Background

Summer 2014 SFMTA awarded a contract to Siemens

January 2017 First vehicle delivered to SFMTA property

Fall 2017 First vehicle in revenue service

Fall 2018 Operator familiarization complete, systemwide deployment of LRVs

Spring 2019 Initiate replacement phase (Phase II)

Summer 2019 Complete expansion phase (Phase I)

Fall 2025 Complete procurement of replacement phase (Phase II)

2

Page 3: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

0

10

20

30

40

50

60

70

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2017 2018 2019

Calendar Year

3

Project statusAll 68 expansion vehicles will be delivered and in service this summer

In service

Delivered

Page 4: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

Key design features

The new trains feature updates from lessons learned on past procurements:

• Lighter vehicle—quieter ride for passengers and neighbors

• Improved interior design:

o Facilitates flow of people—less blocking the doors

o Increased potential standing capacity—more comfortable ride during peak hours

• Upgraded passenger information—know where you are and where you’re going

• Easier to maintain door and step units—less time spent fixing critical systems

4

Page 5: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

5

Performance and reliability

0

5,000

10,000

15,000

20,000

25,000

30,000

Q4 2018 Q1 2019 Q2 2019 Q3 2019 Q4 2019 Q1 2020 Q2 2020

Mea

n D

ista

nce

Bet

wee

n Fa

ilure

s (M

DB

F)

Siemens Actual Siemens Projected

Contract standard

Reliability Demonstration Program launched August 2018, runs for 2 years

Program validates progress to reliability standard of 25k miles between failure

Fleet currently performing at 6,600, on track to meet target

Page 6: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

6

New Flyer Procurement ReliabilityReliability ramp up and performance fluctuations during wear-in are common in any custom fleet procurement

0

5,000

10,000

15,000

20,000

25,000

30,000

Mea

n D

ista

nce

Bet

wee

n Fa

ilure

s (M

DB

F)

New Flyer Hybrid 60’ Mean Distance Between Failure

Fleet performance

MDBF Trendline

Page 7: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

7

Calgary Siemens LRV procurement

0

5000

10000

15000

20000

25000

30000

Fleet performance

Calgary Transit procured similar Siemens vehicles and also underwent a reliability demonstration during the first two years of regular operation

Page 8: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

8

Planning for LRV4 Phase 2

Replace 151 Bredas on expedited schedule

Incorporate design enhancements based on:

• System Performance

• Operator and Mechanic Feedback

• Customer Feedback Sources— 311, Twitter, Letters, etc.— Intercept survey— Focus groups

Page 9: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

9

Operations and maintenance enhancements

Operations: 20 enhancements

• Improved sunshades for enhanced Operator visibility

• Updated operator panel switches to more easily distinguish functionality (e.g., front door versus all door button)

• Updates to passenger information system to clarify messaging

Maintenance: 22 enhancements

• Updates to wheel design to make wheel-truing easier

• Modify brakes to better distribute force during quick stops

• Changes to panel securements for easier access

We’ve been collecting feedback from operators, maintenance, engineering and the public about all aspects of these vehicles since they first arrived

Page 10: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

Very satisfied

40%

Somewhat satisfied

25%

Neutral12%

Somewhat dissatisfied

13%

Very dissatisfied

10%

Customer Feedback for Phase 2 Survey Results

Riders are overwhelmingly satisfied with the new vehicles

Majority of those surveyed are regular riders, all had first hand experience onboard the new Siemens trains

In all categories we surveyed, people are more satisfied than dissatisfied

Are you satisfied with the new LRV4s?

10

n=340

Page 11: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

Where we’ve got it right

70%

71%

83%

85%

87%

15%

17%

9%

6%

6%

Agree Disagree

n=340

11

There is plenty of space to stand

The trains look attractive

The trains are easy to enter and exit

There are plenty of places to hold on when I am standing

The trains are quiet

Page 12: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

What we heard: Room for improvement

50%

52%

53%

57%

33%

33%

34%

27%

Agree Disagree

12

I feel comfortable sitting on the bench seats because I find the height just right

I feel comfortable sitting on the bench seats

There are plenty of spaces to sit

I feel comfortable sitting on the bench seats when the train accelerates and stops

n=340

Page 13: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

13

Focus group feedback

• The seats are very uncomfortable, they are slippery and need seat definition.

