Levelling-Intro
-
Upload
syarifaharina -
Category
Documents
-
view
214 -
download
0
Transcript of Levelling-Intro
-
7/27/2019 Levelling-Intro
1/40
3a. LEVELLING
Rauf Rasam
1
-
7/27/2019 Levelling-Intro
2/40
OUTLINE
Levelling When do we level?
Definitions/Terminology
Levelling Instrumentation
Method of Levelling
Rules for Levelling
Levelling Procedures (Two peg test, reducing levels
using rise and fall method)
-
7/27/2019 Levelling-Intro
3/40
What is levelling?
A measurement process whereby the relative
dif ference in heigh tbetween two or more points
can be determined
Difference in heightH=BS-FS
BS FS
3
-
7/27/2019 Levelling-Intro
4/40
When do we level?
Typical examples include : To establish new vertical control (BM or TBM)
To determine the heights of discrete points
To provide spot heights or contours on a plan
To provide data for road cross-sections or volumes ofearthworks
To provide a level or inclined plane in the setting out of
construction works To prepare a layout map for engineering work (e.g. Water
supply, road, sanitary or drainage.
4
-
7/27/2019 Levelling-Intro
5/40
Definitions
direction of gravity
level surface
Earth SurfaceA
B
Datum = M.S.L
5
Vertical line
Reduced level
-
7/27/2019 Levelling-Intro
6/40
Definitions (cont.)
BS FS
CP
BS FS
6
BMFixed mark of known RL
TBM
-
7/27/2019 Levelling-Intro
7/40
Definitions (cont.)
Level surface
A curved surface
The direction of gravity is always perpendicular to a
level surface
Horizontal Plane
A horizontalplane will be tangent to a levelsurface
Over short distances (
-
7/27/2019 Levelling-Intro
8/40
Definitions (cont.)
Datum
A reference surface to which the heights of all points
in a survey or on a site are referred
Datum in Malaysia is Mean Sea Level
8
-
7/27/2019 Levelling-Intro
9/40
Definitions (cont.)
Reduced Level (RL) The height of a point above/below the datum
Benchmark (BM)
A stable reference point of known RL
Usually used as the starting and finishing point when
levelling
Temporary Bench Mark (TBM)
A point placed (e.g. peg, nail, spike) to provide atemporary reference point
9
-
7/27/2019 Levelling-Intro
10/40
Definitions (cont.)
Backsight (BS) Always the first reading from a new instrument station
Foresight (FS)
Always the last reading from the current instrument
station
Intermediate sight (IS)
Any sighting that is not a backsight or foresight
10
-
7/27/2019 Levelling-Intro
11/40
Definitions (cont.)
Change point (CP) Location of the staff when the level is moved
Change points should be...
Stable
Well defined
Recoverable
e.g.
sharp rock, nail, change plate, etc...
Parallax
-Imperfect focusing due to the image move up/down
relative to cross-hairs/plane of diaphragm
11
-
7/27/2019 Levelling-Intro
12/40
Levelling Instruments
Level (e.g. dumpy, wye, tilting, automatic/auto &digital)
Tripod
Levelling Staff
Levelling Staff bubble
50 m tape measure (sometimes)
12
-
7/27/2019 Levelling-Intro
13/40
Levelling Instruments (cont.)
Eyepiece
Circular bubble
Focusing skru
Object lens
Base plateTangent screw
Levelling staff
Auto level
13
Cross hair in adiaphgram of level
-
7/27/2019 Levelling-Intro
14/40
Method of levelling
Barometric levelling Atmospheric Pressures
Trigonometric levelling
Compute by vertical angle and horizontal angle
Also called stadia levelling Direct levelling
Level and levelling staff
14
-
7/27/2019 Levelling-Intro
15/40
Reading an E-face staff
0.315
0.342
0.364
15
-
7/27/2019 Levelling-Intro
16/40
Rules for levelling
Always commence and finish a level run on aBenchmark (BM or TBM)
Keep foresight and backsight distances as equal as
possible
Keep lines of sight short (normally < 50m)
Never read below 0.5m on a staff (refraction)
Use stable, well defined change points
16
-
7/27/2019 Levelling-Intro
17/40
Procedures
Setting Up Instrument
Levelling up
Eliminate of errors (parallax, collimation)
17
1. Temporary Adjustment/ Levelling Adjustment
Setting/Levelling Up Instruments (Observation)
Taking & booking the staff readings Calculating and adjusting/reducting reduced
levels
2. Fieldwork/Labworks
-
7/27/2019 Levelling-Intro
18/40
Procedures/ Levelling Adjustment
Identifies whether the level has a collimation error
Allows the collimation error to be determined
18
Levelling Adjustment: Two peg test
-
7/27/2019 Levelling-Intro
19/40
Two-peg test (Cont.)
