Linac-4 current situation and outlook
U. Raich, F. Roncarolo, F. Zocca
BI Technical Board 2
Current situation• Transformers: First equipment to be operational. Very stable. Watchdog still to be
included in beam interlock system• SEMGrids: Many tests were needed to determine the correct polarization
voltages for frame and wires. We sometimes see the FESA class with software trigger instead of external trigger
• Wire Scanners: Initial problems with motor movement. Now stable• Emittance Meter: Several problems with motor movement. At the moment stable
and operational. Measured emittance is too small as compared with simulations.• BSM: Had some problems with external RF reference and wire movement. Looks
ok now. However only few measurements after installation in the tunnel since buncher became available only recently
• BPMs: Need still some work. First position measurement were done. Phase measurements still to be tested. At the moment we only have 2 BPMs
• Halo monitor: Not installed at the moment.
2/27/2014
BI Technical Board 3
A few screen shots from the logbook
2/27/2014
BI Technical Board 42/27/2014
Recent Measurements from BSMs
BI Technical Board 5
Profile and Emittance Measurements with Laser
2/27/2014
BI Technical Board 6
Laser
First Laser tests with Diamond detector measuring the neutrals
2/27/2014
BI Technical Board 7
Angle profile for 1 laser position
2/27/2014
BI Technical Board 8
Laser Outlook
• No budget was foreseen for laser stripping • Need to buy Laser + diamond strip detector• Will allow to measure emittance parasitically
on the operational beam at 160 MeV
2/27/2014
BI Technical Board 9
To be finished at 3 MeV
• Adjustment of bunchers– This is currently done using the spectrometer and
the BSM• The BSM software to
be integrated intocontrol system
2/27/2014
BI Technical Board 10
Planning
2/27/2014
BI Technical Board 11
Next step
• Installation of the first DTL tank.• Move the measurement line after the DTL
tank• Re-cable and re-commission all devices
(except spectrometer)• Repeat measurements at 12 MeV• No new devices!
2/27/2014
BI Technical Board 12
New measurement line at 50/100 MeV
• 3 BPMs will be recuperated from the 3 MeV line• 1 Transformer recuperated from the 3 MeV line• The wire scanners & grid tanks for the intertank regions
are fabricated• 3 new tanks with hor/ver SEMGrid + wire scanner
These tanks were expected to be ready by June but will be delayed until September
• BSM recuperated from 3 MeV lineCables for SEMGrids and WS will be pulled back (use CCDTL cables)BPM and transformer cables are availableBSM prolongation cable is available
2/27/2014
BI Technical Board 13
Still missing from the list
• BPMs for inter-tanks (DTL ones ready, all will be ready by July)
• Transformers after DTL CCDTL and PIMS (ready)• Wire Grids and wire scanners for inter-tanks
(last information I have says ok but must check again)
• BLMsAll should be ready by the end 2014
2/27/2014
BI Technical Board 14
BPMs for the inter-tank
2/27/2014
BI Technical Board 15
Summary
• Transformers, wire scanners, wire grids and BSM have been commissioned
• No big problems are expected for the devices to be installed.
• BPMs need further work at the electronics level• Tanks for Grids and WS at 100 MeV are late
Dates for the inter-tank grids and WS to be verified
• BSM needs software integration (not too urgent)2/27/2014