Leo Craig Business Continuity and Data Security Leo Craig Sales Manager Riello Galatrek Ltd UK...
-
date post
18-Dec-2015 -
Category
Documents
-
view
221 -
download
3
Transcript of Leo Craig Business Continuity and Data Security Leo Craig Sales Manager Riello Galatrek Ltd UK...
Leo Craig
Business Continuity and Data Security
Leo CraigSales Manager
Riello Galatrek Ltd
UK Subsidiary of Riello Elettronica srl
Power QualityUPS Technologies
Specification Considerations
Leo Craig
Poor Power Quality
"Power Quality" - words that either mean absolutely nothing,or are absolutely vital to you.
Source www.marcspages.co.uk
General definition:
Poor Power Quality is any variation in electric power resulting in malfunction or failure of equipment.
General effect:
Loss of Data
Loss of Time
Premature Equipment Failure
General result:
Loss of Revenue
Loss of Customers
Costs MONEY!
Leo Craig
Power Quality
GRID & Distribution CodesStipulates max / min values of voltage, frequency etc.
BS EN 61000-4-7 (G5/4)Harmonics limits and regulations
BS EN 50160Details typical disturbances found on the system.
BS EN 61000-4-15Flicker measurement limits and methods
BS EN 61000-4-30Class A & B for monitoring compliancy
Leo Craig
Power Disturbances
Blackout – Power failure
Surge, over-voltage
Sag, under-voltage
Voltage Spikes
High frequency noise
Frequency variation
Waveshape faults – Frequency shift or Harmonics
Equipment FailureEquipment FailureCPU DamageCPU DamagePSU damagePSU damageHard Drive damageHard Drive damageData corruptionData corruptionComponent stressComponent stressComponent DamageComponent Damage
Leo Craig
Where do disturbances come from?
• Bird strike- O/H lines• Wind – O/H lines• Lightning – O/H lines mostly• Equipment failure• Operational errors• Aggravating factors
– Auto reclosers– Fault tracing
Leo Craig
Where do disturbances come from?
Inside the building ! Factory equipment Office equipment Air conditioning and
elevator drive motors
Leo Craig
The Effects of Power Disturbances
ReferenceReference: George W. Allen and: George W. Allen andDonald Segall, IBM Systems Donald Segall, IBM Systems Development Division. “MonitoringDevelopment Division. “Monitoringof Computer Installations for Power of Computer Installations for Power Line Disturbances” 1974.Line Disturbances” 1974.
Electrical Noise & Transients62.6/Month
48.79%
SpikesTransients50.7/Month
39.52%Mains
Failures0.6/Month
0.47%
Sags, Surges & Brownouts14.4/Month
11.22%
A typical mains supply is quite polluted.
Leo Craig
Did You Know!
A typical computer system is subjected to more than 125 potentially devastating power disturbances each month.
source - Business Week
Every hour of downtime for a typical mid-sized network costs its owner £18,000.
source - Business Week
One-third of all data loss is caused by power problems. source - Business Week
Half of all computer problems are traced to the power line. source - Business Week
Poor power quality costs U.S. businesses more than $26 billion each year! source - Business Week
According to Larry Owens of Silicon Valley Power, a blackout costs Sun Microsystems "up to $1 million per minute."