19
-
7/27/2019 Levelling-Intro
20/40
Procedures/ Fieldwork/Labworks
20
Setting/Levelling Up Instruments (Observation)
-
7/27/2019 Levelling-Intro
21/40
Procedures/ Fieldwork/Labworks
21
Taking & booking the staff readings
-
7/27/2019 Levelling-Intro
22/40
A sample loop
BM A
CP 1
CP 2
CP 3
Kerb
Post
Kerb
Setup 1
Setup 2
Setup 3
Setup 4
22
-
7/27/2019 Levelling-Intro
23/40
Booking the observations
BM A
CP 1
CP 2
CP 3
Kerb
Post
Kerb
Setup 1
Back Inter Fore Point
BM A
CP 1
1.32
3.98
23
-
7/27/2019 Levelling-Intro
24/40
Booking the observations
BM A
CP 1
CP 2
CP 3
Kerb
Post
Kerb
Setup 1
Setup 2
Back Inter Fore Point
1.32 BM A
3.98 CP 1
Kerb
Post
CP 2
2.56
1.25
3.65
0.67
24
-
7/27/2019 Levelling-Intro
25/40
Booking the observations
BM A
CP 1
CP 2
CP 3
Kerb
Post
Kerb
Setup 1
Setup 2
Setup 3
Back Inter Fore Point
1.32 BM A
2.56 3.98 CP 1
1.25 Kerb
3.65 Post
0.67 CP 2
KerbCP 3
3.49
2.58
1.54
25
-
7/27/2019 Levelling-Intro
26/40
Booking the observations
BM A
CP 1
CP 2
CP 3
Kerb
Post
Kerb
Setup 1
Setup 4
Setup 2
Setup 3
Back Inter Fore Point
1.32 BM A
2.56 3.98 CP 1
1.25 Kerb
3.65 Post
3.49 0.67 CP 2
2.58 Kerb1.54 CP 3
BM A
2.64
3.79
26
-
7/27/2019 Levelling-Intro
27/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 CP 1
1.25 Kerb3.65 Post
3.49 0.67 CP 2
2.58 Kerb
2.64 1.54 CP 3
3.79 BM A
27
-
7/27/2019 Levelling-Intro
28/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 Kerb3.65 Post
3.49 0.67 CP 2
2.58 Kerb
2.64 1.54 CP 3
3.79 BM A
28
-
7/27/2019 Levelling-Intro
29/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 Post
3.49 0.67 CP 2
2.58 Kerb
2.64 1.54 CP 3
3.79 BM A
29
-
7/27/2019 Levelling-Intro
30/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 CP 2
2.58 Kerb
2.64 1.54 CP 3
3.79 BM A
30
-
7/27/2019 Levelling-Intro
31/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 Kerb
2.64 1.54 CP 3
3.79 BM A
31
-
7/27/2019 Levelling-Intro
32/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 CP 3
3.79 BM A
32
-
7/27/2019 Levelling-Intro
33/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 1.04 51.18 CP 3
3.79 BM A
33
-
7/27/2019 Levelling-Intro
34/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 1.04 51.18 CP 3
3.79 1.15 50.03 BM A
34
-
7/27/2019 Levelling-Intro
35/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 1.04 51.18 CP 3
3.79 1.15 50.03 BM A
10.01 9.98
35
-
7/27/2019 Levelling-Intro
36/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 1.04 51.18 CP 3
3.79 1.15 50.03 BM A
10.01 9.98
(0.03)
36
-
7/27/2019 Levelling-Intro
37/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 1.04 51.18 CP 3
3.79 1.15 50.03 BM A
10.01 9.98 6.24 6.21
(0.03)
37
-
7/27/2019 Levelling-Intro
38/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 1.04 51.18 CP 3
3.79 1.15 50.03 BM A
10.01 9.98 6.24 6.21
(0.03) (0.03)
38
-
7/27/2019 Levelling-Intro
39/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 1.04 51.18 CP 3
3.79 1.15 50.03 BM A
10.01 9.98 6.24 6.21
(0.03) (0.03) (0.03)
39
-
7/27/2019 Levelling-Intro
40/40
Reducing levels (Rise and Fall)
Back Inter Fore Rise Fall RL Comment
1.32 50.00 BM A
2.56 3.98 2.66 47.34 CP 1
1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post
3.49 0.67 2.98 49.23 CP 2
2.58 0.91 50.14 Kerb
2.64 1.54 1.04 51.18 CP 3
3.79 1.15 50.03 BM A
10.01 9.98 6.24 6.21
(0 03) (0 03) (0 03)
40