Lessons Learnt After the Prestige
Response Methods and Equipment on the Coast
Eugene Clonan
THE IRISH COAST GUARD
x
PRINCESS EVA INCIDENTPRINCESS EVA INCIDENTDonegal BayDonegal Bay
Princess Eva
• Outline– Lead up to the incident– Irish Legislation regarding the response– Actions taken by the Irish Coast Guard– Risk Assessment– STS operation– Tank cleaning and repairs– Sailing
Domestic Legislation• LEGISLATION
• Sea Pollution Act 1991• Merchant Shipping (Salvage & Wreck) Act 1993• Sea Pollution (Amendment) Act 1999
• Marine casualty response –embodies intervention in casualty or salvage situations & protection of the coastline
INITIAL ACTIONS BY IRCG
• Local Authorities informed• MRCC obtain further details from vessel• Aerial surveillance commenced• 3 Coast Guard Staff mobilised to Killybegs• MSD surveyors carry out PSC inspection and detain
vessel. • After further surveys decision was taken to transfer
cargo, bunkers and carry out temporary repairs to enable vessel to sail to port where more permanent repairs to be carried out
• IRCG considered moving the vessel to a more sheltered location, technical advice and weather conditions were against this
1P
1C
1S2S
2C
2P
3S
3P
4S
4C
4P
5S
5P
5C
PS
SS
FP3C
Inspection Survey found the following damage
•8 cracks found on upper deck plates in a transverse direction•Wasted/cracked longitudinals•Local corrosion holes found on deck plate around winches
IRISH COAST GUARDINCIDENT ROOM
KILLYBEGS
RISK ASSESSMENT
IRISH COAST GUARD
Princess EVABALLAST
1P
1C
1S2S
2C
2P
3S
3P
4S
4C
4P
5S
5P
5C
PS
SS
EngineRoom
FP3C
1P
1C
1S2S
2C
2P
3S
3P
4S
4C
4P
5S
5P
5C
PS
SS
EngineRoom
FP3C
PRINCESS EVA
CARGO TANKSVGO LOW SULPHUR 28,430 m3 VGO HIGH SULPHUR 30,256 m3
Total 58,686 m3
Pour Point 25C
Specific Gravity .9970
ROLE OF THE IRISH COAST GUARD
• The Irish Coast Guards (IRCG) role throughout the STS operation and subsequent repairs was passive in command but positive in control.
• Objective: to ensure a safe, successful and pollution free incident by ensuring that the STS operation, tank cleaning, gas freeing and repairs were carried out in a text book operation
•
• Actions Directed by IRCG. •• Aerial Surveillance• Tug/tugs in constant attendance• IRCG equipment & response personnel
onscene• OSRL informed for possible assistance• Twice daily meetings with ships
representatives where actions were planned and approved
• The operation was broken down into five phases as follows,
• Phase 1 Arrival of Princess Eva Wednesday 29th January 2003 @1604hrs
• Phase 2 STS transfer• Phase 3 Tank cleaning & gas freeing
MEDIA MANAGEMENT
Regular briefings
Factual accounts
PHASE 2 STS OPERATION
• IRCG directed the Princess Eva to anchor in a sheltered bay. Weather on this part of the coast can be severe in winter.
• STS operations would not be permitted in this area under normal circumstances
•• Detailed risk assessment carried out and followed up with an Oil
Spill Contingency Plan for the STS operation.• IRCG required plans to cover all possible emergencies providing
for a comprehensive response.• IRCG ensured that all guidelines and safety precautions were
adhered to.•• STS operation divided into two parts•• The actual STS operation & oil spill contingency planning
STS OPERATIONIRCG Requirements:Second tug during transhipmentPollution response/recovery vessel with experienced personnel to deploy equipment and recover
• STS plan outlining operational parameters, procedures and safety for preparation approach discharge and breakaway as per Oil Companies International Marine Forum (OCIMF) STS Guide
STS PLAN• Discharge Plan –Discharge rates-monitor shear
forces and bending moments reflecting Plate erosion and Breaches
• Representative list of equipment Details of Yokahama fenders 4 x 6.5mx3.3m Mooring EquipmentCargo hoses 2x 8”
• Pressure test certs for discharge lines
STS PLANOperational Safety Checklists• Pre-fixture information for each ship (between ship operator/charterer and organiser• Before operations commence Check list• Before run-in and Mooring• Before cargo transfer• Before unmooring
• Safety during cargo transfer• Emergency Contingency Planning• Oil Spill Contingency Plan
Oil Spill ContingencyRisk Analysis
• Collision during mooring and unmooring. The largest wingtankcontains 7800m3 of cargo.
