LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September...

18
LHC Status Report LHC Status Report L yn Evans L yn Evans 96 96 th th LHCC meeting LHCC meeting, CERN 19 , CERN 19 th th November 2008 November 2008

Transcript of LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September...

Page 1: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

LHC Status ReportLHC Status ReportLyn EvansLyn Evansyy

9696thth LHCC meetingLHCC meeting, CERN 19, CERN 19thth November 2008November 2008

Page 2: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Situation on 10th SeptemberSituation on 10th September

7 out of 8 sectors fully commissioned for5 TeV operation and 1 sector (3 4)5 TeV operation and 1 sector (3-4)commissioned up to 4 TeV.

Lyn Evans 2

Page 3: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Interim Summary Report on the analysis of the 19th Interim Summary Report on the analysis of the 19th September 2008 incident at the LHCSeptember 2008 incident at the LHC

Incident during poweringIncident during powering

The magnet circuits in the seven other sectors of the LHC had been fully commissioned to theirnominal currents (corresponding to beam energy of 5.5 TeV) before the first beam injection on10 September 2008. For the main dipole circuit, this meant a powering in stages up to a currentof 9 3 kA The dipole circuit of sector 3-4 the last one to be commissioned had only beenof 9.3 kA. The dipole circuit of sector 3-4, the last one to be commissioned, had only beenpowered to 7 kA prior to 10 September 2008. After the successful injection and circulation of thefirst beams at 0.45 TeV, commissioning of this sector up to the 5.5 TeV beam energy level wasresumed as planned and according to established procedures.

On 19 September 2008 morning, the current was being ramped up to 9.3 kA in the main dipolecircuit at the nominal rate of 10 A/s, when at a value of 8.7 kA, a resistive zone developed in theelectrical bus in the region between dipole C24 and quadrupole Q24 The first evidence was theelectrical bus in the region between dipole C24 and quadrupole Q24. The first evidence was theappearance of a voltage of 300 mV detected in the circuit above the noise level: the time was11:18:36 CEST. No resistive voltage appeared on the dipoles of the circuit, individually equippedwith quench detectors with a detection sensitivity of 100 mV each, so that the quench of anymagnet can be excluded as initial event. After 0.39 s, the resistive voltage had grown to 1 V andthe power converter, unable to maintain the current ramp, tripped off at 0.46 s (slow dischargemode). The current started to decrease in the circuit and at 0.86 s, the energy discharge switchopened inserting dump resistors in the circuit to produce a fast power abort In this sequence of

Lyn Evans 3

opened, inserting dump resistors in the circuit to produce a fast power abort. In this sequence ofevents, the quench detection, power converter and energy discharge systems behaved asexpected.

Page 4: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Interim Summary Report on the analysis of the 19th Interim Summary Report on the analysis of the 19th September 2008 incident at the LHCSeptember 2008 incident at the LHC

Sequence of events and consequencesSequence of events and consequences

Within the first second, an electrical arc developed and punctured the heliumenclosure, leading to release of helium into the insulation vacuum of the cryostat.

The spring-loaded relief discs on the vacuum enclosure opened when the pressureexceeded atmospheric, thus relieving the helium to the tunnel. They were howeverunable to contain the pressure rise below the nominal 0.15 MPa absolute in thevacuum enclosures of subsector 23-25, thus resulting in large pressure forces actingon the vacuum barriers separating neighboring subsectors, which most probablydamaged them. These forces displaced dipoles in the subsectors affected from theircold internal supports, and knocked the Short Straight Section cryostats housing thequadrupoles and vacuum barriers from their external support jacks at positions Q23,Q27 and Q31, in some locations breaking their anchors in the concrete floor of thet l Th di l t f th Sh t St i ht S ti t t l d d thtunnel. The displacement of the Short Straight Section cryostats also damaged the“jumper” connections to the cryogenic distribution line, but without rupture of thetransverse vacuum barriers equipping these jumper connections, so that theinsulation vacuum in the cryogenic line did not degrade

Lyn Evans 4

insulation vacuum in the cryogenic line did not degrade.

Page 5: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Interim Summary Report on the analysis of the 19th Interim Summary Report on the analysis of the 19th September 2008 incident at the LHCSeptember 2008 incident at the LHC

Inspection and diagnosticsInspection and diagnostics

The number of magnets to be repaired is at maximum of 5 quadrupoles (inShort Straight Sections) and 24 dipoles, but it is likely that more will have tobe removed from the tunnel for cleaning and exchange of multilayerbe removed from the tunnel for cleaning and exchange of multilayerinsulation. The exact numbers will be known once the ongoing inspectionsare completed. Spare magnets and spare components appear to beavailable in adequate types and sufficient quantities for allowing replacementavailable in adequate types and sufficient quantities for allowing replacementof the damaged ones during the forthcoming shutdown. The extent ofcontamination to the beam vacuum pipes is not yet fully mapped, but knownt b li it d i it l i i b i id d t k t i i thto be limited; in situ cleaning is being considered to keep to a minimum thenumber of magnets to be removed. The plan for removing/reinstallation,transport and repair of magnets in sector 3-4 is being established andintegrated with the maintenance and consolidation work to be performedduring the winter shutdown. The corresponding manpower resources havebeen secured.

