Lessons Learned WTP Expansion
Transcript of Lessons Learned WTP Expansion
Lessons Learned WTP Expansion
We supply water, one of life’s most vital resources,
enabling our members and
communities to thrive and prosper.
Water where it’s needed.
Strategic Goals
Growth Talent
• Water supply to meet future demands
• Manage peak demands
• Attract
• Develop
• Retain
• Succession planning
Resilience Development
• Reliable Infrastructure
• Asset management
• Financial stability
• Economic development
• Brand/reputation
▪ Member (Customer) owned 501-c Non-Profit Utility (Cooperative)
▪ Governed by an Elected Board of 9Directors
▪ Service started in 1974
▪ Currently serving 50K-connections in Seven Counties (Delaware, Morrow, Marion, Knox, Franklin, Union and Crawford Counties)
▪ 1920 miles water main
▪ 820 mile2 service area;
▪ 4 water treatment plants
WHY THE EXPANSION?
Expanded from 19.2 MGD to 28.8MGD
POPULATION GROWTH / FUTURE DEMAND
Average Day
Peak Day
Master Plan:
Population doubles and
water demand doubles
Agenda Topics
Scope of Assets
Preplanning and Continuous Involvement
Document Data Base
Not as Planned
Unforeseen
Multivista so
moving forward
Line Storage Silo
Add’l Re-carb BasinAdd’l 2 x filters
Add’l backup 1,500KW 4160 generator
1-MG Clear Well
UV Disinfection
and new Control
Systems
Major Assets included in the Project
Controls and Scada
HVAC Controls and Automation
2 Lime slakers and associated eq.
CO2 Tank
Sludge Pump
Sodium Hypochlorite system
Several Chemical Feed Pumps
Our Plan for involvement
Involved from inception
Reviewing plans, commenting
Equipment layout and access
Input Ideas
Generator
Valves and actuators
HVAC Controls
Manuals / Spare Parts
turnover and Labeling
Involvement In Meetings❑ We had a couple of our maintenance & Operations personal
attend the progress meetings
❑ Were able to coordinate shutdown mechanical and electrical
❑ Punch list submitting to the project manager for assignment.
Document Data Base Procore
Project management
• O&M
• Notes
• Spare Parts
• Used this to predefine PM’s
Ability to see
Not as Planned
Some of the asset information was not always easy to find (in manuals)
Parts and Asset information did not get onboarded as we had planned
The progress meetings rarely provided useful information regarding asset management (meeting with the project manager might have been better)
Would have liked to see some training on the use of Procore, very intimidating for the 1st time user
Location of Photos in Multivista Software
Photo attached in MultiVista based on location
Progression to the Finish Line • The Manuals had the Attributes we wanted for assets
• We had turnover written into the spec, how we would receive manuals and spare parts.
• Parts were labeled and Identified (turnover by the contractor not the project Manager)
• No more just dropping them off after the project and figuring out what we had.
Unforeseen Obstacles
Start up key equipment exceeded some break in run periods
The complexity of the UV system and valving, caused mutable delays in training and startup.
COVID-19
Really had trouble getting the correct grease for one of the mixer motors Identified
Set up PM on the Clarifier was missing some new material in the O&M manual
Previous equipment discussions being different at installation (Lime Compressor)
Clarifier Oil site glass Grease fitting
Moving Forward ▪ Have parts list given to us in a document that could be easily crossed into our CMMS
▪ Define our required information for asset onboarding and require the definition in the scope
▪ Require lubrication information from the contractor that was added at start up.
▪ Have key personal assigned to areas of the project, Work with PM
▪ We are building several of these as work Flowsin the new CMMS Maximo Implementation
Asset Management • Asset Management Changes
• CMMS
• Data Gathering
• Encompassing several sections of the Organization
• The key with developing asset management is to continue to make forward strides, Look closer at what might not have worked, learn from it and change it the next time.
• Take what did work and implement it as standard procedure.
Thank You for your Time today