Lesson 8 Import and Refresh - Milestones Professional · Import Primavera information into...

3
15-1 Import a Primavera XML: MS Project Schema file 1. In Milestones Professional, choose Connecons tab. 2. In the Other secon choose Import Schedule from XML File. 3. Select XML: MS Project Schema via Project Import Wizard... 4. Choose your computer's hard drive. 5. Navigate to the Program Files\KIDASA\Milestones Professional 2017\Samples\Lessons folder. 6. Select Primavera File.xml. 7. Choose Open. The XML Project to Milestones Wizard displays. For this lesson choose the following: 1. Choose Category Gan. 2. Choose Type Basic Gan2. 3. For Tag with this ID Field select Unique ID. 4. Choose Next The XML Project to Milestones Wizard - Symbology Opons window displays. 1. Summary Bars - XML/Primavera: Summary informaon will be drawn from Microsoſt Project/XML informaon. If Milestones bars are selected the summary bars shown are based on lower level tasks. 2. Shade Symbol + Bar % complete: Symbols and bars will be colored based on the percent complete of the task. 3. Choose Next. There are 6 categories of charts to choose from. Each category has a variety of opons. As you select each opon the window changes for viewing of the different opons available. The outline level selecon can be used to limit what is imported. For this exercise you will import the enre file. A file nick name is used when refreshing a Milestones file from mulple XML project files. In this lesson you will learn how to: Import Primavera informaon into Milestones Professional using the XML: MS Project Schema file. Update (“refresh”) the Milestones Professional schedule from a changed schedule. Lesson 18 - Import and Refresh from Oracle Primavera Tutorials When starng from your own Primavera file you must save the file as an XML: MS Project Schema to use the XML Project to Milestones Wizard.

Transcript of Lesson 8 Import and Refresh - Milestones Professional · Import Primavera information into...

15-1

Import a Primavera XML: MS Project Schema file

1. In Milestones Professional, choose Connections tab.

2. In the Other section choose Import Schedule from XML File.

3. Select XML: MS Project Schema via Project Import Wizard...

4. Choose your computer's hard drive.

5. Navigate to the Program Files\KIDASA\Milestones Professional 2017\Samples\Lessons folder.

6. Select Primavera File.xml.

7. Choose Open.

The XML Project to Milestones Wizard displays.

For this lesson choose the following:

1. Choose Category Gantt.

2. Choose Type Basic Gantt2.

3. For Tag with this ID Field select Unique ID.

4. Choose Next

The XML Project to Milestones Wizard - Symbology Options window displays.

1. Summary Bars - XML/Primavera: Summary information

will be drawn from Microsoft Project/XML information. If

Milestones bars are selected the summary bars shown are

based on lower level tasks.

2. Shade Symbol + Bar % complete: Symbols and bars will be

colored based on the percent complete of the task.

3. Choose Next.

There are 6 categories of charts to choose from. Each category has a

variety of options. As you select each option the window changes for

viewing of the different options available.

The outline level selection can be used to limit what is imported. For

this exercise you will import the entire file. A file nick name is used

when refreshing a Milestones file from multiple XML project files.

In this lesson you will learn how to:

Import Primavera information into Milestones Professional

using the XML: MS Project Schema file.

Update (“refresh”) the Milestones Professional schedule from a

changed schedule. Lesson 18 - Import and Refresh

from Oracle Primavera

Tutorials

When starting from your own Primavera file you must

save the file as an XML: MS Project Schema to use the

XML Project to Milestones Wizard.

15-2

The XML Project to Milestones Wizard - Choose Additional Columns window displays.

Make the following selection:

1. Under the Columns left of the schedule choose Name.

2. Under the Columns right of the schedule choose Actual Cost.

3. Choose Next.

The XML Project to Milestones Wizard - Symbol Text and Notes window displays.

Make the following selections:

1. Symbol Text for Finish first row: choose Resource Names.

2. Symbol Text for Finish second row: choose Percent Complete .

3. Choose Next.

The Project to Milestones Wizard - Chose Layout Options window displays.

Make the following selections:

1. Show Legend.

2. For Rows per page choose 9.

3. Choose Finish.

4. Save this Milestones Professional schedule to your desktop as Projects and Costs.mlf.

5. Leave it open for the next section of the tutorial.

2017

January February March April May June July August September October

Baseline Summary Baseline Summary Current Plan

Baseline Milestone Milestone

Task nameActual

Cost

MS Project file $1,497,927

Project Alpha $1,094,407

Design $559,140

Test $407,150

Review $54,200

Project Beta $403,520

Design $188,820

Test $169,860

Review $20,980

69%

Blue Team,Green Team,Red Team87%

Blue Team100%

Red Team100%

Green Team35%

Blue Team,Green Team,Red Team49%

Blue Team60%

Red Team55%

Green Team20%

Imported schedule from XML file.

15-3

Update (“refresh”) the Milestones Professional schedule from a changed XML file

1. In Milestones Professional, choose the Connections tab.

2. Select Refresh Previously imported Project.

3. Select Refresh from Project XML File.

4. Choose your computer's hard drive.

5. Navigate to the Program Files\KIDASA\Milestones Professional 2017\Samples\Lessons folder.

6. Select Primavera File Changed.xml.

7. Choose Open.

The MS Project Format XML Refresh Options windows displays.

1. For Refresh Using choose Unique ID.

For Symbol Text:

2. Refresh Symbol Text.

3. Update start and finish symbols using.

4. For Line 1: Start select Duration.

5. For Line 1: Finish select Resource Names.

6. For Line 2: Finish select % Complete.

For Percent complete:

7. Refresh Percent Complete.

8. Choose % Complete.

The following changes were made to the original Primavera file. then saved as Primavera File Changed.XML .

Project Alpha task Review finish date changed to 9/23/2017.

Project Alpha task Review percent complete changed to 100%.

This impacted the actual cost to increase to $158,500.

Refreshed Schedule

For Other Options:

9. Refresh tagged columns.

10. Highlight changed dates.

11. Select OK.