Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
-
Upload
baldric-woods -
Category
Documents
-
view
225 -
download
2
Transcript of Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
2May 19, 2011 MOM Report-Coney
MOM Schedule
23 Dec (End of RUN + 1 day)Mo 21 NovYordan Karadzhov
Tu 22 NovMo 24 OctLinda Coney
Tu 25 OctMo 26 SepGiorgio Cecchet
Tu 27 SepMo 12 SepLinda Coney
Tu 13 SepMo 15 AugRoumen Tsenov
Tu 16 AugMo 18 JulPierrick Hanlet
Tu 19 JulyMo 4 JulyYağmur Torun
Tu 5 JulyMo 6 JuneVictoria Blackmore
Tu 7 JuneMo 23 MayYağmur Torun
Tu 24 MayMo 25 AprLinda Coney
Tu 26 AprMo 11 AprVictoria Blackmore
Tu 12 AprMo 28 MarPaul Soler
Tu 29 MarMo 28 FebPaul Hodgson
Tu 1st MarMo 14 FebRay Gamet
Tu 15 FebMo 17 JanAlain Blondel and Victoria Blackmore
Ending DateStarting DateMICE Operations Manager
23 Dec (End of RUN + 1 day)Mo 21 NovYordan Karadzhov
Tu 22 NovMo 24 OctLinda Coney
Tu 25 OctMo 26 SepGiorgio Cecchet
Tu 27 SepMo 12 SepLinda Coney
Tu 13 SepMo 15 AugRoumen Tsenov
Tu 16 AugMo 18 JulPierrick Hanlet
Tu 19 JulyMo 4 JulyYağmur Torun
Tu 5 JulyMo 6 JuneVictoria Blackmore
Tu 7 JuneMo 23 MayYağmur Torun
Tu 24 MayMo 25 AprLinda Coney
Tu 26 AprMo 11 AprVictoria Blackmore
Tu 12 AprMo 28 MarPaul Soler
Tu 29 MarMo 28 FebPaul Hodgson
Tu 1st MarMo 14 FebRay Gamet
Tu 15 FebMo 17 JanAlain Blondel and Victoria Blackmore
Ending DateStarting DateMICE Operations Manager
3May 19, 2011 MOM Report-Coney
Recent Happenings
Power outage for substation work – contractors Work on TOF system and KL – Maurizio, Ludovico and group New Rack installation continues – Henry, Roger, Geoff Work on LH2 system in Hall – Matt Hills and co. Arrival of infrastructure for Step IV Target in R78 – Target group EMR group coming soon EMR data-taking in JULY User Run – Beam starts June 27
10 May – 9 June 2011: ISIS run 10 June – 12 June 2011: machine physics – pushed back to June 13/14 13 June – 26 June 2011: shutdown – starts now June 15 27 June – 3 July: run up and machine physics 4 July 2011: machine permits
5 July – 4 August 2011: ISIS run 5 August – 7 August 2011: machine physics 8 August – 4 September 2011: shutdown? (subject to change)
4May 19, 2011 MOM Report-Coney
Power Outage in MICE Hall
POWER OFF: Hall and Rack Room affected
Lights, fire, some wall power still on – ie. Work in Hall continues
Status:DAQ machines OFFPPS rack OFFTarget rack OFFDS rack OFFMagnet rack OFFNetwork switches ON UPS on wallRAID machines OFFONREC01 OFFOPIPC1 & 3 OFFMICESTORE OFF
Checked rack room and all consumer units isolated OFF
Checked all hall racks and all consumer units isolated OFF
POWER ON: MICE Control Room still powered
ON In Hall: Neutron Monitor DS Vacuum pump in DSA SY527 HV crate CKOV air flow
Some Online Computers remain ON for use by group
IOCPC1 ON wall power ONREC02 ON wall ECSERV2 ON wall IOCPC2 ON wall ECSERV ON wall CAGATEWAY ON wall OPIPC2 ON wall
5May 19, 2011 MOM Report-Coney
Work on Substation in Hall
Power out as of Friday May 13 Work began promptly – old equipment already gone Expected complete by Friday May 27 (next week) – possbily sooner
6May 19, 2011 MOM Report-Coney
Return from Power Outage
Developing plan for bringing up the system again Controlled, gradual turn-on of systems Test of equipment – learn of any potential failures early! Turn ON and test w/o beam as much as possible Decay Solenoid cooldown will start as soon as relevant equipment is
