Leona Heights Sulfur Mine Cleanup Lindsay Whalin, MS, PG Engineering Geologist San Francisco Bay Regional Water Quality Control Board

Transcript of Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design...

Page 1: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Leona Heights Sulfur Mine Cleanup

Lindsay Whalin, MS, PG Engineering Geologist San Francisco Bay Regional Water Quality Control Board

Page 2: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

SITE DESCRIPTION

Leona Heights Sulfur Mine 2

Page 3: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Site Description 3

Oakland Hills

Page 4: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Site Description

Mine Tailing Piles

McDonell

Ave. Leona St.

4

pyrite mined

Page 5: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Site Description 5

Leona Creek runs through the site

Page 6: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Upper Tailings Pile 6

Discharge of solid mining waste

Page 7: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Lower Tailings Pile 7

Discharge of solid mining waste

Page 8: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Acid Mine Drainage 8

Sulfuric acid produced on contact of mining waste with water

Page 9: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Leona Creek 9

Page 10: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Evidence of Ongoing Discharge: Acid Mine Drainage

pH As Ni Pb Zn Cd Cu Hg

Leona Creek

5

to 1.5

4

to 1,800

7

to 230

<2

to 110

2,400

to 14,500

7

to 57

5

to 34,000

<0.2

to 27

Water Quality Objectives

6.5 to

8.5

150

52

2.5

120

0.25

9

0.0025

Concentration Range (µg/L)

WET SEASON

DRY SEASON

10

10xWQO* 100xWQO 10,000xWQO

* WQO = water quality objective to protect human and aquatic habitat health

Page 11: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

November 2012 April 2013

Evidence of Ongoing Discharge: Tailings 11

Page 12: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Dry Season – Baseline AMD

Bedrock

Sulfur Tailings + Groundwater = AMD

Groundwater

12

Page 13: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Wet Season – Maximum AMD

Bedrock

Groundwater

Sulfur Tailings + Groundwater + Stormwater = Max AMD

13

Page 14: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Approved Remedial/Restoration Design: Isolate Tailings from Groundwater

Bedrock

Groundwater

14

Page 15: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Bedrock

15

Approved Remedial/Restoration Design: Isolate Tailings from Surface Water

Page 16: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

PERMITTING

Leona Heights Sulfur Mine 16

Page 17: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Permitting 17

City of Oakland Mitigated Negative Declaration

(CEQA) Creek Protection Permit Grading Permit Tree Protection Permit Temporary Traffic Control Plan Erosion Control Plan Construction Management Plan Alternative Materials and

Methods Wet season construction

Alameda County Well Destruction Permit

Army Corps of Engineers Clean Water Act Section 404

(Nationwide Permit)

San Francisco Bay Water Board Remedial Design/Construction

Plan Approval Monitoring and Maintenance

Plan 401 Water Quality Certification Storm Water Pollution

Prevention Plan

California Department of Fish and Wildlife Streambed Alteration

Agreement Incidental Take Permit

(Alameda Whipsnake)

Page 18: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Permitting 18

City of Oakland saves ~ 85 Oak Trees

Image courtesy of E2C Remediation

Original design footprint Revised design footprint

Page 19: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

REMEDY & RESTORATION DESIGN AND CONSTRUCTION

Leona Heights Sulfur Mine 19

Page 20: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Remedial Design Construction 20

Images courtesy of E2C Remediation

Grading of tailings, preparation for slope and cap

Page 21: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Remedial Design Construction 21

Images courtesy of E2C Remediation

Slope reinforcement (Geogrid) layer installation

Page 22: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Remedial Design Construction 22

Images courtesy of E2C Remediation

Slope construction and liner installation, terraces for stability

Page 23: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Remedial Design Construction 23

Images courtesy of E2C Remediation

Next terrace constructed, topsoil over exposed liner

Page 24: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Restoration Design Construction 24

Images courtesy of E2C Remediation

Creek reconstruction, armoring rock placement

Page 25: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Restoration Design Construction 25

Images courtesy of E2C Remediation

Creek step-pools sedimenting in Slopes hydroseeded with natives

Page 26: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

PROJECT STATUS

Leona Heights Sulfur Mine 26

Page 27: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Pre-Construction Post-Construction

It’s Done! - Upper Pile 27

Images courtesy of E2C Remediation

Page 28: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Pre-Construction Post-Construction

It’s Done! - Lower Pile 28

Images courtesy of E2C Remediation

Page 29: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Pre-Construction Post-Construction

It’s Done! - McDonell View 29

Images courtesy of E2C Remediation

Page 30: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

NEXT STEPS

Leona Heights Sulfur Mine 30

Page 31: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

Deed Restriction

Due 180 Days after construction completion√ (completed 9/15)

Monitoring and Maintenance (in progress w/ permitting agencies)

Post construction finishing touches Slope stability Creek stability Native vegetation Post earthquake inspections Post large rain event inspections Water quality improvement

What comes next… 31

Page 32: Leona Heights Sulfur Mine Cleanup€¦ · Leona Heights Sulfur Mine . 19 . Remedial Design Construction 20 Images courtesy of E2C Remediation . Grading of tailings, preparation for

It took a village…

City of Oakland – Darin Ranelletti, Rebecca Tuden, Ed Manasse, Bill Quesada, Dave Mog, & Lesley Estes, David Harlan…

CDFW – Marcia Grefsrud, Annee Ferranti, & Craig Weightman USACE – Greg Brown Project Design Team: E2C Remediation (especially Phil Goalwin and Aiguo Xu),

Environmental, Olberding Environmental, LSA Associates