1 INTRODUCTION................................................................................ 1

    1.1 Motivation ............................................................................................... 2

    1.2 Research Objectives ................................................................................. 3

    1.3 Research Scope and Limitation ................................................................ 4

    CHAPTER TWO LITERATURE REVIEW ............................................................... 9

    2.1 Schedule Theory .................................................................................... 10

    2.1.1 Planning, Scheduling and Control................................................ 10

    2.1.2 Scheduling Methods and Techniques ........................................... 13

    2.2 Management Theory .............................................................................. 15

    2.2.1 Project management .................................................................... 15

    2.2.2 PM Process and Benchmarking ................................................... 16

    2.3 Project Participants Capabilities ............................................................. 18

    2.3.1 Human Factors ............................................................................ 18

    2.3.2 Skills, Training and Experience ................................................... 19

    2.4 Project Environment .............................................................................. 19

    2.4.1 Owners Sophistication ................................................................ 20

    2.4.2 Project Complexity ...................................................................... 20

    2.4.3 Schedule Specification ................................................................ 22

    2.4.4 Culture ........................................................................................ 23

    CHAPTER THREE FACTORS AFFECTING SCHEDULING PROCESS .............. 25

    3.1 Scheduling Process Problems ................................................................. 25

    3.1.1 Personnel..................................................................................... 26

    3.1.2 Procedures ................................................................................... 28

    3.1.3 Problems in Developing Countries .............................................. 29

    3.2 Initial Survey in Belize........................................................................... 32

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    12/120

    viii

    3.2.1 Preliminary Results ..................................................................... 33

    3.2.2 Informalities in the Industry ........................................................ 36

    CHAPTER FOUR SURVEYING SCHEDULE PRACTICE LEVELS ANDRESULTS ................................................................................................................ 39

    4.1 Establishing Schedule Practice Levels .................................................... 39

    4.1.1 Effort to establish the scheduling practice .................................... 39

    4.1.2 Maturity Level Assignment ......................................................... 41

    4.2 Questionnaire Design ............................................................................. 42

    4.2.1 General Information .................................................................... 42

    4.2.2 Project Environment .................................................................... 43

    4.2.3 Scheduling Process ...................................................................... 44

    4.2.4 Schedule Performance ................................................................. 45

    4.3 Survey Process and Results .................................................................... 46

    4.3.1 General Information .................................................................... 47

    4.3.2 Project Environment .................................................................... 51

    4.3.3 Scheduling Process ...................................................................... 57

    4.3.4 Schedule Performance ................................................................. 64

    CHAPTER FIVE LINKAGE ANALYSIS OF SCHEDULING ASPECTS ............ 71

    5.1 Linkage Strategy ......................................................................................... 71

    5.1.1 Relationships to be Identified ...................................................... 71

    5.1.2 Regressionandcorrelation analysis ............................................. 73

    5.2 Relationship Identification ..................................................................... 74

    5.2.1 General Information-Schedule Process and Performance ............. 75

    5.2.2 Project Environment Scheduling Process .................................. 78

    5.2.3 Project Environment Schedule Performance ............................. 82

    5.2.4 Scheduling Process Schedule Performance ............................... 85

    CHAPTER SIX CONCLUSIONS AND RECOMMENDATIONS ........................ 89

    6.1 Conclusions ........................................................................................... 89

    6.2 Recommendations .................................................................................. 90

    REFERENCES ........................................................................................................ 93

    Appendix A: Initial Survey Questions about Scheduling Problems ................. 97

    Appendix B: Questionnaire (English Version) ................................................... 98

    Appendix C: Questionnaire () .............................................................. 101Appendix C: Summary of Questionnaire Survey Results ................................ 104

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    13/120

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    14/120

    x

    LIST OF FIGURES

    Fig. 1.1 Gap between schedule theory and practice .................................................... 3

    Fig. 1.2 Research Process .......................................................................................... 6Fig. 2.1 Schedule theory and practice aspects ............................................................ 9Fig. 2.2 Planning and Scheduling Phases (AACE, 2006) ......................................... 11Fig. 2.3 Scheduling Process (PMI, 2007) ................................................................. 11Fig. 2.4 Scheduling model (PMI, 2007) ................................................................... 13Fig. 2.5 Links among processes in a phase (PMBOK, 2004) .................................... 16 Fig. 2.6Project processes and knowledge areas (PMBOK, 2004) ............................ 17 Fig. 2.7Drivers of project complexity (Vidal and Marle, 2008) ............................... 21Fig. 3.1 Scheduling process problems ...................................................................... 26Fig. 3.2 Critical factors affecting project schedules .................................................. 33Fig. 3.3 Most common scheduling tool .................................................................... 33Fig. 3.4 Pre-job meeting for reviews of project scope .............................................. 34Fig. 3.5 Project Participant that affect Project Schedule ........................................... 34Fig. 3.6Are delays inevitable .................................................................................. 35Fig. 3.7Schedulers as part of project ....................................................................... 35Fig. 3.8Attention to scheduling ............................................................................... 36Fig. 3.9 Consensus of scheduling ............................................................................. 36Fig. 3.10 Average update cycle ................................................................................ 36Fig. 3.11 More challenging phase ............................................................................ 36Fig. 4.1 Schedule Practice Levels ............................................................................ 41Fig. 4.2 Respondent organizations ........................................................................... 47

    Fig. 4.3 Relative size of organization ....................................................................... 48Fig. 4.4 Positions of respondents ............................................................................. 49Fig. 4.5 Number of years of experience ................................................................... 49Fig. 4.6Scheduling as part of the respondents job description ................................ 50Fig. 4.7Source of scheduling knowledge ................................................................. 51Fig. 4.8Average project duration ............................................................................. 52Fig. 4.9 Project complexity increasing efforts to project schedules........................... 52Fig. 4.10 Owners view on project schedule ............................................................. 53Fig. 4.11 Owners knowledge and experience effect on project scheduling .............. 54Fig. 4.12 Project participants view of project planning and scheduling ................... 55Fig. 4.15 Specifications similarity for projects ......................................................... 56

    Fig. 4.15 Schedule requirements affecting scheduling process ................................. 57Fig. 4.16Types of scheduling method often used ..................................................... 58 Fig. 4.17Type of scheduling tool often used ............................................................ 59Fig. 4.18Use of WBS for planning .......................................................................... 59Fig. 4.19 Use of sequencing relationship other than finish-start on PDM .............. 60Fig. 4.20 Use of CPM techniques for project schedule ............................................. 61 Fig. 4.21 Use of resource loading on project schedules ............................................ 62Fig. 4.22 Use of earned value analysis ..................................................................... 62Fig. 4.23 Update cycle ............................................................................................. 63Fig. 4.24 Calculations of time to complete upon project updating ......................... 64Fig. 4.25 Average schedule delay ............................................................................. 64

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    15/120

    xi

    Fig. 4.26Cost spent toward project schedules .......................................................... 65Fig. 4.27Scheduling as a result of good planning .................................................... 66Fig. 4.28Opinions of project schedule improving communication ........................... 67Fig. 4.29 Schedules being used for project time control ........................................... 68 Fig. 4.30 Overall satisfactions with current scheduling practice ............................... 68

    Fig 5.1 Scheduling aspects tested for relationships .................................................. 72

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    16/120

    xii

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    17/120

    1

    CHAPTER 1 INTRODUCTION

    The need for scheduling in the project management can be argued from

    economical, technical and continued control points of view (Cole, 1991). Research

    has shown that where scheduling is fairly and consciously practiced throughout the

    project life cycle, the project results in favorable schedule and cost performance

    (Griffith, 2005). However, schedule practices are still deficient in the construction

    industry. One main reason is that there is a gap between the schedule theory and

    general practice.