powered – likely June 1 Beam test planned for Machine Physics period after current User Run –
now June 13/14 Need experts either at RAL or on call:
DAQ - Yordan, Jean-Sebastien Controls & Monitoring – Pierrick Control Room/Rack Room/New Rack – Craig, Henry DS - Mike Courthold, Matt Hills
Need water restored to Hall – pipes were cut for substation work No water to magnets, magnet PS, LH2 system
7May 19, 2011 MOM Report-Coney
TOF, KL & CKOV Update
Italian groups were at RAL last week working hard to get detectors ready again The repaired SY527 HV crate was delivered and reinstalled in the Hall
HV’s for TOF0, TOF2 must be taken from new tables and have been modified inside minicom
The installation work of last week 9/5-13/5 was successfully accomplished. TOF0 - A PMT on TOF0 was changed with a DSA access by the MIB team KL & TOF2
The RM3 downstream platform was modified to allow easy installation of the EMR calorimeter by the RM3 team (Ludovico, Alfredo, Maximo and Valerio) with the help of the MIB team and the MIce Hall Willie's team
Both detectors were recabled and all PMTs tested. One dead TOF2 PMT was discovered – on the edge - swapped out for a spare
TOF0, TOF2, and KL are in good shape and ready for data-taking TOF1 delivery scheduled for mid-June CKOVa out of beamline – Lucien & David to RAL mid-June
8May 19, 2011 MOM Report-Coney
Rack Room & PPS
New rack almost full (grid data mover PC, micestore, miceacq* servers and DAQ KVM system) Old micestore turned on last Thursday to do requested backup New micestore will be brought online after power outage
Most systems OFF due to substation work
PPS Disconnected from ISIS system during Power Outage DSA now officially part of ISIS – but currently chained up Installation & testing of Hall PPS to happen this month
Requires complex process to test all options within PPS for securing and/or dropping each area
Plan to have Hall PPS during EMR Run
9May 19, 2011 MOM Report-Coney
Target in R78
Ran T2.7 Able to predict behavior of target
Now running T2.8
At MICE/ISIS target meeting last week agreed:
Present DLC/Vespel design IS suitable for use on ISIS Performance of T2 now sufficiently good for it to be considered a “live
spare” for T1, the target presently on ISIS!!
10May 19, 2011 MOM Report-Coney
Next: EMR Running
Another focused data-taking period to test the first installation of the EMR
Production Running - User Run in June/July: Machine physics June 27 - July 3 User Run – July 5 – August 4 Run 5 days/week – M-F 10-12 hours/day (8am-8pm) Personnel needed: MOM, BeamLine Expert, Shift Leader, Shifter
Shift leader has more experience and trains up new person Novices need 1 week training shifts before official shifter
Experts/those doing the study are also there to guide & monitor progress Need to start signing up for Shifts & BLOC duties
11May 19, 2011 MOM Report-Coney
EMR Running
Need to prepare for arrival Schedule of arrival Schedule of installation
What equipment needed here? What personnel? Crane work? Cabling? Etc.
Schedule of data-taking What beam, how much, how determine tests done?
12May 19, 2011 MOM Report-Coney
Conclusions
Everything is OFF at the moment….
However, it is all ready to come back on – this will take some time, but will hopefully be smoother process than last time!
EMR data-taking will be here soon & We must be ready – come take data again!