source- www.nrel.gov
Network DOWNTIME costs:
£50,000 per hour when one megabyte of data needs to be restored or recreated £18,000 an hour for a PC network £90,000 for the transportation industry £6.5 million for large brokerage houses
source – www.unifiedcomputing.com
Leo Craig
CBEMA Voltage Tolerance Curve
Computer & Business Equipment Manufacturers Association (CBEMA) curve
Leo Craig
ITIC Voltage Tolerance Curve
ITIC (Information Technology Industry Council) formally CBEMA curve
EQUIPMENT MALFUNCTION
EQUIPMENT DAMAGE RISK
Leo Craig
Power Solutions
PowerProblem
Standby Power
System Generator
Power Conditioner
CVT
TVSS AutomaticVoltage
Stabiliser (AVS)
UPS
(online) Dual Conversion
Mains Failures Sags /Brownouts Surges Spikes / Transients High Frequency Noise Frequency Variation
Leo Craig
UPS Technologies
Power Problem Off-Line Line InteractiveOn-Line
Double Conversion
Mains Failures Sags / Brownouts Surges Spikes / Transients High Frequency Noise Harmonic Distortion Frequency Variation No Break Change-over
Leo Craig
UPS - Line interactive (Off Line)
MAINS INPUT
OUTPUT LOAD
Inverter
BatteryCharger
UPS
VoltageStabiliser
Leo Craig
UPS - Line interactive (Off Line)
MAINS INPUT
OUTPUT LOAD
Inverter
BatteryCharger
Normal Operation
VoltageStabiliser
Leo Craig
UPS - Line interactive (Off Line)
MAINS INPUT
OUTPUT LOAD
Inverter
BatteryCharger
Mains Failure
VoltageStabiliser
£ = Square wave ££ = Stepped or Quasi sinewave
£££ = Sinewave
2-20mSecsbreak in supply (£)
Leo Craig
On-Line Dual Conversion (VFI)
MAINS INPUT
OUTPUT LOAD
Inverter
Battery
Converter
On line UPS
Static/Maintenance Bypass
VFI = Voltage and Frequency Independent
Leo Craig
On-Line Dual Conversion (VFI)
MAINS INPUT
OUTPUT LOAD
Inverter
Battery
Converter
NORMAL OPERATION
V +/- 20%45-65Hz
V +/- 1%+/-1%Hz
VdcVac Vac
Static/Maintenance Bypass
VFI = Voltage and Frequency Independent
Leo Craig
On-Line Dual Conversion (VFI)
MAINS INPUT
OUTPUT LOAD
Inverter
Battery
Converter
MAINS FAIL
V +/- 1%+/-0.05%Hz
Vdc Vac
Static/Maintenance Bypass
VFI = Voltage and Frequency Independent
Leo Craig
On-Line Dual Conversion (VFI)
MAINS INPUT
OUTPUT LOAD
Inverter
Battery
Converter
OVERLOAD/FAULT
Vac
Static/Maintenance Bypass
VFI = Voltage and Frequency Independent
Leo Craig
Specification Considerations
• Standards required
• Requirements of Load
• Site Considerations
• Type of System
• Autonomy (Back-up time)
• Battery Specification
• Communications
Leo Craig
Standards
BS EN 62040: UPS Industry standard
• BS EN 62040-1-1:2003 Uninterruptible power systems (UPS). General and safety requirements for UPS used in operator access areas
• BS EN 62040-1-2:2003 Uninterruptible power systems (UPS). General and safety requirements for UPS used in restricted access locations
• BS EN 62040-3:2001 Uninterruptible power systems (UPS). Method of specifying the performance and test requirements
Leo Craig
Standards
EN50091-1: Uninterruptible Power supply systems; general provisions of safetyEN50091-1-1: Uninterruptible Power supply systems; general provisions of safety used in
areas accessible to operatorsEN60950 : ITE Information technology equipment safetyEN50091-2: Uninterruptible Power supply systems (UPS) electromagnetic compatibility
provisionsEN50081-2: Electromagnetic compatibility (immunity)EN61000-4-2: Immunity: Electro Static Discharge (ESD)EN61000-4-3: Immunity: Electromagnetic FieldsEN61000-4-4: Immunity: Transient over voltages (BURST)EN61000-4-5: Immunity: Current surges (Surges)EN61000-4-11: Low frequency DisturbancesEN50141: Induced radio interferenceEN55022: Radio frequency disturbanceENV50091-3: UPS performance and test provisionsIEC146 : semiconductor electronic convertersIEC529 : degree of protection of casings
European directives73/23: Low Voltage Directive enforcing CE marking89/336: electromagnetic compatibility directive enforcing CE marking
BS EN 62040 replaces the EN50091 standard.
Leo Craig
Recommendations
UPS will put Harmonics back on to the mains6 Pulse Rectifier typical THD of 20-30%12 Pulse rectifier typical THD less than 8%.
Filters are required to give a THD less than 5%.Active or Passive.
G5/4 States-If load draws more than 16A / phase an assessment should be made.
If in Doubt - Ask the UPS Manufacturer.Remember the Building should comply with the standard not just the UPS
Engineering Recommendation G5/4
Planning levels for Harmonic Voltage Distortion and the connection of non-linear equipment to transmission systems and distribution networks in the United Kingdom
Leo Craig
Sizing the UPS
Total load of equipment – Load list
Manufacturers rating plate will always be maximum worst case load
Stated Amps is often rated at 110Vac and 50% less at 230Vac
Using the manufacturers Wattage and VA ratings may over-size the UPS by up to 50% or worse
Leo Craig
47.26TOTAL POWER REQUIRED Amps
10870TOTAL POWER REQUIRED Watts
702054013LAN switches
150752Screening router
6506501Voice Acquisition Mod
1001001Flat screen TFT
1501501KVM switch
20005004Server
8004002Telecoms Switch
Total Power (w)Power (w)QuantityItem
From the published information the UPS was sized with a load of 10.87kW. A 15kVA UPS that is capable of supplying 12kW was selected.