• Most participants like the handholds and want one to three more of them per vertical pole; also received requests for hand straps that accommodate different rider heights.

• Participants liked the wider aislecreated by the sideways-facing seats for people to travel through more easily.

Page 14: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

14

Focus Groups Special considerations

Customers with disabilities

• Similar overall satisfaction levels as all respondents

• High levels of approval for ease of access and egress

• Much higher levels of dissatisfaction with the seats

Shorter riders: 5’4” or less

• Similar overall satisfaction levels as all respondents

• Lower levels of satisfaction with the height of seats

Page 15: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

PASSENGER ENHANCEMENTS

15

Page 16: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

16

Passenger comfort updates

Options for changes were developed to address customer feedback in the following categories:

• Additional handholds

• Seating type

• Interior seating layout

Page 17: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

17

Additional Handholds

ArchwaysProvide handholds in center of aisle

Hand StrapsProvide multi-length hand straps

Page 18: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

18

Seating typeSeat type can be updated to provide more definition of seats and to increase passenger comfort

Seat Options B & C reduce seating capacity

Option A : No change Option B: Freedman Option C: SMC

Page 19: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

19

Seating layout

Base Change

Modest alteration

Lower bench seating 2 inches, except where train control equipment box is stored (applies to all options)

Option 1Modest

alterationConvert area across from leaning bar to single transverse seats

Option 2Intermediate

alterationConvert most longitudinal seats to single transverse seats

Option 3Significant alteration

Convert one side of seating to double transverse seats

Page 20: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

20

Base Change: Lower bench seating

All seats would be lowered 2 inches except over the train control equipment box

Page 21: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

21

Base Change: Lower bench seating

Retains aisle width

Provides more seating variety

Preserves current number of seats

Meets accelerated schedule

Increases hand holds

Page 22: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

22

Option 1: Convert area across from leaning bar to single transverse seats

Page 23: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

23

Option 1: Convert area across from leaning bar to single transverse seats

Retains aisle width

Provides more seating variety

Preserves current number of seats (4 seats fewer)

Meets accelerated schedule

Increases hand holds

Page 24: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

24

Option 2: Convert most longitudinal seats to single transverse seats

Page 25: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

25

Option 2: Convert most longitudinal seats to single transverse seats

Retains aisle width

Provides more seating variety

Preserves current number of seats (12 seats fewer)

Meets accelerated schedule

Increases hand holds

Page 26: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

26

Option 3: Convert one side of seating to double transverse seats

Page 27: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

27

Option 3: Convert one side of seating to double transverse seats

Retains aisle width

Provides more seating variety

Preserves current number of seats

Meets accelerated schedule

Increases hand holds

Page 28: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

28

Seat Layout Summary

Base Change: All Bench

Seating but Lowered

Option 1: Convert area across from

leaning bar to single

transverse seats

Option 2: Convert One

Side to Single Transverse

Seats

Option 3: Convert One

Side to Double Transverse

Seats

Retains Aisle Width

Provides More Seating Variety

Preserves Number of Seats

Meets Accelerated Schedule

Increases HandHolds

Page 29: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

NEXT STEPS29

Page 30: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

How do we take feedback and turn them into improvements?

48%

50%

23%

21%

29%

29%

Seating is more important that the train’s overall capacity

Being able to fit more people standing ineach train is more important than seating

Agree Neutral Disagree

30

• There are no easy choices - even survey responses from the same participants appear to conflict (see below)

• Timeline matters: quick decisions help preserve schedule

• Some changes could impact popular features

n=340

Page 31: LIGHT RAIL VEHICLE PROCUREMENT - SFMTA

31

Timeline

March 2019 Present Options to CAC and Board for Feedback

March - April 2019 Negotiate change order and pricing with Siemens

May 2019 SFMTA Board reviews/approves change order

Summer 2019 Final expansion vehicle in service

December 2020 First replacement LRV delivered

October 2025 Last replacement LRV delivered