    Project schedule is essentially a management tool used as basis for decision

    making by project participants. They reflect the schedule baseline and the subsequent

    changes as project progresses (Hartley, 1993). The main objective of schedules is to

    provide a roadmap that represents how and when the project will deliver the products

    defined in the project scope (PMI, 2007). Schedules provide a holistic view of the

    project while communicating the project scope both vertically and horizontally to all

    participants (PMI, 2007; Sappe, 2007).

    Schedules can be an effective management tool when good practices are utilized in

    the scheduling process. However this depends on competence and level of maturity of

    project participants. According to Kerzner (2009), maturity implies that the proper

    foundation of methods, tools, techniques, and processes exist. It generally comes from

    experience gained from exposure to several types of project.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    18/120

    2

    1.1 Motivation

    Construction projects are getting more complex and difficult (Chan et al, 2004)

    hence the need for the use of project scheduling cannot be over emphasized. In spite of

    the vast amount of research related to scheduling, most research is related to advances

    in methodologies and techniques, while others research the factors affecting schedule

    performance (Herroleon, 2005). However, the scheduling process involved and

    schedule performance are seldom linked.

    One of the most widely researched topics in project schedule performance is the

    concept of project success and the criteria to measure it (Iyer and Jha, 2006). Chan et

    al., (2004) categorized the factors affecting project success into four groups:

    project-related, procurement-related, project management and project

    participant-related factors.

    In spite of all these efforts, projects are still suffering delays and going over budget.

    Dos Santos (2002) reveals that part of the problem stems from the partial application of

    theory, gap in knowledge amongst practitioners and the lack of support from the

    organizational structure. Additionally, high reliability cannot be achieved when the

    schedule preparation process is separated from the project operational reality (Son and

    Rojas, 2011). Together this implies that the lack of linkage between applicable theory

    and current practices make schedule practice inefficient.

    Figure 1.1 shows the existence of a gap between the schedule theory and reality or

    practice. The theoretical aspects are scheduling and management theory, while the

    project participants and the project environments compose the reality of the schedule

    practice.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    19/120

    3

    Fig. 1.1 Gap between schedule theory and practice

    Efforts are being established to better bond and link these four aspects. The Project

    Management Institute (PMI) has added a college of scheduling as part of its

    organization (Galloway, 2006). This was done in an effort to standardize and achieve

    consistency in its application, requirements for schedule development, and use in the

    construction industry. PMI developed the Practice Standard for Scheduling Manual

    to regulate the scheduling practice (Galloway, 2006), in addition to providing the

    Project Management Book of Knowledge (PMBOK) which serves as a guide to project

    management.

    1.2 Research Objectives

    The objective of this research is to analyze the linkage between scheduling process

    maturity and schedule performance in the construction industry. This research aims to

    find a linkage by evaluating responses from a survey in areas of project environment,

    scheduling process and schedule performance. As a secondary objective, by

    assigning numeric levels to the responses it will be possible to define the general

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    20/120

    4

    schedule maturity level of the respondents. The responses level will indicate which

    areas are in more need of attention by the respondents. In return recommendation can

    be given on specific areas to increase the scheduling process maturity.

    Additionally the level maturity can be used to compare and rank the level of

    schedule maturity between the two countries and surveyed groups of project

    participants. The results of such research should enable individual to promote

    schedule maturity and schedule consciousness in construction project. This will

    enhance the scheduling process and consequently should improve performance.

    Though scheduling process maturity may be linked to schedule performance, this is

    limited to the commitment and competence of the scheduler and other direct project

    participants.

    1.3 Research Scope and Limitation

    This research intends to surveys the scheduling practices of construction

    professionals in the Belize and Taiwan. The analysis and results provide insight of the

    scheduling process maturity currently being practiced. The research objective and

    method outline the process of this research and provides the objective aimed to

    achieve.

    During this investigation some limitations were encountered. Some of these

    limitations are:

    - Sample size: though the number of total responses totals 93, this includesresponses for both Belize and Taiwan. The responses are not even

    distributed among owners, consultants, and contractor, and though the

    responses represent the scheduling practice in both countries, is some areas

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    21/120

    5

    the sample size is too small to find a significant relationship between the

    schedule process and the schedule performance. The results of this

    research may be used only as reference material in identifying the level of

    maturity of Belize and Taiwan given the size of the sample size

    - Lack of prior research: previously, linking the respondents capabilities withthe schedule usage was researched. However linking the schedule process

    with schedule performance has not yet been researched, therefore this

    research is more exploratory, than explanatory.

    - Methodology used in data collection: the main focus of this research isbased on the questionnaire sent to Belize and to Taiwans project

    participants. A better approach would have being to self fill out the

    questionnaire in face to face interviews this would probably have yielded

    better results.

    1.4Research Method and ProcessThe main research methods used were an initial survey of semi-open question

    interviews and a questionnaire survey. The initial survey rendered a picture of the

    scheduling practices problems in Belize. The initial survey was followed by a Likert

    scaled questionnaire. The questionnaire was developed after schedule literature

    review and analysis of the initial survey. This questionnaire was distributed to owners,

    consultants, and contractors both in Belize and Taiwan. The respondents selected

    from Belize were all those listed in the Association of Professional Engineers of

    Belize. While in Taiwan the respondents that have certain relationships with NCKU

    were asked to participate in this survey.

    The questionnaire was divided into four parts. The first part addresses

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    22/120

    6

    background of the respondents: their job positions, types of organization, and sources

    of scheduling knowledge and whether scheduling is a major or minor job. The second

    covers the project environment in which scheduling is practiced. This includes the

    views of the project participants toward project planning and scheduling, project

    complexity and scheduling specifications issues. Part three addresses the scheduling

    process practiced in the industry. This includes the scheduling tools and methods in

    developing and controlling of schedules. The final part covers the of project schedule

    performance: the average delays, cost spent, and the overall satisfaction the respondent

    have of scheduling practice.

    This research process can be summarized into five general steps as seen in Figure

    1.2.

    Conclusion and recommendation

    Step 1

    Step 2

    Step 3

    Step 4

    Step 5

    Literature review and initial survey

    Identification of the problems related to scheduling

    process

    Questionnaire design and survey

    Data analysis and linkage

    Fig. 1.2 Research Process

    1.5Thesis StructureThis thesis contains six chapters. Chapter 1 is the introduction of this thesis which

    contains the motivation, research objectives and research scope and limitation and

    research methodology. Chapter 2 contains a summary of the literature read and

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    23/120

    7

    reviewed for the development of this thesis. Chapter 3 presents an analysis of the

    general schedule problems encountered in Belize. Chapter 4 describes the

    questionnaire design and development. Chapter 5 presents the results and the efforts

    using correlation to establish a linkage between the scheduling process and the

    schedule performance. Finally, Chapter 6 presents the conclusion and

    recommendation of this research.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    24/120

    8

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    25/120

    9

    CHAPTER TWO LITERATURE REVIEW

    Researches has shown that scheduling practice involves integration of

    scheduling methods and techniques, management procedures and guidelines, the

    experience of the project participants, and the skills to adapt to existing project

    environment. Figure 2.1 shows these schedule aspects.

