Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.

13
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report

Transcript of Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.

Linda Coney

MC VCMay 19, 2011

MICE Operations Manager Report

2May 19, 2011 MOM Report-Coney

MOM Schedule

23 Dec (End of RUN + 1 day)Mo 21 NovYordan Karadzhov

Tu 22 NovMo 24 OctLinda Coney

Tu 25 OctMo 26 SepGiorgio Cecchet

Tu 27 SepMo 12 SepLinda Coney

Tu 13 SepMo 15 AugRoumen Tsenov

Tu 16 AugMo 18 JulPierrick Hanlet

Tu 19 JulyMo 4 JulyYağmur Torun

Tu 5 JulyMo 6 JuneVictoria Blackmore

Tu 7 JuneMo 23 MayYağmur Torun

Tu 24 MayMo 25 AprLinda Coney

Tu 26 AprMo 11 AprVictoria Blackmore

Tu 12 AprMo 28 MarPaul Soler

Tu 29 MarMo 28 FebPaul Hodgson

Tu 1st MarMo 14 FebRay Gamet

Tu 15 FebMo 17 JanAlain Blondel and Victoria Blackmore

Ending DateStarting DateMICE Operations Manager

23 Dec (End of RUN + 1 day)Mo 21 NovYordan Karadzhov

Tu 22 NovMo 24 OctLinda Coney

Tu 25 OctMo 26 SepGiorgio Cecchet

Tu 27 SepMo 12 SepLinda Coney

Tu 13 SepMo 15 AugRoumen Tsenov

Tu 16 AugMo 18 JulPierrick Hanlet

Tu 19 JulyMo 4 JulyYağmur Torun

Tu 5 JulyMo 6 JuneVictoria Blackmore

Tu 7 JuneMo 23 MayYağmur Torun

Tu 24 MayMo 25 AprLinda Coney

Tu 26 AprMo 11 AprVictoria Blackmore

Tu 12 AprMo 28 MarPaul Soler

Tu 29 MarMo 28 FebPaul Hodgson

Tu 1st MarMo 14 FebRay Gamet

Tu 15 FebMo 17 JanAlain Blondel and Victoria Blackmore

Ending DateStarting DateMICE Operations Manager

3May 19, 2011 MOM Report-Coney

Recent Happenings

Power outage for substation work – contractors Work on TOF system and KL – Maurizio, Ludovico and group New Rack installation continues – Henry, Roger, Geoff Work on LH2 system in Hall – Matt Hills and co. Arrival of infrastructure for Step IV Target in R78 – Target group EMR group coming soon EMR data-taking in JULY User Run – Beam starts June 27

10 May – 9 June 2011: ISIS run 10 June – 12 June 2011: machine physics – pushed back to June 13/14 13 June – 26 June 2011: shutdown – starts now June 15 27 June – 3 July: run up and machine physics 4 July 2011: machine permits

5 July – 4 August 2011: ISIS run 5 August – 7 August 2011: machine physics 8 August – 4 September 2011: shutdown? (subject to change)

4May 19, 2011 MOM Report-Coney

Power Outage in MICE Hall

POWER OFF: Hall and Rack Room affected

Lights, fire, some wall power still on – ie. Work in Hall continues

Status:DAQ machines OFFPPS rack OFFTarget rack OFFDS rack OFFMagnet rack OFFNetwork switches ON UPS on wallRAID machines OFFONREC01 OFFOPIPC1 & 3 OFFMICESTORE OFF

Checked rack room and all consumer units isolated OFF

Checked all hall racks and all consumer units isolated OFF

POWER ON: MICE Control Room still powered

ON In Hall: Neutron Monitor DS Vacuum pump in DSA SY527 HV crate CKOV air flow

Some Online Computers remain ON for use by group

IOCPC1 ON wall power ONREC02 ON wall ECSERV2 ON wall IOCPC2 ON wall ECSERV ON wall CAGATEWAY ON wall OPIPC2 ON wall

