    CHAPTER 1: SITE INVESTIGATIONAims to get potential value bearing land and identify

    types of land for each layer under foundation of

    construction, land strength of soil and moisture

    content.

    Most suitable used to design foundation supply

    something construction where very important

    strength of soil factor because all load focused onthat land.

  • 7/30/2019 LI jkr pasir mas

    3/29

    SOIL INVESTIGATION SELECTION

    Geological condition on site

    Design site surface

    Type of information that is needed

    Cost and time

  • 7/30/2019 LI jkr pasir mas

    4/29

    SOIL TEST WHICH OFTEN CONDUCTED IN

    MALAYSIA

    Mackintosh Probe

    Wash Boring

  • 7/30/2019 LI jkr pasir mas

    5/29

    SOIL TEST UNDER LABORATORY

    Bearing Test California Size Distribution Analysis

    Soil Particle

  • 7/30/2019 LI jkr pasir mas

    6/29

    CHAPTER 2: FOUNDATION

    Defined as part of building structure which it touch

    further to land and also act as lowest part located

    above those land bear. Built to move basic structure burden such as column,

    beam, floor etc to land safely.

  • 7/30/2019 LI jkr pasir mas

    7/29

    FOUNDATION FUNCTION

    Spread building load so that burden altogether can

    be borne by building safely.

    Prevent building of settle into soil.

    To seek stable and flat surface for construction

    works later.

    Increase building stability with are structure in soils.

  • 7/30/2019 LI jkr pasir mas

    8/29

    FOUNDATION SELECTION FACTORS

    Land physical condition

    Building load (live load and dead load)

    Economy

    Nature and kind of building

  • 7/30/2019 LI jkr pasir mas

    9/29

    FOUNDATION TYPES

    Pad Foundation

    Raft Foundation

    Band FoundationPile Foundation

  • 7/30/2019 LI jkr pasir mas

    10/29

    PILE FOUNDATIONIs reinforcement post which aims support one

    building.

    Knocked and implanted into land and concreted withother reinforcement for building pile cap through

    starter bar fitted at him.

    His use main function was to move live load or dead

    load (his structure is own) into soil uniformly andefficient.

  • 7/30/2019 LI jkr pasir mas

    11/29

    TEST ON PILE (STATIC LOADING TEST)Made aimed at:

    Determine maximum liability capacity obtained by pile.

    Ensure pile knocked acceptable from structure aspect.

    Determine link between pile depositions with loaded brought.System used was block system kentledge because amounts of

    weight hit was double pile work load.

    Equipment of necessity to test this is:

    Hydraulic Jack and Pressure Gauge

    Dial Gauge

    Levelling Instrument

    Concrete block

  • 7/30/2019 LI jkr pasir mas

    12/29

    CHAPTER 3: FORMWORK

    Was one mould where concrete is poured and

    reinforced.

    To make up concrete is wanted.Is made from woodwork, steel or plastic

  • 7/30/2019 LI jkr pasir mas

    13/29

    FORMWORK INSTALLATION WORKSMust be built firmly and strong not to curved or

    expand when concrete included in its.

    Must be easy to be opened without damaging ordisturb concrete.

    Must be cleaned fully and should free from wood

    dust, wood shaving, mud dust or other does not

    require.Need to be wiped with mould oil that does not leave

    diacritical concrete, approved prior reinforcement

    housed.

  • 7/30/2019 LI jkr pasir mas

    14/29

    OPEN FORMWORK

    Opened gradually without shaking or shock not to

    occurence of damages in structure surface.

    Minimum time period for period opening formwork

    Mould Place Opening Period

    Timber side 4 days

    Volley to floor 10 days

    Volley to timber 21 days

    Column and wall without load 7 days

    Floor side (volley no come off) 4 days

    Floor which exceeded 3.3m broad 28 days

    Timber bottom 28 days

  • 7/30/2019 LI jkr pasir mas

    15/29

    CHAPTER 4: REINFORCEMENT

    Function to bear load tension which acted in

    concrete.

    Concrete tension combination equivalent to 100% ofhis compressive strength.

    Reinforcement designed to take forces tension

    transferred or dispersed through surface bond two

    that material namely concrete and reinforcement.

  • 7/30/2019 LI jkr pasir mas

    16/29

    Concrete and reinforcement comparison

    Characteristic Concrete Steel

    Strength Weak Good

    Compressive strength Good Good

    Shear strength Good Good

    Durable Good Good

  • 7/30/2019 LI jkr pasir mas

    17/29

    TYPES AND SIZE OF REINFORCEMENTUsual steel reinforcement size available is from

    size 10, 12, 16, 20, 25 and 32.