    ParticipantCapabilities

    ProjectEnvironment

    ScheduleTraining

    SchedulingExperience

    SchedulingSkills

    OwnersSophistication

    ProjectComplexity

    SchedulingSpecification

    Culture

    Schedule aspects

    ScheduleTheory

    ManagementTheory

    Planning,SchedulingControl

    SchedulingMethods andTechniques

    ProjectManagement

    ProjectManagementProcess andBench Marking

    Fig. 2.1 Schedule theory and practice aspects

    This chapter reviews the four aspects of schedule theory and practice as

    shown in Figure 2.1. Section 2.1 reviews schedule theory, Section 2.2 management

    theory, Section 2.3 project participants, and Section 2.4 the Project-Related

    environment.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    26/120

    10

    2.1 Schedule Theory

    Much has been written about project scheduling dealing with the mechanics of

    creating the schedule document itself (Hartley, 1993). This happened as extensive

    documentation requiring the need for planning and schedule methodologies (Cole,

    1991).

    Scheduling has been around for sometimes. Henry Gantt first used bar chart as

    a mean to represent and sequence activities in early 1900s (Kerzner, 2009). Bar

    charts are advantageous in that they are easily understood and represent a picture of

    the project in progress. When a project becomes larger and complex, the bar chart

    has a disadvantage (Kerzner, 2009). This gives way to the CPM and PERT scheduling

    methods which were introduced in the late 1950s, and since then they have been

    vastly researched (Herroelen, 2005). Nonetheless, after their establishment, the

    basic principles of project scheduling and control have gone unchanged for the major

    parts. However, their application in the construction industry has still not received

    100% acceptance or consistency (Galloway, 2006).

    2.1.1 Planning, Scheduling and Control

    The American Association of Cost Engineers (AACE, 2006) provides various

    definitions for scheduling. A time-sequence of activities and events that represent

    and operating timetable, specifying the relative beginning and ending times of

    activities and the occurrence of events is a better suited definition. Figure 2.2

    define Planning and Scheduling as per AACE (2006).

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    27/120

    11

    Planning and Scheduling Phases

    Planning ScheduleDevelopment

    Scheduling Control

    Fig. 2.2 Planning and Scheduling Phases (AACE, 2006)

    Scheduling commonly starts at the planning phase and continues to the

    execution as a control system. Furthermore it has its place and time after project

    completion, usually in court when conflicts arise regarding the completion time

    (Gould and Joyce, 2009). Nonetheless for schedules to be rendered useable for

    planning, executing, monitoring and communication, it should adhere to standard

    practices (PMI, 2007).

    Project Start

    SelectingScheduling

    Method

    Instances ofProject

    Schedules

    Enter ProjectScecific Data

    SelectScheduling

    Model

    ProjectSchedule

    Updateand

    Status

    ProjectComplete

    Fig. 2.3 Scheduling Process (PMI, 2007)

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    28/120

    12

    As Figure 2.3 shows, the scheduling process includes selecting a scheduling

    method and tool, incorporating project specific data to develop a project specific

    project schedules (Fig. 2.4) (PMI, 2007)

    A schedule model should include five major processes in developing the

    project schedule (PMBOK, 2004): activity definition, activity sequencing, activity

    duration estimating, schedule development, and schedule control. Once developed,

    the schedule model is regularly updated to reflect progress and changes, in areas such

    as scope of logic (PMI, 2007).

    Given that the construction industry is dynamic in nature, project planning

    cannot be consider as a straight-through process but rather it is best thought of as a

    planning cycle (Chan et al., 2004). Project planning starts early and continues

    throughout the various phases of the project life cycle. Planning encompasses

    defining the project objectives and determination of activities, selection of methods,

    resources and establishing responsibilities to accomplish completion as required

    (AACE, 2006). The methods, tools and techniques play important role in both the

    planning and scheduling phases. This selection depends on the project

    characteristics, the participants involved and the environment (Hartley, 1993).

    The purpose of the schedule development is to implement the project schedule

    by converting the project plan into a logical arrangement and sequence of activities.

    During the schedule development phase, the project activities are refined, activity

    durations are determined, activity relationships and sequencing are detailed, and key

    milestones are confirmed. Resource and cost may be included in the schedule

    activities (AACE, 2006). Construction managers need to develop a schedule for

    directing and controlling resources (Lu and Lam, 200).

    The PMBOK(2004) considers that schedule control is concerned with

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    29/120

    13

    influencing the factors that create schedule changes to ensure that changes are agreed

    upon, provided that the schedule has changed, and managing the actual changes

    when and as they occur.

    Nothing goes according to plan, and schedules have to be modified.

    Excessive change orders can cause changes in the planned schedules and,

    consequently, cause significant disruption to construction projects (Long et al., 2003).

    Thus the reason exists to keep a good control on project schedules. Proper planning

    and control are usually among the top five factors required to avoid project delays

    (Tumi et al, 2009).

    2.1.2 Scheduling Methods and Techniques

    Selecting scheduling methods occurs in the early part of the scheduling process.

    The scheduling methods provide the framework within which the scheduling model is

    developed with its specific tool and techniques applicable to manipulate the project

    information, as seen in Figure 2.4 (PMI, 2007).

    Scheduling

    Method

    Scheduling

    Tools

    Schedule

    Model

    Project

    Information

    Output

    ProjectSchedule

    Fig. 2.4 Scheduling model (PMI, 2007)

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    30/120

    14

    The PMBOK (2004) states the usual and accepted scheduling method: the

    ADM (AOA) and PDM (AON). Hinze (2008) also mentions the LOB for repetitive

    vertical and horizontal construction, and the bar chart as the popular method of

    sequencing activity at an initial stage of the scheduling process.

    Most efforts in research have been directed to the developing of

    methodologies and techniques for optimizing resources for single project. However

    practice has shown that many of these methodologies have proven to have limitations

    and in real cases project managers often find themselves managing up to four projects

    on average (Herroleon, 2005).

    The use of project scheduling techniques early in the project correlates with

    better project outcome (Griffith, 2005). These techniques are clearly defined during

    the schedule development stage. PMBOK (2004) mentioned the CPM, PERT and

    GERT as mathematical analysis techniques to calculate the delivery dates of the

    activities. Thought some scheduling techniques are better than others, all have their

    advantages and disadvantages (Kerzner, 2009).

    The scheduling tool is used to assemble the schedule model and provide

    means of adjusting various parameter and components that are typical during

    modeling process. The scheduling tool contains the scheduling components and the

    rules for relating and using the components to represent the process for completing a

    project. This is easily visualized by running scheduling software tool (PMI, 2007),

    though other tools have the form of forms and templates (PMBOK, 2004).

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    31/120

    15

    2.2 Management Theory

    Modern project management appeared during World War II and was initially

    used for large military and construction projects (Vidal and Marle, 2008). Though its

    growth and acceptance has changed significantly since its appearance, these changes

    continue into the twenty-first century (Kerzner, 2009).