5May 19, 2011 MOM Report-Coney

Work on Substation in Hall

Power out as of Friday May 13 Work began promptly – old equipment already gone Expected complete by Friday May 27 (next week) – possbily sooner

6May 19, 2011 MOM Report-Coney

Return from Power Outage

Developing plan for bringing up the system again Controlled, gradual turn-on of systems Test of equipment – learn of any potential failures early! Turn ON and test w/o beam as much as possible Decay Solenoid cooldown will start as soon as relevant equipment is

powered – likely June 1 Beam test planned for Machine Physics period after current User Run –

now June 13/14 Need experts either at RAL or on call:

DAQ - Yordan, Jean-Sebastien Controls & Monitoring – Pierrick Control Room/Rack Room/New Rack – Craig, Henry DS - Mike Courthold, Matt Hills

Need water restored to Hall – pipes were cut for substation work No water to magnets, magnet PS, LH2 system

7May 19, 2011 MOM Report-Coney

TOF, KL & CKOV Update

Italian groups were at RAL last week working hard to get detectors ready again The repaired SY527 HV crate was delivered and reinstalled in the Hall

HV’s for TOF0, TOF2 must be taken from new tables and have been modified inside minicom

The installation work of last week 9/5-13/5 was successfully accomplished. TOF0 - A PMT on TOF0 was changed with a DSA access by the MIB team KL & TOF2

The RM3 downstream platform was modified to allow easy installation of the EMR calorimeter by the RM3 team (Ludovico, Alfredo, Maximo and Valerio) with the help of the MIB team and the MIce Hall Willie's team

Both detectors were recabled and all PMTs tested. One dead TOF2 PMT was discovered – on the edge - swapped out for a spare

TOF0, TOF2, and KL are in good shape and ready for data-taking TOF1 delivery scheduled for mid-June CKOVa out of beamline – Lucien & David to RAL mid-June

8May 19, 2011 MOM Report-Coney

Rack Room & PPS

New rack almost full (grid data mover PC, micestore, miceacq* servers and DAQ KVM system) Old micestore turned on last Thursday to do requested backup New micestore will be brought online after power outage

Most systems OFF due to substation work

PPS Disconnected from ISIS system during Power Outage DSA now officially part of ISIS – but currently chained up Installation & testing of Hall PPS to happen this month

Requires complex process to test all options within PPS for securing and/or dropping each area

Plan to have Hall PPS during EMR Run

9May 19, 2011 MOM Report-Coney

Target in R78

Ran T2.7 Able to predict behavior of target

Now running T2.8

At MICE/ISIS target meeting last week agreed:

Present DLC/Vespel design IS suitable for use on ISIS Performance of T2 now sufficiently good for it to be considered a “live

spare” for T1, the target presently on ISIS!!

10May 19, 2011 MOM Report-Coney

Next: EMR Running

Another focused data-taking period to test the first installation of the EMR

Production Running - User Run in June/July: Machine physics June 27 - July 3 User Run – July 5 – August 4 Run 5 days/week – M-F 10-12 hours/day (8am-8pm) Personnel needed: MOM, BeamLine Expert, Shift Leader, Shifter

Shift leader has more experience and trains up new person Novices need 1 week training shifts before official shifter

Experts/those doing the study are also there to guide & monitor progress Need to start signing up for Shifts & BLOC duties

11May 19, 2011 MOM Report-Coney

EMR Running

Need to prepare for arrival Schedule of arrival Schedule of installation

What equipment needed here? What personnel? Crane work? Cabling? Etc.

Schedule of data-taking What beam, how much, how determine tests done?

12May 19, 2011 MOM Report-Coney

Conclusions

Everything is OFF at the moment….

However, it is all ready to come back on – this will take some time, but will hopefully be smoother process than last time!

EMR data-taking will be here soon & We must be ready – come take data again!