LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June...

19
LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech

Transcript of LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June...

Page 1: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO-G030258-00-D

Commissioning and Detector PlansStan Whitcomb

Program Advisory Committee

6 June 2003Caltech

Page 2: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 2LIGO-G030258-00-D

Commissioning History

Now

E2 E3 E4

S1 Science

Run

Washington earthquake

First Lock

One Arm

Power Recycled Michelson

Recombined Interferometer

Full Interferometer

Washington 2KLouisiana 4kWashington 4K

LHO 2k wire accident

S2 Science

Run

2002200019991Q 2Q 2Q1Q4Q3Q4Q 3Q

E1 E5Inauguration

E6

4Q 2Q1Q 3Q

E7 E8

10-17 10-18 10-19 10-20L4k strain noise @ 150 Hz [Hz-1/2]

2001

4Q 1Q

E9

10-21

2003

Page 3: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 3LIGO-G030258-00-D

First Science Run (S1)

• August 23 - September 9, 2002 (~400 hours)

• Three LIGO interferometers, plus GEO (Europe) and TAMA (Japan)

• Range for binary neutron star inspiral ~ 40-200 kpc

• Hardware reliability good for this stage in the commissioning» Longest locked section for individual interferometer:

21 hrs (11 in “Science mode”)

LLO-4K LHO-4K LHO-2K 3x Coinc.

Duty cycle 42% 58% 73% 24%

Page 4: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 4LIGO-G030258-00-D

S1 Sensitivities

Will hear about searches for different sources tomorrow

Page 5: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 5LIGO-G030258-00-D

S1 Noise Component Analysis, LLO 4k

G020482-00-D5

Rana Adhikari noise analysis

Page 6: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 6LIGO-G030258-00-D

Changes Between S1 and S2

• Optical lever improvements» Structural stiffening (designed for thermal/kinematic stability, not low vibration)» Improved filtering to take advantage of reduced resonances» Pre-ADC "whitening" for improved dynamic reserve

• Improved DAC "De-Whitening"» Match DAC dynamic range to spectrum of correction forces at each frequency» Tricky handoff; reciprocal analog & digital filters must switch roles after lock

acquisition, without transients

• Digital Suspensions installed on LHO-2K and LLO-4K» New coil drivers & realtime control code for suspensions» Lower noise, switchable dynamic range (200 mA acquisition, 5 mA running)» Separate DC biases for alignment» Better filtering, diagonalization and control/sequencing features

• MORE POWER» Enabled by better alignment stability» Also required control of "I-phase" photocurrent (overload)» Now ~ 1.5 W into mode cleaners, ~ 40 W at beamsplitter (R~40)» Only 10-20 mA average DC photocurrent at dark ports !! (optics very good)

Page 7: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 7LIGO-G030258-00-D

Stability improvements for S2

• Wavefront sensing alignment control progress» LHO-4K: 8 of 10 (14) alignment degrees-of-freedom under

feedback control– Greatly improves long term power stability– Still need: all DOF; more feedback bandwidth to reduce short term

power fluctuations

» LLO-4K: 2 DOF under feedback control– Bandwidth of this loop increased 10x since S1, reducing short term

fluctuations– Phase camera implemented: makes a 2-D map of the RF amplitude

and phase Proven useful as a manual alignment aid

» LHO-4K: 2 DOF under feedback control

Page 8: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 8LIGO-G030258-00-D

S1

6 Jan

Page 9: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 9LIGO-G030258-00-D

Second Science Run (S1)

• February 14 – April 14, 2002 (~ 1400 hours)

• Three LIGO interferometers and TAMA (Japan)

• Steady improvement in sensitivity continues» Range for binary neutron star inspiral for LLO-4K up to 1.2 Mpc

• Duty cycle similar to S1» Increased sensitivity did not degrade operation

» Longest locked stretch ~ 66 hours (LHO-4K)

LLO-4K LHO-4K LHO-2K 3x Coinc.

Duty cycle 37% (42%) 74% (58%) 58% (73%) 22% (24%)

Page 10: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 10LIGO-G030258-00-D

S2 Sensitivities

Approximately 10x improvement over S1

LIGO I Design

Preliminary!