The running load was estimated to be 6.5kWatts (28Amps) for battery sizing.
Once Installed, the load was monitored and the maximum RMS current drawn by the equipment above was 7.3 amps (1.68 kWatts). Power drawn was 15% of the manufacturers published data.
This is an extreme case but highlights the potential for over-estimating.
Sizing the UPS - Example
Leo Craig
Total load of equipment –
Manufacturers rating plate will always be maximum worst case load
Stated Amps is often rated at 110Vac and 50% less at 230Vac
Using the manufacturers wattage and VA ratings may over-size the UPS by up to 50% or worse
Measure current – RMS and Peak
Future Power RequirementUpgrading to ‘Blade or Edge’ servers (1U high servers -450Watts approx)Rack fully populated could exceed 18kW! ‘Power densities is rising’
What should not be supported
LightingAir – conditioningPhotocopiers/non essential printers
Sizing the UPS
Leo Craig
Multiple Small or One Large UPS
Price per kVA
£0.00
£100.00
£200.00
£300.00
£400.00
£500.00
£600.00
Question - Question - Should I select one large UPS of multiple small UPS Should I select one large UPS of multiple small UPS in my server room?in my server room?
Answer - Answer - Under most circumstances one large UPS is bestUnder most circumstances one large UPS is best
• Cheaper per kVA Cheaper per kVA • Better Build QualityBetter Build Quality• Cheaper and Easier MaintenanceCheaper and Easier Maintenance• Saves SpaceSaves Space
Leo Craig
Site Considerations
• Physical size of the UPS.Delivering and positioning – Will it go through the door?
• Physical weight of the UPSCan it go up the stairs?Will it fall through the floor?
• Location Access: Installation – Servicing - SecurityFloods, Chemicals and Gases.AC, Soil or water pipes overhead.Ventilation – Removal of heat
• Regulations Fire regulations. EPO requirement?Site specific regulations Hospitals, military etc
• Interface with Generator 1.6 times larger minimum than UPS
Leo Craig
400 400
400kVA Configuration - Options
400 KVA Single UPSCost effectiveUPS Fails – No Protection (Raw Mains)
2 x 200 KVABuild up system 200kVa to 400kVAUPS Fails – No Protection (Raw Mains)Expandable System
400
200 200
Parallel Redundant 2 x 400 KVA Full Protection if a UPS FailsExpensive
N+1 Redundant 3 x 200 KVA Full Protection if a UPS FailsTakes up space Expandable
400 400
200 200 200200 200 200200 200 200 200
400
200 200200 200 200
Leo Craig
External Bypass Switch
RECTIFIER INVERTER
STATIC SWITCH
TOEXTENSION
BATTERYCABINET
BYPASS LINE INPUT. (STATIC SWITCH)
INPUT MAINS
BYPASS LINE INPUT. (MAINTENANCE BYPASS)
Bypass Switch.
CRITICAL LOAD
Mains Supply
200kVA Single UPS with External Bypass
Leo Craig
Parallel System With External Bypass
RECTIFIER INVERTER
STATIC SWITCH
TOEXTENSION
BATTERYCABINET
BYPASS LINE INPUT. (STATIC SWITCH)
INPUT MAINS
BYPASS LINE INPUT. (MAINTENANCE BYPASS)
RECTIFIER INVERTER
STATIC SWITCH
TOEXTENSION
BATTERYCABINET
BYPASS LINE INPUT. (STATIC SWITCH)
INPUT MAINS
BYPASS LINE INPUT. (MAINTENANCE BYPASS)
Bypass Switch.
CRITCAL LOAD
Mains Supply
UPS A
UPS B
200kVA Parallel 2 x100kVA with External Bypass
Leo Craig
Parallel Redundant System
RECTIFIER INVERTER
STATIC SWITCH
TOEXTENSION
BATTERYCABINET
BYPASS LINE INPUT. (STATIC SWITCH)
INPUT MAINS
BYPASS LINE INPUT. (MAINTENANCE BYPASS)
RECTIFIER INVERTER
STATIC SWITCH
TOEXTENSION
BATTERYCABINET
BYPASS LINE INPUT. (STATIC SWITCH)
INPUT MAINS
BYPASS LINE INPUT. (MAINTENANCE BYPASS)
CRITCAL LOAD
UPS A
UPS B
Mains Supply
200kVA Parallel Redundant (2 x200kVA) UPS(No Bypass Required)
Leo Craig
Electrical Infrastructure
RECTIFIER INVERTER
STATIC SWITCH
TOEXTENSION
BATTERYCABINET
BYPASS LINE INPUT. (STATIC SWITCH)
INPUT MAINS
BYPASS LINE INPUT. (MAINTENANCE BYPASS)
UPS A
RECTIFIER INVERTER
STATIC SWITCH
TOEXTENSION
BATTERYCABINET
BYPASS LINE INPUT. (STATIC SWITCH)
INPUT MAINS
BYPASS LINE INPUT. (MAINTENANCE BYPASS)
UPS B
RECTIFIER INVERTER
STATIC SWITCH
TOEXTENSION
BATTERYCABINET
BYPASS LINE INPUT. (STATIC SWITCH)
INPUT MAINS
BYPASS LINE INPUT. (MAINTENANCE BYPASS)
UPS C
CRITCAL LOAD
Mains Supply
Leo Craig
Autonomy
Question - How long should the UPS support the load?