    2.2.1 Project management

    Project involves doing something that has not being done before and is unique

    (PMBOK, 2004). Project management (PM) is the planning, organizing, directing,

    and controlling of company resources for a relatively short-term objective that has

    been established to complete specific goals and objectives (Kerzner, 2009).

    PMBOK (2004) describes PM as the application of knowledge, skills, tools and

    techniques to project activities to meet the project requirements established. Others

    perceive management by project as temporary organizations for the performance of

    complex processes, such as contracts for external clients (Garies and Huemann,

    2000).

    PM has gone through three major development phases (Kerzner, 2009).

    Initially line manager used the concept of over-the-fence management to manage

    project. Executives began searching for new management techniques and

    organizational structures that could be quickly adapted to a changing environment.

    Thereafter, companies in general consensus begun to realize that PM was a necessity

    not a choice.

    Projects are getting bigger and invariably more complex than ever (Baccarini,

    1996), and the project team is required more than ever to more competent in PM.

    Corporate organizations are in favor of PM tools and practices that are well suited for

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    32/120

    16

    todays rapidly changing industry. This however poses a question, how well is the

    organization using these tools and practices. To answer to this question the Project

    Management Process Maturity (PM2) model measures the relative PM maturity level

    of an organization (Kwak and Ibbs, 2002).

    2.2.2 PM Process and Benchmarking

    PMBOK (2004) define the PM processes in five groups. PM processes are:

    - Initiating: authorizing the project or phase.- Planning: defining and refining objectives and selecting the best of the

    alternatives courses of action to attain the objectives that the project was

    undertaken to address.

    - Executing: coordinating people and other resources to carry out the plan.- Controlling: ensuring that project objectives are met by monitoring and

    measuring progress regularly to identify variance from plan so that

    corrective action can be taken when necessary.

    - Closing: formalizing acceptance of the project or phase and bringing it toan orderly end.

    Fig. 2.5 Links among processes in a phase (PMBOK, 2004)

    InitiatingProcesses

    ClosingProcesses

    ControllingProcesses

    ExecutingProcesses

    PlanningProcesses

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    33/120

    17

    Each of the five PM processes in Figure 2.5 includes nine knowledge areas as

    shown in Figure 2.6.

    Fig. 2.6Project processes and knowledge areas (PMBOK, 2004)

    Despite the broad usage of PM tools and practices, organizations are often

    confused and uncertain about their current application of such tools. The five-level

    PM2 model has become the basis to evaluate and position an organization current PM

    maturity and level of sophistication. The model motivates organizations and

    people to accomplish higher and more sophisticated PM maturity by a systematic and

    incremental approach. It also provides and guides the necessary processes and

    requirements to achieve a higher PM maturity level. It allows an organization to

    determine the strength and weakness of current PM practices and focus on the weak

    PM practices to achieve higher PM maturity.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    34/120

    18

    2.3 Project Participants Capabilities

    Project participants related problems that reflect the deficiency in project

    scheduling appears in various forms. The often cited problems or reasons for

    project failure that are related to the participants are: inadequately trained and/or

    experience project managers; poor leadership; failure to adequately identify,

    document and track project requirement; poor planning process; inadequate or

    misused methods; inadequate communication, including project tracking and

    reporting (Herroelen, 2005). Therefore it is absolutely necessary that practitioner be

    competent, capable and possesses knowledge in management, this can only be

    achieved by training, possessing former experience and planning skills.

    2.3.1 Human Factors

    There are few things more disheartening than to see an untouched, project

    schedule rolled in a corner or even being used as wall paper in a project office. This

    is a usual occurrence of good intentions, but failed scheduling efforts (Hartley, 1993).

    Project participants must be proactive and committed to meet time and cost

    requirements as planned. In order to achieve project success the project team is

    required to possess motivating, organizing and planning skills (Chan et al., 2009). Be

    able to coordinate resources and labor through continued involvement in the project.

    The adaptability of project participants to changes in the project plan is essential (Iyer

    and Jha, 2009).

    Iyer and Jha (2009) stated that a competent project manager has the technical

    and monitoring capabilities for effective leadership. Furthermore, the project

    manager should be able to delegate authority and responsibilities to the project team

    and all other project participants involved in the project execution. Project

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    35/120

    19

    managers competence is related to the skills, training and experience that he

    possesses.

    2.3.2 Skills, Training and Experience

    Every participant has skills and knowledge that may be useful in developing

    the project plan (PMBOK, 2004). Given that all construction projects are different,

    the use of skills play a significant role in identifying the aspects that add value to

    project scheduling (Chan et al., 2004). Iyer and Jha (2006) emphasized the

    importance of project planning and suggested that project planning be carried out by

    skilled individuals.

    Many organizations acknowledge the need to improve the level of knowledge

    and skills in the construction community by providing training in the form of

    continuing education, workshops, lunch and other learning programs (Buziak, 2008).

    Training of highly regarded that PMI has recently added a college of scheduling

    (PMICOS) as part of it organization (Galloway, 2006b).

    The key to project success is to apply knowledge, experience and intuition to

    the project plan, and then attempt to execute according to plan (PMI, 2007). Chan et

    al. (2004) mentioned that previous related experience is key to project success.

    Project participants experience is the backbone for the development of planning and

    scheduling (AACE, 2006).

    2.4 Project Environment

    Project scope is widely accepted to be a contributing factor to the project

    success. It is thought to be a useful indicator of the expected project construction

    timeline. The attributes related to the project scope are: type of project, nature of

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    36/120

    20

    project, complexity, and project size (Chan et al., 2004).

    Construction projects are unique and temporary in nature and so their

    management. This uniqueness in project activities often requires consumption of

    initial time getting used to the project and the demands of the project scope. Though

    the commitment of the all the project participants is essential to project completion,

    the sophistication (competence) of the owner weighs in project schedule success (Iyer

    and Jha, 2006).

    2.4.1 Owners Sophistication

    Taking timely decisions, regular monitoring and feedback of the project progress

    is some of the characteristics of the owners competence (sophistication). It has

    been found that in projects where the owners are technically competent and

    financially strong good project performance is achieved. On the other hand,

    incompetent owners proceed with projects without proper planning and are not able to

    recruit competent personnel to look after their interests (Iyer and Jha, 2006).

    Indecisiveness or slow decision by owners is also of great concern to both consultants

    and contractors in respect to timely completion of projects (Odeh and Battaineh,

    2002). All this results in an unsuccessful outcome as far as schedule is concerned

    (Iyer and Jha, 2006).

    2.4.2 Project Complexity

    The construction process may be considered the most complex undertaking in

    any industry. The construction industry has displayed great difficulty in coping with

    the progressive increase in complexity of construction projects (Baccarini, 1996).

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    37/120

    21

    However complexity of project schedule is different from the complexity of the

    project itself. The complexity of the project schedule indicates high interconnection

    between activities. When the resources needed for the project are widely spread, the

    project is considered complex. Project complexity can be an important criterion in

    the selection of an appropriate project organization form. Conversely, the complexity

    of a project can affect the projects objectives of time, cost, and quality; it is

    frequently used as a criterion in the selection of a suitable project procurement

    arrangement (Nassar and Hegab, 2006).

