Lick Creek Trail Project Status Report City Council Meeting May 22, 2014

Transcript of Lick Creek Hike & Bike Trail

Page 1: Lick Creek Hike & Bike Trail

Lick Creek TrailProject Status Report

City Council MeetingMay 22, 2014

Page 2: Lick Creek Hike & Bike Trail

Background

• 2002 – Proposed in the Bikeway and Pedestrian Master Plan

• 2004 – Prioritized by the Hike and Bike Task Force and adopted by City Council as a High Priority

• 2008 – Funding included in bond referendum approved by voters ($4.4 million)

• 2011 – Awarded contract to Halff Associates to conduct a preliminary design study

• May 2012 – Route alternatives presented to Council

• January 2013 – Awarded design contract to Halff Associates

Page 3: Lick Creek Hike & Bike Trail

Segment A

Page 4: Lick Creek Hike & Bike Trail

Segment A

Segment A (Eagle/Longmire/Barron) Reconstruct sidewalks Address ADA issues Stripe bike lanes Minimize impacts to landscaping, fences, and

neighborhood signs inside the ROW Keep all improvements inside the existing ROW

or existing public access easements

Page 5: Lick Creek Hike & Bike Trail

Segment B

Page 6: Lick Creek Hike & Bike Trail

Segment C

Page 7: Lick Creek Hike & Bike Trail

Budget Information

Project Budget: $4,410,000 Expended to Date: $590,983 Balance: $3,819,017

Construction Estimate w/10% Contingency: $3,400,000

Budgeted Annual O&M Costs: $33,000

Page 8: Lick Creek Hike & Bike Trail

Schedule Information

July 2014: Bid for Construction August 2014: Award Construction Contract September 2014: Receive/Review Initial

Submittals, Hold Preconstruction Conference, and Establish Notice To Proceed Date

October 2014: Notice To Proceed With Construction

October 2015: Final Completion

Page 9: Lick Creek Hike & Bike Trail

QUESTIONS ?