    Steel length is in standards long form such as5m or 12m.

    Hard Mild Steel

    Known with symbol R'.

    His outer surface shaped smooth.Used for the construction reinforcement does

    not experience strong and common load useis as box link or bunk only.

  • 7/30/2019 LI jkr pasir mas

    18/29

    CONTINUE

    High Tensile Steel

    Known with symbol Y'.

    His exterior is shaped rough.

    Used for construction reinforcement bear load

    heavier.

    Hard Mild Steel High Tensile Steel

  • 7/30/2019 LI jkr pasir mas

    19/29

    REINFORCEMENT INSTALLATION

    Reinforcement set according to engineering drawing

    attached for something that building.

    Reinforcement bars which overlap need to be tied strong

    with binding wire.

    All binder wire end should bend into from formwork

    surface.

  • 7/30/2019 LI jkr pasir mas

    20/29

    CHAPTER 5: CONCRETE

    Is additive is made from cement, sand, aggregate

    and water follow certain ratio.

    His advantage was malleable, achieved of naturalthing, easy formed according to static will, major

    protector to reinforcement of rusty and strong from

    compression aspect.

  • 7/30/2019 LI jkr pasir mas

    21/29

    CONCRETE MATERIALS

    Cement

    Aggregate

    Water

    Additive

  • 7/30/2019 LI jkr pasir mas

    22/29

    CONCRETE CAN BE BLEND BY THREE

    WAYS

    mix by using scoop

    mix by use machine mixer

    obtain supplies of factory blend completed

  • 7/30/2019 LI jkr pasir mas

    23/29

    CONCRETE MIXTURE RATIO

    Mixture Ratio Grade Use In Structure

    1 : 1 : 2 30

    Reinforced concrete basis, beamconcrete land reinforced, strict concreteonce, strict concrete column once,concrete column, wall lift, water tank.

    1 : 1 : 2 25 Strict concrete once, water tank.

    1 : 2 : 4 20Reinforced concrete for column and

    beam.

    1 : 3 : 6 15 Basis floor.

    1 : 5 : 10 10 Site in trench and hard ground work.

  • 7/30/2019 LI jkr pasir mas

    24/29

    TRANSPORT CONCRETE

    Ready mix concrete from factory shall be paid into

    concrete lorry.

    Concrete must be transported as soon as possible from

    tool blend to which place want is poured with fair way to

    avoid again casting.

    For small task, bucket and

    wheelbarrow used and if

    possible, mixer tool or readymix should might be close with

    building structure to save time

    transport. ready mix concrete lorry

  • 7/30/2019 LI jkr pasir mas

    25/29

    CASTING CONCRETEBefore concrete is poured into formwork, slump test

    and cube test performed first.

    Concrete should is poured in places is wanted assoon as possible after mix.

    Should crammed fully by using vibrator device.

  • 7/30/2019 LI jkr pasir mas

    26/29

    COMPACTING CONCRETE

    Aims to produce captured air inside concrete without

    causing isolation materials.

    Concrete packing is made by using vibrator device(compacter).

  • 7/30/2019 LI jkr pasir mas

    27/29

    PRESERVE CONCRETENeeded to assist concrete mix to serve process

    hydration.

    Important because it can avoid this concrete

    surfaces from facing result rift from top layer dryness

    concrete.

    Concrete is preserved with put wet gunny after fresh

    concrete fairly hard and small areas his surface suchas beam and basis.

    Whereas for wide surface such as slab should

    moisten with water.

  • 7/30/2019 LI jkr pasir mas

    28/29

    CONCRETE CUBE TEST Concrete cube made at the site building to seek concrete minimum

    strength like those resides within stated specification. Tools of necessity to test this is mould, ram rod, spatula,

    Preservation Tank and Compressive Machine.

    Test made using steel mould measuring 150mm x 150mm x 150mm.

    Concrete is poured in three pretty similar layers thick. Every layer

    should crammed at least 35 times use ram bar. Concrete accommodated at a suitable place during 24jam before

    mould being stripped.

    Concrete cube placed within curing tank to process curing. This

    process takes time 7, 14 and 21 days.

    After 7 days, cube take out from curing tank and put concrete cube

    into Compressive Machine to be tested his compressive strength.

  • 7/30/2019 LI jkr pasir mas

    29/29

    SLUMP TEST

    Aimed to ensure concrete having same consistency will

    be down with equal distance apart.

    Cone filled with four concrete layers and every layer has

    to be stamped as much as 25 times.

    Then cone need to be pulled on vertically and placed

    beside concrete formed.

    Reduction value is differentiation difference between high

    concrete compared to cone height.

    Distance permitted was 2inch namely 50mm with

    concrete state fall true.