    Project complexity can be characterized through some factors that can be

    classified into four categories as see in Figure 2.7. The project size is a project

    complexity factor. Identifying the parameters that characterize the size of the

    project system gives a first list of drivers of project complexity. A project system

    must be over a minimum critical size to be considered a complex system. Factors

    that are contemplated for the project size are: the duration of project, number of

    activities, resources, decisions, departments, investors, objectives, stakeholder and the

    largeness of scope.

    Project Complexity

    Project interdependence

    Elements of contextProject Variety

    Project Size

    Fig. 2.7Drivers of project complexity (Vidal and Marle, 2008)

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    38/120

    22

    Project variety relates closely to the diversity of the number of emergent

    properties (factors) and is a necessary condition for project complexity. The factors

    underlined are: diversity of staff experience, and variety of financial resources,

    organizational interdependencies, organizational skills, stakeholders, resources

    manipulated, project components, technical skills and dependencies.

    Project interdependence is likely the greatest driver of project complexity.

    Components of complexity will depend on and influence each other, making it

    problematic in project scheduling. The following components make up the

    interdependencies within a project system: interdependencies between the

    components of the product, resource and raw material interdependencies,

    specification interdependencies, amongst others.

    Project complexity cannot be neither analyzed nor managed without

    considering the elements of project context. The project context cannot be

    transferred from project to project with different institutional and cultural

    configuration. Elements of contextuality are: competition, culture, environment

    complexity, local laws and regulation, public agenda and existing technological

    innovation.

    2.4.3 Schedule Specification

    A critical step in the execution of a construction project is the selection of

    planning and scheduling specification clauses to be included in the construction

    contract (Ballast and Popesco, 2001). According the PMI (2007), a specification is a

    document that specifies, in a complete, precise, verifiable manner, the requirements,

    design, behavior, or other characteristics of a system, component, product, result or

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    39/120

    23

    service and, often the procedures for determining whether these provisions have been

    satisfied.

    Currently the scheduling specifications have become over burdened with the

    challenge of addressing the entire range of roles now encompassed by the activity of

    scheduling. As a result, scheduling specification advancements over the years have

    been extremely uneven, resulting in contract specification with schedule provision

    ranging from two sentences to two dozen pages. This lack of standards and wide

    variety of scheduling methodologies are the reasons for establishing standards and

    best practices (Levin, 2006).

    2.4.4 Culture

    Culture is important to determine and analyze the ways of perception,

    evaluation and application of techniques and technology in society (Kuruoglu and

    Ergen, 2002). Culture is the totality of socially transmitted behavior patterns, arts,

    beliefs, institution, and all other products of human work and thought. Every project

    must operate within a context of one or more cultural norms. This area of influence

    includes political, economic, demographic, educational, ethical, ethnics, religious,

    and other areas of practice, belief, and attitudes that effects the way people interact

    (PMBOK, 2004).

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    40/120

    24

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    41/120

    25

    CHAPTER THREE FACTORS AFFECTING SCHEDULING

    PROCESS

    Schedule delays and cost over runs are not a recent phenomenon (Son and

    Rojas, 2011). The dynamic and unique nature of construction projects makes it

    difficult to plan, schedule and control. Most research in factors affecting scheduling

    has been taken up by developed countries. The difference in context, the

    applicability in developing countries may not be the same and is therefore in need of

    exploration (Iyer and Jha, 2006). Kuruoglu and Ergen (2002) explained that

    developing societies do not approach problems the same ways developed societies do.

    Though this may be partly due to cultural differences, other factors have significant

    effects.

    This chapter explores the common problems affecting the scheduling process

    and provides a background of the problems. A brief summary of an initial survey is

    presented about the schedule phenomena in the Belizean construction industry.

    3.1 Scheduling Process Problems

    Project schedules by nature are evolutionary documents and contain varying

    amounts of detail. As a project progresses, more information is available and the

    schedule is appropriately refined to reflect the available data (Hartley, 1993).

    Planning and scheduling cannot be though as a one-time task, but rather a process

    throughout the life of the project (PMBOK, 2004).

    The dynamics of the project, the characteristics of the participants and the

    nature of the environment constitute the factors that constantly influence changes and

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    42/120

    26

    the schedule performance. However, Hartley (1993) commented that successful

    planning and schedule development and control process is inherently affected by a

    scheduling system. This scheduling system consists of the characteristics of

    personnel and procedures that cause problems in the scheduling process as shown in

    Figure 3.1. This will determine how well the schedule will serve as an efficient

    management tool (PMI, 2007).

    Personnel Procedures

    Lack of commitment,

    competence and

    coordination

    Lack of experience and

    knowledge

    Lack of communication

    Poor Management

    Improper Planning

    Improper use of

    scheduling methods

    and techniques

    Lack of standards and

    schedule specification

    Improper use and

    knowledge of software

    Fig. 3.1 Scheduling process problems

    3.1.1 Personnel

    Lack of commitment, competence, and coordination

    Project managers competence, commitment of the project participants,

    owners competence and coordination among project participants predominantly

    contribute towards success of the project. Competence enables the project

    participants to make appropriate decisions on time including corrective actions if

    necessary. Commitment motivates the team toward successful and on-time

    completion of the project. While, coordination keeps the flow of information,

    resources and skills among the various participants engage in a project (Jha and Iyer,

    2007).

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    43/120

    27

    Lack of experience and knowledge

    Individuals with construction knowledge and experience should carry out the

    early project planning so that interference between design and construction can be

    avoided (Nima et al., 2002). Hartley (1993) stated that without the involvement of

    skilled and experienced personnel, scheduling is doomed to fail.

    There are many short comings when schedule personnel are inexperienced.

    The most common of this is unrealistic planning (Nima et al., 2002) and unrealistic

    base-lined schedules (Son and Rojas, 2011). This is mainly because todays

    schedulers have been taught a mechanized approach to scheduling that downplays or

    even ignores the planning process (Ponce de Leon, 2008).

    Lack of communication amongst project participants

    Lack of communication is always listed as one of the short comings for poor

    project schedule performance. Communicating involves the exchange of information.

    The sender and receiver are responsible for clear, unambiguous and complete

    diffusion of information (PMBOK, 2004). Projects schedules are the medium

    through which information is presented for the clear execution of the project. To

    attain maximum benefits, the continual use of the project schedule by all project

    participants is necessary.

    Poor management

    Participants often experience some sort of schedule pressure which often

    causes out-of-order work to be corrected (Nepal et al., 2006). PM solutions need to

    be flexible so that schedules can weather out these and other turbulences. Poor

    management fails to integrate and respond to difficulties that may arise. Combining

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    44/120

    28

    superior scheduling solutions with strong project management, close communication

    among project participants and standardization of technology and procedures make a

    good model for success (Sappe, 2007).

    3.1.2 Procedures

    Improper planning

    Construction projects involve large group of activities to achieve the goals in

    the project scope. These activities require vast amount of resources, having them

    available at the right time and in the proper quantity is a challenge, which project

    managers are constantly faced with. Additionally resources are not always provided

    at construction sites upon demand because some of them are scarce in the market

    (Kim et al., 2005). Some of these challenges can sometimes be mitigated or even

    avoided with proper planning. Ponce de Leon (2008) concurs with this by stating

    that the one common thread linking the majority of schedule slippage is having

    inadequate collaborative planning. Planning is the essence of project management, the

    aim of which is to achieve a defined objective within defined temporal and financial

    constraints (Long et al., 2004). Glenwright (2004) also agrees that the main issue

    plaguing scheduling planning and development is not doing enough planning of the

    details of the contract execution.