Lyn Evans 5

Page 6: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

1919thth septemberseptember incidentincident

Lyn Evans

Page 7: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

BusbarBusbar splicesplice

Lyn Evans

Page 8: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

BusbarBusbar splicesplice

Lyn Evans

Page 9: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Magnet cooling schemeMagnet cooling scheme

Lyn Evans

Page 10: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Cryostat and cold masses longitudinal Cryostat and cold masses longitudinal displacementsdisplacements

Lyn Evans 10Courtesy JP. Tock

Page 11: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Interim Summary Report on the analysis of the 19th Interim Summary Report on the analysis of the 19th September 2008 incident at the LHCSeptember 2008 incident at the LHC

Preliminary recommendationsPreliminary recommendationsPreliminary recommendationsPreliminary recommendations

Recommendations made by the task force aim at two different goals, namely toprevent any other occurrence of this type of initial event, and to mitigate itsp y yp , gconsequences should it however reproduce accidentally. Possible precursors of theincident in sector 3-4 are being scrutinized in the electrical and calorimetric datarecorded on all sectors, in order to spot any other problem of the same nature in thep y pmachine. An improvement of the quench detection system is under way, to generateboth early warnings and interlocks, and to encompass magnets, bus bars andinterconnects. The relief devices on the cryostat vacuum vessels will be increased indischarge capacity and in number, so as to contain a possible pressure rise to below0.15 MPa absolute even in presence of an electrical arc. The external anchoring ofthe cryostats at the locations of the vacuum barriers will be reinforced to guaranteemechanical stability.

Lyn Evans 11

Page 12: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

SubSub--sector magnet cooling schemesector magnet cooling scheme

Q Q DDDD

HXBayonet HX Supply pipeSaturated LHeII

DD D D Q Q DDDDDD D D

HX

CV910

TT911

Q Q DDDDDD D D Q Q DDDDDD D DCV910

PrincipleBlocking of the JT valve at a value to extract the static heatinleaks before the poweringinleaks before the poweringThen, the temperature drift is due to electrical resistiveheating dissipated during the powering

Lyn Evans

Page 13: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

MethodologyMethodology

12001.88Temperature

C t

800

1000

1 86

1.87K]

Current

400

600

1.85

1.86

Curr

ent

Tem

pera

ture

[

200

400

1.84

T

01.83

0 1 2 3 4

Time [hour]

1. Assessment of the baseline slope (remaining CV opening mismatch w/r to static HL)2. Assessment of the temperature increase during powering plateau

Lyn Evans

3. Assessment of the internal energy variation (J/kg)4. Assessment of the deposited energy assuming a mass of 26 l/m of LHeII

Page 14: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Distributed power dissipated during the Distributed power dissipated during the current plateauscurrent plateaus

40

30

35

W/m

]

20

25

ower

[m

5000 A

10

15

ibut

ed p

o 5000 A

5000 A #2

7000 A

0

5

1 1 1 1 1 1 1 2 2 2 2 2 2age

dist

ri

-10

-5

07R1

11R1

15R1

19R1

23R1

27R1

31R1

29L2

25L2

21L2

17L2

13L2

09L2

Aver

a

Lyn Evans

-15

Page 15: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Additional local dissipation in 15R1Additional local dissipation in 15R1

14

10

12

n [W

]

y = 9.2E-08x2.0E+00

8

10

ssip

atio

n

4

6

l loc

al d

i

2

4

ddit

iona

l

-2

0

0 2000 4000 6000 8000 10000 12000

Ad

Lyn Evans

2Dipole current [A]

Page 16: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Conclusion on Conclusion on calorimetrycalorimetry

Calorimetric measurement during the repowering of sector 1-2 hasconfirmed an additional resistive heating in the sub-sector 15R1confirmed an additional resistive heating in the sub sector 15R1

– The corresponding electrical resistance is about 90 nW– At nominal current the additional heat dissipation will be about 13 W (not an issue for

cryogenic system)

Th t l i t t i i i l d th k tThe present calorimetry measurement is impressively good thank to:– the excellent quality of the thermometry.– The excellent stability of the cryoplants and overall system.– The cooling with pressurized superfluid helium.g p p

Room for improvement is existing, especially for the stability of theincoming cooling flow:

– Operate with minimum valve opening (around 20 %) by suppression of all thel t i l h ti dd d i th ld t t dditi l fl f th ldelectrical heating added in the cold-masses to generate additional flow for the cold

compressors (generation of this flow in the QRL return module).– Reduction of the valve-positioner dead-band.

– Diagnose and suppress the instabilities observed in the sub-cooled temperatureDiagnose and suppress the instabilities observed in the sub cooled temperature(upstream the JT valve).

– The accuracy of a calorimetric measurement could then become less than 1 W persub-sector.

Due to the high thermal conductivity of HeII the calorimetry will not

Lyn Evans

Due to the high thermal conductivity of HeII, the calorimetry will notallow to locate the position of a local dissipation below 15 W within asub-sector.

Page 17: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

Results from provoked massive PostResults from provoked massive Post--Mortem of all dipoles in Mortem of all dipoles in Sectors 67 & 78Sectors 67 & 78

Sector 67

S t 78Sector 78

Lyn Evans

Page 18: LHC Status Report - indico.cern.ch · Interim Summary Report on the analysis of the 19th September 2008 incident at the LHC Incident during powering The magnet circuits in the seven

ConclusionsConclusions

The repair is now well underway with approximatelyp y pp y100 people from CERN and contractors working on it.

All damaged magnets will be removed before the endof the year and about 20 new dipoles will be installed.

Powerful techniques have been developed to spotresistive splices at low current.

Steps are being taken to improve the busbarprotection and to avoid collateral damage in theunlikely event of another incident of this kind

Lyn Evans

unlikely event of another incident of this kind.