Linac Installation Status, Schedule & Coordination
description
Transcript of Linac Installation Status, Schedule & Coordination
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/081
Linac Installation Status, Schedule&
Coordination
Jose Chan/Kathleen Ratcliffe
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/082
Linac Status and ScheduleInstallation Coordination
Review 2007 installation issuesComponent statusInstallation statusSafetyScheduleSummary
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/083
Linac-Issues From Last ReviewConcerns of completing 2007 installation (Linac/BC2)
Not getting final RP approval to turn on the beamThere were issues with BC2 shielding and engineer redesigned shielding to accommodate RP requirements
Not receiving repair coils for BX24 on timeBX24 coil was repaired and delivered to SLAC in December 2007. Magnet was measured and installed in January
Not having repair opportunity days, ROD, available to complete BC2 installation
RODs were made available to install BX24 magnet, remaining BC2 earthquake supports and BL22
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/084
Linac- 2007 Installation
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/085
LTU & E-Dump Components StatusLTU and E-Dump design complete except:
Spot shielding in LTUMost components are available for installation with few exceptions of
LTU vacuum chambers expected complete deliveries from vendor by 6/15/08 Spot shielding for LTU not approved by RP yet, however some parts are being fabricated Single Beam Dump in fabrication completed by the end of JuneTDUN in fabrication Supplier delivered two BYD magnet: one measured and second BYD magnet is being prep for magnetic measurements. The third and last magnet is expected to be delivered by June 20th.
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/086
Components Status
L TU STATUS
DESCRIPTIONS DESIGNCOMPONEN
T
BEND BY DONE RFI
BEND BX DONE RFI
BEND BYKIK DONE RFI
BPM SABPM DONE RFI
BPM FFTB BPM DONE RFI
BPM RFBPM DONE 6/18/08
COLLIMATOR MOVABLE DONE RFI
COLLIMATOR FIXED DONE RFI
DUMP SINGLE DONEIn Fabrication 6/30
PROFILE MONITOR OTR DONE RFI
QUAD 0.91Q17.72 DONE RFI
QUAD Q150kG DONE RFI
X/Y CORRECTORS CLASS 4/5 DONE RFI
E-DUMP STATUS
DESCRIPTIONS DESIGN COMPONENT
BEND BYD DONE
Rec’d 2/3 magnets VENDOR FAB-7/3/08
BPM DONE RFI
COLLIMATOR PCPM1L DONE RFI
DUMP MAIN DONE RFI
DUMP SAFETY DONE RFI
PROFILE MONITOR OTRDMP DONE RFI
QUAD 3.25Q20 DONE RFI
TOROID DONE RFI
X/Y CORRECTORS CLASS 4/5 DONE RFI
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/087
RFI Components
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/088
LTU and Dump Installation Status
LTU and Dump installation are managed by Kathleen RatcliffeUsing lessons learned from last two installations and following the same ISMESAll LTU stands are installed in LTU and vacuum components installation have started. Open vacuum installations have just granted under co-occupancy (i.e. interconnect vacuum chambers to the components)Cable installations has begunCompleted all pre-assemblies in building 26 and are staged in “End Station A” for installation
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/089
LTU and Dump Installation Status
Awarded two Davis Bacon contract for LTU: installation of support stands and installation of magnets (80% complete)Awarded one Davis Bacon contract for E-Dump: installation of support stands, e-dump steel and e-dump components installation (not fully available for installation)Submitted purchase requisitions for TDUND, Single Beam Dump and Zero Degree Shielding
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0810
LTU and Dump Installation Status
Mechanical Fabrication department has started component installation in BTH and BTH west Critical issues that could delay completion of installation:
LTU drifts not available in time for beam line vacuum pump downAvailability of Single Beam Dump and TDUND from MFDSpot shielding design approval from RPIon Pump power suppliers not ready in time for vacuum (plans to use local power supplies)Wire cards for Wire Scanners are not yet in fabrication Potential problem between dump supports stands and dump housing, this issue is being resolved by the installation integration engineerInstallation of pit steel is on hold until Crane is available. Crane is certified but has not been transferred to SLAC because it is not on permanent power
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0811
Installation Assurance & Safety
Tailgate meetings before every shift to discuss daily activities and any safety related issuesJob walk with contractors before start of each jobInstallation weekly meetingsInstituted Quality Control check list sign off for both components and post installationSafe Performance Observation walk (minimum once a week for managers)
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0812
Safety Approval Documents
Statement of Work (SOW) – These documents are written by installation manager for Davis Bacon contractor and are submitted to Building Inspection Office, BIO, for approval. BIO requires 11 signatures for approvalDavis Bacon contractors are required to submit and approval of following documents:
Industrial Injury and Illness Prevention Plan (3 approval signatures)Site Specific Safety Plan (4 approval signatures)Job Safety Analysis (3 approval signatures signatures)Rigging Plans (3 approval signatures)
Work Authorization Form (WAF) – this is approval for SLAC employee to work in installation site (8 approval signatures)
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0813
LCLS installation and commissioning time-line
LTU/Und/Dump Install
LTU/UndComm.
Re-commission
Inj/BC2 to SL2
First Lightin FEE
PEP-I
I ru
n
ends FE
E/N
EH
In
stall
PPS C
ert
. LT
U/D
um
p
FEH
In
stall
CD
-4
(7/3
1/2
01
0)
X-R
ays
in N
EH
First Lightin FEH
NEH Operations/ Commissioning
JJ FF MM AA MM JJ JJ AA SS DD JJ FF MM AA MM JJ JJ AA SS OO NN DD JJ FF MM AA MM JJ JJONAA
2008 2009 2010 2008 2009 2010Down
PPS
AAMM
now
Linac/BC2 Commissionin
g FEE
Comm. April 18, 2008
FEH
Hutc
h B
O
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0814
Planning and Scheduling
Daily tailgate meetings – reporting daily installation work activities
Weekly integration meetings – intergroup status reporting
Weekly installation meetings – integration engineers and MFD supervisors discussing technical installation issues
Weekly MFD parts status meetings – discussing status and cost on open work orders
Weekly procurement meetings – discuss open and future purchase orders
Weekly meeting with Turner – planning six weeks look ahead schedule with Turner
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0815
Integrated Schedule
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0816
Schedule
LTU complete date
Magnet installation @95% (Davis Bacon) 6/24/08Install Vacuum components (SLAC-MFD) 9/15/08TDUND, Single Beam Dump & Zero Degree Shielding (Davis Bacon) 9/15/08Cable Installation (Davis Bacon) 9/09/08Check Out 10/30/08
E-DumpComplete stand installation (Davis Bacon) 7/07/08Complete magnet installation (Davis Bacon) 8/01/08Install Dump Shielding (Davis Bacon) 7/15/08
Install Vacuum components/drifts (SLAC-MFD) 8/15/08Cable Installation (Davis Bacon) 11/5/08Check Out 12/31/08
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0817
BTH West
BSY Shielding Wall
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0818
BTH West
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0819
BTH
Jose Chan and Kathleen Ratcliffe
FAC Review- LTU/DUMP installation Status & Schedule
6/16/0820
Summary
Progress towards completion of 2008 installation is going well in a safe working conditionsWhile waiting for beneficial occupancy we pre assembled components to the alignment stages and moved to staging area for installationWe are following the integrated schedule from Richard M. BoyceThere are still some installations challenges:
Co-occupancy with Turner constructionsSome components late into fabrication due to approval from RPHigh rejection rates of copper plated drift tubes from supplierE-Dump not yet fully accessible for installation