    Improper use of scheduling methods and tools

    The drivers of success are not in the relative advantage of one scheduling

    algorithm over the other, but in how your project scheduling process uses the tools

    and methods available to the projects best advantage (Griffith, 2005). When properly

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    45/120

    29

    used, scheduling methods and tools force the project team to break down the project

    into discrete activities, estimate the duration of each, and think through the possible

    and preferable sequencing of the activities (Griffith, 2005).

    Inefficient standards and specification

    I cant stress enough the correlation between standardization and success,

    writes Richard Sappe (2007). A comprehensive planning and scheduling specification

    system can aid in the planning and job sequencing of financing, workforce, material

    and equipment (Ballast and Popescu, 2001).

    Schedule provisions are necessary for a number of issues (Levin, 2006).

    They contain information regarding the qualification of the scheduler, the scheduling

    methods, tools and techniques that are to be used. They establish the ground rule for

    owner-supplied materials or actions required in given events. Additionally, schedule

    specifications transfer risk to the respective project participants.

    Incompetent use of software

    Many of the schedules were modeled in scheduling software packages, but the

    activities were not networked together systematically (Griffith, 2005). Many

    researchers have found out the scheduling software in many instances is used mainly

    for representation purposes and not for communicating the project deliverable and

    time of deliverables (Herroleon, 2005).

    3.1.3 Problems in Developing Countries

    Good project performance or project success is not common in the

    construction industry. Hence, many professionals and scholars have been motivated

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    46/120

    30

    to take extensive efforts to meet this challenge (Long et al., 2004).

    Previous research has found that the major problems contractors in developing

    countries are faced with can be classified into four groups. They are: problems

    imposed by the industry, problems of inaccurate information, failure to meet

    obligations on the part of project participants, and problems imposed by their own

    short comings (Odeh and Battaineh, 2002). Ogunlana et al. (1996) stated that the

    construction industry problems in developing countries are nested in three layers:

    inadequacies in the industry infrastructure, problems caused by owners and

    consultants, and problems caused by the contractors incompetence.

    Inadequacies of the infrastructure

    Lack of management skill and technical personnel is one of the most noted

    shortcomings of the industry in developing countries. The few individuals that

    practice project management are at the mercy of uncertainty of resource shortage and

    a fluctuation of work force with variable productivity. The productivity may be

    attributed to the lack of improper training and associations that regulates the

    acceptable productivity yield (Odeh and Battaineh, 2002).

    Accurate estimation needs accurate information in terms of quality, flow and

    availability (Long et al., 2004). It is commonly perceived that the contractor is

    ultimately responsible for the schedule performance, but the project involves owners,

    designers and other people who are also responsible for the problems.

    Schedule specifications are often inconsistent, confusing and poorly written,

    and the owners construction management staff lacks the expertise to verify

    compliance. Therefore causing a lack of respect to the schedule specification and

    standard that are usually part of the contract requirement (Warhoe, 2009)

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    47/120

    31

    Problems caused by owners and consultants

    Owners are unwilling to delegate authority to consultants to do the project

    management (Odeh and Battaineh, 2002). This causes managing the contract

    ineffectively. This may be the outcome of the general practice where designers

    /consultants and construction management is usually not well defined. Owners are

    constantly causing interference, setting unrealistic contract duration, delaying

    payments for completed works (Long et al., 2004). Owners and consultants with

    slow decision making and limited support in project management plague the general

    construction practice.

    Problems caused by contactors

    Contractors are reluctant to use scheduling techniques and to update schedules on

    a regular basis (Odeh and Battaineh, 2002). Despite the fact that contractors are

    required to submit schedules on most work, the schedules are often summary that are

    hard used and updated. The inadequate contractor experience is the most common

    known phenomenon which is caused by the selection carried out by the consultants

    and owners when considering the lowest bidder as candidate for the project (Long et

    al., 2004). Contractors lack management skill and are reluctant to invest in planning

    and control or to hire construction managers. It is common to find that most on-site

    manager are experienced civil engineers but with little training or education in

    management.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    48/120

    32

    3.2 Initial Survey in Belize

    The purpose of this initial survey was to get an initial understanding of

    scheduling practice in Belize, a developing country. A questionnaire of 10 questions

    related to factors affecting project scheduling process was designed (Appendix A).

    These questions were derived from references such as AACE (2006), Buziak (2008),

    and Iyer and Jha (2006). The questions were formatted to allow the respondents the

    freedom to comment. This was done to enable to grasp an idea of the practice in

    project scheduling in the Belizean construction industry.

    Belize is a young nation that progressively is making improvements in its

    construction industry. Nonetheless, it can be said that there is much to be done.

    The construction industry over the last decade accounted for approximately 25% of

    the GDP; however the industry is suffering from extreme delays due to many

    shortcomings. Some efforts have being made and Belize now has a certified body of

    professionals in the construction industry. There is still quiet more to be done in

    establishing best practice, standards and regulations.

    Many respondents contacted were willing to grant an interview. However,

    contractors were more skeptical about granting an interview. It was realized later

    that the reluctance was due to their lack of management knowledge.

    A total of 15 professionals were surveyed, amongst were contractors, owners and

    architects. These individuals represent a picture of the current practice in the

    construction industry in Belize, given that the least years of experience was 4 and the

    most was 20, with an average of about 12 years.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    49/120

    33

    3.2.1 Preliminary Results

    The first question was to pinpoint the critical factors in the practice. Many of

    the interviewees claimed that the main issue affecting project schedule is the lack of

    project management and scheduling by the contractors. Figure 3.2 shows that 41%

    of the interviewed agrees with this.

    Fig. 3.2 Critical factors affectingproject schedules

    Fig. 3.3 Most common schedulingtool

    Most contractors are individuals with some experience as tradesmen and

    entrepreneurial skills. These individuals often run into problems such as under pricing,

    establishing unrealistic deadlines and often breaching initial contract agreement.

    This, however, does not imply that there are not capable professionals, but reflects the

    attitude of contractors toward planning and scheduling.

    The second question surveyed the use of scheduling tools. Figure 3.3 shows

    majority of the respondents use MS Project as their preferred scheduling tool.

    This majority of the interviewees are in design and consulting firms. The 21%

    represents the contractors who often use MS Excel table or other writing tools. This

    indicates that scheduling knowledge is mostly within the consultants, which may

    create a barrier for communication by using scheduling tools between project parties

    Question 3 surveyed the use of pre-job meeting practices. These pre-job

    17%

    6%

    12%

    24%

    41%

    Information

    Control

    Participants'

    Resources

    Management

    21%

    7%

    71%

    Others

    P3/6

    Ms Project

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    50/120

    34

    meetings for reviews of project scope are very important. Griffith (2005) comments

    this provides a check to ensure accuracy and opportunity for functional personnel to

    very their plans and expectation. However, Fig. 3.4 shows that this is not a common

    practice and reinforces the fact that there is a lack of communication.