•• During the STS operation the deck fractures on the Princess
Eva could worsen. Two wing tanks contain 15,300 m3 of cargo.•• During the STS transfer the discharge/loading hose(s) or
pipelines could rupture or part on both the Princess Eva and/or transfer vessels. The estimated pumping rate will be 2000m3 per hour.
•Fire or other Emergencies
•Tank Overflow could occur on the transferring or transfer vessels
•
1st STS OPERATION Bro JupiterSwedish 8,800GRT
Commenced 12/2 5hrs 4,000m3 Hsulphur
CARGO PUMP ROOM PRINCESS EVA
2nd STS Operation Princess Pia–Panama 34,000GRT–Commenced 19/2 42hrs 23,981m3 HS
25,536m3 LS
PHASE 3 TANK CLEANING GAS FREEING
• Tank cleaning Plan• The sequence of tank cleaning was from
forrad to aft, total time for tank washing and stripping 48hrs,• Hot SW wash Temp 65-70C (2cycles as required)• Tanks to be kept inerted during tank cleaning • Slops to stbd slop tank
• Copy of company operations procedures
• As per ISGOTT• International Safety Guide for oil Tankers and Terminals
GAS FREEING• Vessel ventilated
• each cargo tank cleaned with her • own water driven fans•
PHASE 4 REPAIRS
• Plan of repairs, proposed procedures, materials and equipment
• Hot work permits, enclosed space entry in accordance with ISGOTT
• Daily Safety meetings
Princess Eva REPAIRS
Indicating position of doubler plates
1P
1C
1S2S
2C
2P
3S
3P
4S
4C
4P
5S
5P
5C
PS
SS
FP3C
Repairs• Firm contracted to carry out repairs• Foreman , engineer & 10 welders/steel workers• Equipment
Diesel electric welding plants• Deck scrunters• 17 doubler plates @ ¾ ton each• Gas free technician
• Daily Safety meetings Master & Crew• IRCG• Repair Co• Class• Gas Free Tech• Managers Rep
Scafolding inside tanks
PHASE 5 SAILING
• Letter of undertaking S P Act ’91 sect 26 (expences incurred by the minister).
• Repairs Inspected by NKK and MSD surveyors • Issued with conditional safety construction cert
by class• Ship ballast conditions employed for voyage to
repair yard in Argentina; examined and accepted.
• Detention lifted and Princess Eva Sailed on Friday the 7th of March. Routing thru’ Irish Sea.
ConclusionsThe Alarm phase was satisfactory
The overall operation was conducted in a satisfactory manner
The Co-operation with the EU Monitoring Information centre was very satisfactory
In Ireland, no ships are available for counter pollution response in the near shore or off shore area and are sourced internationally.
The Coast Guard uses its own SAR helicopters for aerial surveillance and can call on Defence Force CASA aircraft (No remote sensing eq) for fixed wing surveillance. IRCG has the possibility to contract specialised oil pollution surveillance aircraft and has done so in the past.
Ireland has at present no dedicated 24hr ETV capability but contracted an ASD 50BP tug from Shannon Foynes Port at short notice.
Mobilisation of shore response equipment and personnel to site worked well
• Command and control of the operation by the IRCG worked well
RecommendationsTest Local Authority Contingency Plans
Carry out regular exercises to test Irish Coast Guard Incident Command System in dealing with large marine pollution and salvage incidents.
Although the structures for the National Contingency Plan (NCP) are in place, pursue provision of ETV and Aerial Surveillance capability.
To Conclude:
•?