Levelling-Intro

download Levelling-Intro

of 40

Transcript of Levelling-Intro

  • 7/27/2019 Levelling-Intro

    1/40

    3a. LEVELLING

    Rauf Rasam

    [email protected]

    1

  • 7/27/2019 Levelling-Intro

    2/40

    OUTLINE

    Levelling When do we level?

    Definitions/Terminology

    Levelling Instrumentation

    Method of Levelling

    Rules for Levelling

    Levelling Procedures (Two peg test, reducing levels

    using rise and fall method)

  • 7/27/2019 Levelling-Intro

    3/40

    What is levelling?

    A measurement process whereby the relative

    dif ference in heigh tbetween two or more points

    can be determined

    Difference in heightH=BS-FS

    BS FS

    3

  • 7/27/2019 Levelling-Intro

    4/40

    When do we level?

    Typical examples include : To establish new vertical control (BM or TBM)

    To determine the heights of discrete points

    To provide spot heights or contours on a plan

    To provide data for road cross-sections or volumes ofearthworks

    To provide a level or inclined plane in the setting out of

    construction works To prepare a layout map for engineering work (e.g. Water

    supply, road, sanitary or drainage.

    4

  • 7/27/2019 Levelling-Intro

    5/40

    Definitions

    direction of gravity

    level surface

    Earth SurfaceA

    B

    Datum = M.S.L

    5

    Vertical line

    Reduced level

  • 7/27/2019 Levelling-Intro

    6/40

    Definitions (cont.)

    BS FS

    CP

    BS FS

    6

    BMFixed mark of known RL

    TBM

  • 7/27/2019 Levelling-Intro

    7/40

    Definitions (cont.)

    Level surface

    A curved surface

    The direction of gravity is always perpendicular to a

    level surface

    Horizontal Plane

    A horizontalplane will be tangent to a levelsurface

    Over short distances (

  • 7/27/2019 Levelling-Intro

    8/40

    Definitions (cont.)

    Datum

    A reference surface to which the heights of all points

    in a survey or on a site are referred

    Datum in Malaysia is Mean Sea Level

    8

  • 7/27/2019 Levelling-Intro

    9/40

    Definitions (cont.)

    Reduced Level (RL) The height of a point above/below the datum

    Benchmark (BM)

    A stable reference point of known RL

    Usually used as the starting and finishing point when

    levelling

    Temporary Bench Mark (TBM)

    A point placed (e.g. peg, nail, spike) to provide atemporary reference point

    9

  • 7/27/2019 Levelling-Intro

    10/40

    Definitions (cont.)

    Backsight (BS) Always the first reading from a new instrument station

    Foresight (FS)

    Always the last reading from the current instrument

    station

    Intermediate sight (IS)

    Any sighting that is not a backsight or foresight

    10

  • 7/27/2019 Levelling-Intro

    11/40

    Definitions (cont.)

    Change point (CP) Location of the staff when the level is moved

    Change points should be...

    Stable

    Well defined

    Recoverable

    e.g.

    sharp rock, nail, change plate, etc...

    Parallax

    -Imperfect focusing due to the image move up/down

    relative to cross-hairs/plane of diaphragm

    11

  • 7/27/2019 Levelling-Intro

    12/40

    Levelling Instruments

    Level (e.g. dumpy, wye, tilting, automatic/auto &digital)

    Tripod

    Levelling Staff

    Levelling Staff bubble

    50 m tape measure (sometimes)

    12

  • 7/27/2019 Levelling-Intro

    13/40

    Levelling Instruments (cont.)

    Eyepiece

    Circular bubble

    Focusing skru

    Object lens

    Base plateTangent screw

    Levelling staff

    Auto level

    13

    Cross hair in adiaphgram of level

  • 7/27/2019 Levelling-Intro

    14/40

    Method of levelling

    Barometric levelling Atmospheric Pressures

    Trigonometric levelling

    Compute by vertical angle and horizontal angle

    Also called stadia levelling Direct levelling

    Level and levelling staff

    14

  • 7/27/2019 Levelling-Intro

    15/40

    Reading an E-face staff

    0.315

    0.342

    0.364

    15

  • 7/27/2019 Levelling-Intro

    16/40

    Rules for levelling

    Always commence and finish a level run on aBenchmark (BM or TBM)

    Keep foresight and backsight distances as equal as

    possible

    Keep lines of sight short (normally < 50m)

    Never read below 0.5m on a staff (refraction)

    Use stable, well defined change points

    16

  • 7/27/2019 Levelling-Intro

    17/40

    Procedures

    Setting Up Instrument

    Levelling up

    Eliminate of errors (parallax, collimation)

    17

    1. Temporary Adjustment/ Levelling Adjustment

    Setting/Levelling Up Instruments (Observation)

    Taking & booking the staff readings Calculating and adjusting/reducting reduced

    levels

    2. Fieldwork/Labworks

  • 7/27/2019 Levelling-Intro

    18/40

    Procedures/ Levelling Adjustment

    Identifies whether the level has a collimation error

    Allows the collimation error to be determined

    18

    Levelling Adjustment: Two peg test

  • 7/27/2019 Levelling-Intro

    19/40

    Two-peg test (Cont.)