    Fig. 3.4 Pre-job meeting for reviewsof project scope

    Fig. 3.5 Project Participant thataffect Project Schedule

    When question 4 was answered, Figure 3.5 shows that the owners and

    contractors cause most of the delays. This question emphasizes that scheduling

    knowledge on the part of the contractors is one of the causes for deficient schedule

    performance. Additionally, designers/consultants and contractors suggest that

    owners demand often cause delays. Owners cause schedules to be constantly

    adjusted and no-value activities are sometimes done out of sequence in order to

    maintain a workforce, as consequence of delays in payments of work completed.

    This causes an increase in project cost due to rework in the tasks that are

    out-of-sequence.

    This trend has caused project participants to accept delays as part of project

    operations. Contractors blame owners of indecision, lack of timely payment and

    excessive change orders, while owners and designers blame contractors of lacking

    management and scheduling knowledge to execute and deliver a project in time. Fig.

    3.6 shows the responses to question 5, which asks how delays are seen.

    75%

    25%

    no

    yes

    19%

    38%

    6%

    38%

    Suppliers

    Sub/Contractor

    Designer/Consultants

    Owners

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    51/120

    35

    Fig. 3.6Are delays inevitable Fig. 3.7Schedulers as part of project

    Schedulers are necessary for large companies with multimillion dollar projects

    but are a commodity for others: hence the reason for project engineer/schedulers to

    be employed by small to medium companies (Buziak, 2008). This means that the

    project engineers should be knowledgeable to carry out project planning and

    scheduling.

    Fig. 3.7 shows it is not common for construction companies to hire schedulers as

    part of their project team. It is common practice for engineers that are heading a

    project to provide a project schedule. This makes it necessary for engineers in

    Belize to possess some scheduling knowledge. These are the responses relate to

    question 6.

    Question 7 was a direct question of the attention focus toward project schedule.

    Figure 3.8 shows that 42 % scored themselves low, 25 % as medium and 33% as high.

    However, Figure 3.9 (question 8) shows a consensus that project scheduling is

    essential for proper project management. Nonetheless, many claim that there is a

    lack of commitment, cooperation and support from other project participants, agreeing

    with Jha and Iyer (2007).

    67%

    33%

    No

    yes

    83%

    17%

    No

    Yes

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    52/120

    36

    Fig. 3.8Attention to scheduling Fig. 3.9 Consensus of scheduling

    Control and maintenance of scheduling dictates that schedules should be

    frequently updated. Question 9 queried the average frequency that update is carried

    out on project schedule. Figure 3.10 shows that 67% of the updates occur at

    intervals greater than one month.

    Fig. 3.10 Average update cycle Fig. 3.11 More challenging phase

    Time management has two basic phases, planning and scheduling. Question 10

    asked which is found to be more difficult. Figure 3.11 shows that 91 % claim

    planning to be more challenging. Majority replied that planning is more time

    consuming and more difficult due to lack of historical data and industry standards.

    This is true for young engineers, and more experienced engineers claimed that they

    collect personal data that help them with future projects.

    3.2.2 Informalities in the Industry

    After the survey results are presented, a culture toward project scheduling, the

    lack of management knowledge, and lack of schedule specification and standards are

    summarized below.

    33%

    25%

    42%

    8-10

    5-7

    1-4

    17%

    83%

    No

    Yes

    67%

    17%

    17%

    > 1mth

    2wks - 1mth

    < 2wks.

    9%

    91%

    Schedulin

    g

    Planning

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    53/120

    37

    Planning and scheduling are viewed as waste of time. This is because the

    industry is overwhelmed with a variety of uncertainty. Amongst these uncertainties

    are the shortage of supplies and fluctuation of skilled labor. Therefore, prior

    planning, although practiced, is considered a useless commitment of time and efforts.

    Many experienced contractors do plan prior to construction, but it is rather an ad hoc

    activity. This ad hoc planning lacks many of the processes described in the PMBOK

    (2004) in order to make it effective.

    Most project participants that are indirectly involved with project execution

    acknowledge project scheduling. However, bulk of the construction is done mostly

    by experienced contractors in technical aspect of construction without schedule

    management knowledge. This leads to improper planning, scheduling and control of

    projects.

    Most project scheduling specifications are often copied and pasted from past

    projects. These are seldom updated and enforced by the owners consulting team.

    This affects the efforts that contractors put into scheduling. Not having updated and

    enforced scheduling specifications lead to incomplete and unusable schedules. The

    levels of details presented are minimal and cannot be used to monitor and control the

    project progress.

    On the interviews held, the interviewees claimed that there is no documentation

    for them to rely on. No set standards for the requirements, variation of views of the

    importance, and the informality of the schedules influence the contractors not to use

    project schedules. The limited number of professionals and the availability of an

    arbitration system for contract breach disputes have made schedule delays an

    acceptable part of the construction industry.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    54/120

    38

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    55/120

    39

    CHAPTER FOUR SURVEYING SCHEDULE PRACTICE

    LEVELS AND RESULTS

    After having discussed the problems and factors that affect scheduling practice in

    Chapter 3, a questionnaire was developed in this chapter to survey the scheduling

    process and performance to determine the level of practice and point out those areas

    that need more attention. Section 4.1 explains the need for establishing scheduling

    practice levels, Section 4.2 describes the questionnaire design, and Section 4.3

    explains the questionnaire survey results.

    4.1 Establishing Schedule Practice Levels

    Benchmarking and determining the levels of expertise in an organization is not a

    new idea. A five stage model to determine or benchmark the quality of an

    organization was first presented in the late 1970s (Kwak, 2001). This was later

    followed by the introduction of a continuous process improvement practices for better

    quality management in an organization (Kwak and Ibbs, 2002). This idea can be

    used to determine the levels of practice for project scheduling process.

    4.1.1 Effort to establish the scheduling practice

    Projects are dynamic, unique and temporary that makes the scheduling practice

    difficult (PMBOK, 2004). One schedule model cannot work for all projects. Each

    project in itself determines what tools and techniques are more adequate (Hartley,

    1993). This causes project managers and schedulers in both the public and private

    sectors to range across an organizational spectrum, in different levels of scheduling

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    56/120

    40

    knowledge and practice. Many have argued that defining the practice level can help

    to improve performance (Barber, 2004).

    As evidence of the effort to determine and position an organizations level of

    knowledge and practice in PM, the PM2 model has been introduced (Kwak and Ibbs,

    2002). Additionally the conformance index scoring using scheduling components as

    described in the PMIs (2004) Practices Standard for Scheduling, reflects the

    maturity and levels of scheduling practice of scheduling practitioners.

    In the efforts to establish a scheduling practice standard, the Project Management

    Institute College of Scheduling (PMICOS) has two publications that discuss time

    management: the Project Management Book of Knowledge (PMBOK) and Practice

    Standard for Scheduling. In the PMBOK (2004), chapter 6 is devoted to the time

    management processes, which are required to ensure a timely completion of the

    project. The Practice Standard for Scheduling (PMI, 2007) describes the methods

    related to scheduling that are generally recognized as good practice for most project

    most of the time. It contains the schedule components that ought to be used to make

    the scheduling model useful as a planning and control tool.

