Org chart tool linear flow illustration of stepwise process powerpoint 4 stages
Linear Programmimng Chart
-
Upload
shilpanbor6188 -
Category
Documents
-
view
218 -
download
0
Transcript of Linear Programmimng Chart
-
8/14/2019 Linear Programmimng Chart
1/10
LINEARLINEARPROGRAMMIMNGPROGRAMMIMNG
CHARTCHARTPRESENTED BY
SHILPAN PATEL 231134
JAYENDRA PATEL 231133TAPAS KUMAR 231114SHEKHAR SUMAN JHA 231077VISHRUT 231082
-
8/14/2019 Linear Programmimng Chart
2/10
Prof. Awad Hanna
IntroductionIntroduction
A simple diagram to show locat ion
and t ime at which a certain crew will beworking on a given operat ion.
-
8/14/2019 Linear Programmimng Chart
3/10
CharacteristicsCharacteristics
Shows repet itive nature of the
construction.
Progression of work can be seen easily.
Sequence of different work act ivit ies canbe easily understood .
Have fairly high level of detail.
Can be developed and prepared in ashorter t ime period than other formats.
-
8/14/2019 Linear Programmimng Chart
4/10
LINEAR PROGRAMMING CHARTLINEAR PROGRAMMING CHARTFEATURESFEATURES
A practical deterministic approach ofscheduling
Time-distance relationship No crossing of activitiesTime-space buffer
Time
dist
an
ce
12 3
4 5
-
8/14/2019 Linear Programmimng Chart
5/10
NATURE OF LINEAR REPETITIVENATURE OF LINEAR REPETITIVEPROJECTSPROJECTS
There are two basic categories of repetitiveprojects
vVertical repetitive projects.vHorizontal repetitive projects.
v
vVertical repetitive projects.Progress units are discrete entities
vHorizontal repetitive projects.Progress is continuous and is expressed in terms of
length or location.
-
8/14/2019 Linear Programmimng Chart
6/10
Advantages of LPCAdvantages of LPC
Simple way of presenting time & work completionEasier time and cost optimizationSimple modification, update & changeBetter optimization and management of resourcesBetter forecasting based on actual rate of progress
Disadvantages of LPC
Inability to generate critical pathUsed at repetitive projects onlyNo representation of crew learning effectChart is based on location not system
-
8/14/2019 Linear Programmimng Chart
7/10
Example ProjectExample Project
The project was to connect an existing pipeline to awater treatment plant
Length 1000m
Pipe length 12m Dia.76.2cm Thk. 7mm
Trench - depth 2m width 1.8m
Trench should excavated wider at junction of 1m onboth sides
Total number of required pipes was 84
-
8/14/2019 Linear Programmimng Chart
8/10
Example ProjectExample Project
Since it was difficult to weld pipes inside the trench, pipeswere preliminary welded outside.
Trench should be excavated 288m per day
This production for excavation was 12 pairs of pipes perday.
Welders were divided into two crews. Each crew consistedof two welders, two helpers, and one side boom.
The outside-welding crew was responsible for weldingpipes in pairs outside the trench and the inside-weldingcrew welded those pairs inside the trench.
-
8/14/2019 Linear Programmimng Chart
9/10
Example ProjectExample Project
The production rates of outside-welding and inside-welding crews were 8 welds/day, (to connect 8pairs/day) and 6 welds/day (to connect 12pairs/day since each weld connected 2 pairs of
pipes.) After pipes were welded in the trench, twopainters applied epoxy paint at connections toprevent corrosion. The lead-time between the firstand second paint coats was 1 day to assure thepaint is dry. The duration to apply a coat of epoxypaint is 1 day.
Backfill and compaction was performed by eightlaborers and one front-end loader. The daily outputwas estimated to be 220 cubic meters, which wasconverted to 3 pairs of pipes.
REPORT\lpc\CHART.xls
http://smb//tmp/sv6dc.tmp/REPORT/lpc/CHART.xlshttp://smb//tmp/sv6dc.tmp/REPORT/lpc/CHART.xlshttp://smb//tmp/sv6dc.tmp/REPORT/lpc/CHART.xlshttp://smb//tmp/sv6dc.tmp/REPORT/lpc/CHART.xls -
8/14/2019 Linear Programmimng Chart
10/10
THANK YOUTHANK YOU