    19

  • 7/27/2019 Levelling-Intro

    20/40

    Procedures/ Fieldwork/Labworks

    20

    Setting/Levelling Up Instruments (Observation)

  • 7/27/2019 Levelling-Intro

    21/40

    Procedures/ Fieldwork/Labworks

    21

    Taking & booking the staff readings

  • 7/27/2019 Levelling-Intro

    22/40

    A sample loop

    BM A

    CP 1

    CP 2

    CP 3

    Kerb

    Post

    Kerb

    Setup 1

    Setup 2

    Setup 3

    Setup 4

    22

  • 7/27/2019 Levelling-Intro

    23/40

    Booking the observations

    BM A

    CP 1

    CP 2

    CP 3

    Kerb

    Post

    Kerb

    Setup 1

    Back Inter Fore Point

    BM A

    CP 1

    1.32

    3.98

    23

  • 7/27/2019 Levelling-Intro

    24/40

    Booking the observations

    BM A

    CP 1

    CP 2

    CP 3

    Kerb

    Post

    Kerb

    Setup 1

    Setup 2

    Back Inter Fore Point

    1.32 BM A

    3.98 CP 1

    Kerb

    Post

    CP 2

    2.56

    1.25

    3.65

    0.67

    24

  • 7/27/2019 Levelling-Intro

    25/40

    Booking the observations

    BM A

    CP 1

    CP 2

    CP 3

    Kerb

    Post

    Kerb

    Setup 1

    Setup 2

    Setup 3

    Back Inter Fore Point

    1.32 BM A

    2.56 3.98 CP 1

    1.25 Kerb

    3.65 Post

    0.67 CP 2

    KerbCP 3

    3.49

    2.58

    1.54

    25

  • 7/27/2019 Levelling-Intro

    26/40

    Booking the observations

    BM A

    CP 1

    CP 2

    CP 3

    Kerb

    Post

    Kerb

    Setup 1

    Setup 4

    Setup 2

    Setup 3

    Back Inter Fore Point

    1.32 BM A

    2.56 3.98 CP 1

    1.25 Kerb

    3.65 Post

    3.49 0.67 CP 2

    2.58 Kerb1.54 CP 3

    BM A

    2.64

    3.79

    26

  • 7/27/2019 Levelling-Intro

    27/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 CP 1

    1.25 Kerb3.65 Post

    3.49 0.67 CP 2

    2.58 Kerb

    2.64 1.54 CP 3

    3.79 BM A

    27

  • 7/27/2019 Levelling-Intro

    28/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 Kerb3.65 Post

    3.49 0.67 CP 2

    2.58 Kerb

    2.64 1.54 CP 3

    3.79 BM A

    28

  • 7/27/2019 Levelling-Intro

    29/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 Post

    3.49 0.67 CP 2

    2.58 Kerb

    2.64 1.54 CP 3

    3.79 BM A

    29

  • 7/27/2019 Levelling-Intro

    30/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 CP 2

    2.58 Kerb

    2.64 1.54 CP 3

    3.79 BM A

    30

  • 7/27/2019 Levelling-Intro

    31/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 Kerb

    2.64 1.54 CP 3

    3.79 BM A

    31

  • 7/27/2019 Levelling-Intro

    32/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 CP 3

    3.79 BM A

    32

  • 7/27/2019 Levelling-Intro

    33/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 BM A

    33

  • 7/27/2019 Levelling-Intro

    34/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 1.15 50.03 BM A

    34

  • 7/27/2019 Levelling-Intro

    35/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 1.15 50.03 BM A

    10.01 9.98

    35

  • 7/27/2019 Levelling-Intro

    36/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 1.15 50.03 BM A

    10.01 9.98

    (0.03)

    36

  • 7/27/2019 Levelling-Intro

    37/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 1.15 50.03 BM A

    10.01 9.98 6.24 6.21

    (0.03)

    37

  • 7/27/2019 Levelling-Intro

    38/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 1.15 50.03 BM A

    10.01 9.98 6.24 6.21

    (0.03) (0.03)

    38

  • 7/27/2019 Levelling-Intro

    39/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 1.15 50.03 BM A

    10.01 9.98 6.24 6.21

    (0.03) (0.03) (0.03)

    39

  • 7/27/2019 Levelling-Intro

    40/40

    Reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 1.15 50.03 BM A

    10.01 9.98 6.24 6.21

    (0 03) (0 03) (0 03)

    40