    The American Association of Cost Engineering (AACE) has published various

    Recommended Practices that delineate the responsibilities of scheduler, level of

    details, methodology for schedule oriented claims and analysis (AACE, 2006). All

    the above literature describes the required knowledge, process, and methods and

    responsibilities that a scheduler should possess and practice. This literature

    complements each other by having and sharing the same relevant principles related to

    time management requirements.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    57/120

    41

    4.1.2 Maturity Level Assignment

    In order to assess the maturity level of practice, reference was made to the

    methodology used by the PM2 model described by Kwak and Ibbs (2002). The PM2

    model has five levels of maturity, level one being the lowest and five being the

    highest. Figure 4.1 shows the different PM2 levels with their corresponding PM

    maturity.

    Initial

    Level 1

    Planned

    Level 2

    Managed

    Level 3

    Integrated

    Level 4

    Sustained

    Level 5

    Adhoc PM

    Process

    Basic project

    Planning

    Standard Project

    Tracking

    Advanced Project Planning

    and Management

    Continous PM Process

    Improvement

    Level 1

    Level2

    Level3

    Level 4

    Level 5

    PM2

    LevelsScheduling Practice Levels

    Very formal

    Planning and scheduling methods are mostly

    used and scheduling control is mostly done

    Very informal

    Planning and scheduling techniques almost

    never used and no schedule control execution

    Informal

    Planning and scheduling techniques seldom

    used with no schedule control.

    Moderately formal

    Planning and scheduling methods are

    sometimes used with some schedule control

    Formal

    Planning and scheduling methods are often

    used alone with schedule control

    Fig. 4.1 Schedule Practice Levels

    Numeric level assignment to qualitative responses enables such to be quantitative.

    The questions in parts B, C, and D in the questionnaire (Appendix B) give the

    respondents 5 options to choose from. The answers are in a Likert scale form which

    surveyed the agreement, frequency, formality, and importance of the factors

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    58/120

    42

    of the scheduling practice. To the five options provided, each progressive as the

    level of the Likert scale from low to high, or 1 to 5, respectively, indicating the level

    of maturity. This is similar to the PM2 model that was developed by Ibbs and Kwak

    (2002).

    Figure 4.1 shows the similarity between the PM2 and scheduling practice

    maturity levels. Note that the scheduling maturity practice levels correspond to

    those of the PM2 model. To evaluate the levels of any sample, the averages of each

    part (B, C and D) will be indicative of such. Moreover, these averages can be further

    average to indicate an overall level of performance. Note that Figure 4.1 shows that as

    the practice maturity level increases, so does the formal level of planning and

    scheduling methods and techniques practiced.

    4.2 Questionnaire Design

    A questionnaire was developed to target construction project participants in

    Taiwan and Belize (Appendix B). These participants involve contractors, consultants

    and owners working in the public and private sectors of the construction industry.

    The design of this questionnaire took into consideration the literature regarding

    the scheduling practice. The questionnaire consists of four parts: general

    information, project environment, scheduling process and scheduling performance.

    The general information of the respondents was collected to correlate the experience

    and area of work to the level of schedule practice.

    4.2.1 General Information

    This part covers general information of the project participants surveyed. The

    questions are related to the type and size of organization, and the position the

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    59/120

    43

    respondent holds in the organization. It also covers the years of experience, how

    scheduling knowledge was obtained and whether scheduling is a major part of their

    job description. These questions are required to determine the quality of

    knowledge available and how well it is being used and in which sector of the industry

    is being more successful in implementing scheduling process.

    4.2.2 Project Environment

    This part covers the project environment in which scheduling process is

    developed and utilized for monitoring and control. It has eight questions, the first

    two questions address the size and complexity of the projects, the following four

    address how project participants view project scheduling. The last two questions

    survey the use of scheduling specifications.

    The first question attempts to identify the size of projects that are normally

    practiced in term of duration. This will provide a measure for the need of scheduling

    practice that is required. The second question addresses how project complexity

    affects the effort and time that are required for scheduling. This is because project

    complexity usually demands an exceptional level of management (Baccarini, 1996).

    Jha and Iyer (2007) have stated that commitment of project participants,

    including the owner, is dominating factor for schedule compliance. Therefore

    questions 3 through 6 addresses how the project participants view the use of

    scheduling as a management tool in their project management.

    Question 7 is directed to find out whether scheduling specifications are carefully

    designed for each project. Schedule specifications are important for they contain the

    necessary information regarding the type of schedules, the update cycle and specify

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    60/120

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    61/120

    45

    ask, when will the project be completed? As a control tool the time and cost

    information of the work performed is essential. To address this, question 9 was

    included as part of the scheduling process section.

    4.2.4 Schedule Performance

    This part discusses the delays that are common in the industry, the cost spent on

    scheduling and level of satisfaction the practitioner have toward the current practice.

    Project delays are one of the biggest problems construction firms are facing today

    (Tumi et al., 2009). This makes it noteworthy to assess the schedule performance in

    order to assess it in a particular industry. Question 1 asks the delays that each

    individual has experienced. The delays are measured as a percentage of the

    baseline schedule: this will provide a more indicative ratio, rather than measuring the

    delays in unit time, which would be dependent of the duration of the project.

    Using schedule tools and techniques on projects does require investment of time

    and money. Practitioners assert that using these practices drive a better outcome that

    outweighs the cost to implement (Griffith, 2005), thought in its initial stage the

    returns are not high (Ibbs and Reginato, 2002). Therefore, question 2 surveys the

    actual cost that is being spent for working on schedules.

    Project scheduling management has two phases: planning and scheduling. The

    successful schedule development is only as good as the planning efforts. Improper

    planning and scheduling has been identified as one of the causes of delays in the

    construction projects (Long et al., 2004). Question 3 queries the developed schedule

    based on initial planning. Project schedule defines the scopes of work of a project

    which can be used to communicate the deliverables required to complete the project.

  • 7/31/2019 Linkage between Scheduling Process Maturity and Schedule Performance of Construction Projects

    62/120

    46

    The use of the project schedule as a tool to improve communication is queried in

    question 4.

    Change is inevitable and every project will experience it (PMI, 2007). The use

    of the project schedule as control tool is dependent on accurate reporting and tracking

    of the baseline. Nonetheless this is dependent on the schedule capabilities of the

    project team. Question 5 addresses the degree to which project schedules are used

    for time control. Overall, the last question surveys the level of satisfaction that the

    respondent has toward project schedule.

    4.3 Survey Process and Results

    The questionnaire was first designed in English (Appendix B) and then translated

    to Chinese (Appendix C). This was done in order to survey the professionals

    project schedule maturity of both Belize and Taiwan.

    The questionnaire was made available to the professionals of the Belizean

    construction industry via e-mails containing an attached Word file and a link to a web

    page. Some of the responses were e-mailed back whilst others were directly

    uploaded to the online web page. Of the 70 questionnaire that were sent to Belize, a

    total of 29 responses were collected. Ten of the responses were e-mailed, whilst the

    remaining 19 were uploaded directly to the web page, this account to 41% of the

    questionnaires sent. None of these responses were discarded.

    The Chinese translated questionnaire web link was also e-mailed to professionals

    of Taiwan in addition to the hard copies that were made available at seminars and

    visits. Taiwanese responses were divided in to three groups: owners, consultants and