Answer - Minimum autonomy as I have a generator!
WRONG!
The autonomy should be as long as it takes to carry out a controlled shutdown!
Answer – I want to keep going for 2, 4 or 8 hours
WRONG!
Temperature rise will be to great if there’s for no air-conditioning 30-45 minutes.
Take into account load shedding. Load reduced = increased autonomy & lower heat output
Battery sharing?Batteries are the weakest component in a UPS!!!
Leo Craig
Battery Specification
Vented - Old Specification, 3 Monthly top-up. Special battery room - gassing. Special Transport required and Handling. COSHH
Recommend to use 2 strings in single UPS applications
Valve Regulated Sealed Lead Acid (VRLA) 5 or 10 year design life and BS6290pt 4. Maintenance free. Used in office environment. Virtually No gassing. Safe to Transport. Mounted in any plane.
NiCad - 20 year design life, 3 Monthly top-up. Special battery room – gassing. Special Transport required. Due to be banned in Europe 2008! COSHH
Plante – 20 year design life, 3 Monthly top-up. Special battery room – gassing. Special Transport and handling required. COSHH
Leo Craig
Battery Gassing
Electrolysis produces Oxygen and Hydrogen on chargeElectrolysis produces Oxygen and Hydrogen on charge
Hydrogen production is 100ml per ah per cell per annum Hydrogen production is 100ml per ah per cell per annum on float chargeon float charge
E.g. 4 x 64 EN160-6 would produce 100ml x 160ah x 4 E.g. 4 x 64 EN160-6 would produce 100ml x 160ah x 4 strings x (4 x 64 cells) NB EN160-6 is 3 cells. (8960kgs strings x (4 x 64 cells) NB EN160-6 is 3 cells. (8960kgs of batteries)of batteries)
Total 12.3 cubic metres of hydrogen per annumTotal 12.3 cubic metres of hydrogen per annumi.e. 1 cubic metre per monthi.e. 1 cubic metre per monthi.e. 0.04 cubic metres of hydrogen per day.i.e. 0.04 cubic metres of hydrogen per day.
Result - negligible gas productionResult - negligible gas production
H2H2
O2O2
Leo Craig
Heat Output
Heat…. Heat….
Battery on charge is exothermic (gives out heat) Battery on charge is exothermic (gives out heat) Battery on discharge is endothermic (takes in heat)Battery on discharge is endothermic (takes in heat)
- On discharge heat is negligibleOn discharge heat is negligible
- On charge heat is 0.02 watts per ah per 12 voltsOn charge heat is 0.02 watts per ah per 12 volts
E.g. 4 x 64 EN160-6 gives off 410 watts of heat on charge. (8960kgs)E.g. 4 x 64 EN160-6 gives off 410 watts of heat on charge. (8960kgs)
Room temperature has a greater effect!Room temperature has a greater effect!
Leo Craig
Battery Life
Room temperature is important!
10 year Design Life Battery
10 year – 20oC
5 year - 30oC
2.5 year - 40oC
Temperature compensated charging avoids over/undercharge
Life increase of 15% max
Other influences
Quality of Charger will affect the life of the battery
Higher the DC ripple the shorter the battery life.
Fast recharges also shorten the battery life.
Leo Craig
COMMUNICATIONS
• Remote Indication – LEDs, LCD, mimics• Volt Free Contacts – BMS • Modem – Remote interrogation by phone • FCT (fixed cell terminals) for remote locations.• 24/7 Monitoring – Service Centre• Controlled Shutdown & Monitoring Software
• RS 232 – Direct connection to server/PC• SNMP – Presence on LAN – WWW• Keep critical servers running longer (load shedding)• Real time monitoring• 24/7 Monitoring - email alert, SMS, WAP