Page 11: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 11LIGO-G030258-00-D

Tasks at Hand

• Seismic retrofit at LLO

• Finish wavefront sensing alignment system

• RFI cleanup, linear power supplies

• Thermal lensing

• Shot noise sensitivity

• Optical gain increase of LSC photodiodes

• Acoustic coupling

• Others: microseismic peak reduction (LHO), ISS, photon calibrator, ASI servo, WFS 5, replace lossy PMCs, clean MC mirrors, digital IO WFS, tune up PSLs, remote power dial, 2K ITMX replacement, read/ process more LSC channels, finish stabilization servos, duty cycle

Page 12: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 12LIGO-G030258-00-D

Commissioning: SEI Upgrade

• The Seismic Isolation System (SEI) at LLO needs to be upgraded» Seismic noise environment much worse below 10 Hz than originally

planned (logging largest factor, but also train, other anthropogenic noise)

» Plan is to add an active, external pre-isolation (EPI) stage without disturbing the alignment of the installed optics

• Current Plan:» Continue prototype testing at LASTI, including migrating from

dSpace to VME based controls

» Review held for 4/18; management decision on how to proceed pending

» Order components, fabricate and assemble; fabrication/assembly phase lasts ~5.5 months

» Installation starts ~Jan ‘04 and should complete ~Apr ‘04

Page 13: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 13LIGO-G030258-00-D

Commissioning: SEI Upgrade at MIT

Hydraulic ExternalPre-Isolator (HEPI)

electro-Magnetic ExternalPre-Isolator (MEPI)

BSC

HYDRAULICACTUATOR(HORIZONTAL)

OFFLOADSPRINGS

HYDRAULICLINES & VALVES

CROSSBEAM

PIER

HAM

STIFFENING BEAM

OFFLOADSPRING

CROSSBEAM

ELECTRO-MAGNETICACTUATORS

Page 14: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 14LIGO-G030258-00-D

Optical characterization

• Good news: optics quality is (almost all) good» Recycling gain meets or exceeds goals

– LLO-4K: Gain of nearly 50 seen, more usually about 45– LHO-4K : Gain of 40-45

» Contrast defect meets or exceeds goals– LLO-4K : Pas/ Pbs = 3 x 10-5

– LLO-4K : Pas/ Pbs = 6 x 10-4

• Bad news: Very low RF sideband gain/efficiency» LHO-4K : Sideband power efficiency to AS port: ~6%

» Cause: thermal lensing in the ITMs isn’t at the design level

» Achieving shot noise goal requires that this be fixed

• LHO-2K: Cause of low recycling gain (20) discovered» Bad AR coating on ITMX, must be replaced

Page 15: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 15LIGO-G030258-00-D

Thermal Lensing

• RF sideband efficiency is very low» Efficiency: TEM00 SB power at anti-

symmetric port, relative to input SB power» H1 efficiency: ~6%» Need a stable PRM: lack of ITM

thermal lens makes g1·g2 > 1

» Thermal lensing relies on point design

• Possible solutions» Change RM (w/ new ROC);

6 month lead time» Add the missing heat to ITMs

with another source» Operate at optimal power

(could be higher or lower than design!)

DC (carrier) RF sidebands

Arm power

RF sidebandsin PRM

Bad mode overlapITM Heating

Page 16: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 16LIGO-G030258-00-D

Shot Noise Sensitivity

• Simple power calculations project a factor of ~2 shortfall» Improvements to SB

efficiency with thermal lensing should get us there

• Pick-off detector» Power levels in pick-off

beams not well controlled, could limit noise through cross-couplings if not careful

Factor of 6 shortonly 10x more light avail.

H2 Sensitivity with 50-70mA of Light

Page 17: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 17LIGO-G030258-00-D

Optical Gain Increase for LSC Photodiodes

• Dynamic range requirement: 1000x» Locking ~100 A / running ~100 mA

» Solution:– Separate PDs for locking (low power)

and running (high power)– Remote control for input power

• ASI signal dominant!

• Multiple AS port detectors» LHO-4K: PAS = ~500 mW 4 detectors

» LLO-4K: PAS = ~30 mW 1 detector

ASI ServoAS Port

Page 18: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 18LIGO-G030258-00-D

Acoustic Peaks: Scattering/clipping• Peaks occur in 80-1000 Hz band, at a level 10-100x the SRD

• Source for LHO correlated noise (stochastic search)

• Considering:» Acoustic isolation improvements: ISC tables only, or all LVEA?» Modify output periscopes/mirror mounts: stiffer, damped» Active ISCT beam direction stabilization» Larger in-vacuum Faraday» Eliminate EO shutters

quiet

loud

Acoustic Excitations

Page 19: LIGO-G030258-00-D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.

LIGO PAC -- June 2003 19LIGO-G030258-00-D

Summary

• Lots to do!