An FPGA Implementation of the Ewald Direct Space and Lennard-Jones Compute Engines
LEARNING OBJECTIVE: Compute the variable manufacturing overhead rate and efficiency variances....
-
Upload
anis-baker -
Category
Documents
-
view
213 -
download
0
Transcript of LEARNING OBJECTIVE: Compute the variable manufacturing overhead rate and efficiency variances....
LEARNING OBJECTIVE: • Compute the variable manufacturing overhead
rate and efficiency variances.• Explain how direct materials standard and direct
labor standards are set.• Compute the direct materials price and quantity
variances and explain their significance.• Compute the direct labor rate and efficiency
variance and explain their significance.
Using Standard Cost-Variable Manufacturing Overhead VariancesBy: G.E ZAFRANATENEO-MBA REGIS PROGRAM 2011-12
Using Standard Costing:• Standard costing means assigning the expected,
budgeted costs to the goods manufactured, the goods in inventory, and the goods sold. In other words, the amounts assigned are the costs that should occur when manufacturing products.
• The actual costs are then compared to the standard costs and any differences are reported as variances. Since the standard costs are often tied to the company's annual profit plan, a variance is also an indicator that the actual profit will be different from the planned amount.
-
-
Following Definition:• Standard Cost- detailed listing of the standard
amounts of inputs and their cost that are required to produce a unit of a specific product
• Standard Cost per Unit- standard quantity allowed of an input per unit of a specific product, multiplied by the standard price of the input
• Standard hours allowed- the time that should been taken to complete the period’s output. It is computed by multiplying the actual number of units produced by the standard hours per unit.
-
• Standard hour per unit-the amount of direct labor time that should be required to complete a single unit of product .
• Standard price per unit- the price that should be paid for an output.
• Standard rate per hour- the labor rate that should be incurred per hour of labor time.
• Variable overhead efficiency variance- the difference between the actual level of activity (direct labor-hours, machine-hours, or some other base) and the standard activity allowed, multiplied by the variable part of the predetermined overhead rate.
• Variable overhead variance-the difference between the actual variable overhead cost incurred during a period and the standard cost that should have been incurred base on the actual activity of the period.
-
Compute the variable manufacturing overhead spending and efficiency variances.
INPUTS (1)Std. Qty or Hr
(2)Std Price or
RateStd. Cost
1 x 2
Direct Materials 1kg 60.25 60.25
Direct Labor P/kg 1kg 17.18 17.18
Vqriqble Mfg Overhead (VMO) .54 10 5.4
TOTAL STANDARD COST/UNIT 82.83
KENPO FOODS has the following direct variable manufacturing overhead labor standard for its Siomai
production.
.9 standard hour per kg siomai at P82.43 per hour
Last month, employees actually worked 240 hours to make 266.40kg siomai. Actual variable manufacturing
overhead for the month was P19,783.20
VMO=82.43 per kg (8.hrs x 30 days)
VMO=19,783.20
Variable Manufacturing Overhead Variances Example
EXHIBIT 11-7Variance Analysis-Variance Manufacturing Overhead
Actual hours Actual Hours Standard Hours Of Input, of Input, Allowed for Actual Output At the Actual Rate at the Standard Rate at the Standard Rate (AH x AR) (AH x SR) (SH x SR) 240 hrs x P9 per hr 240 hrs x P10 per hr 239.76 hrs* x 10 per hr = P2160 =P2400 = P2397.6
Rate variance, P240 F Efficiency variance, P2.4 F
Total variance, P237.6 F
_________*266.40 kg x .90 hr per kg = 239.76F = Favorable ; U = Unfavorable
Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate
240 hours 240 hours 239.76 hours × × × P83 per hour P82.43 per hour P82.43 per hour
= P19, 920 = P19,783.20 = P19, 763.42
Spending varianceP136.8 unfavorable
Efficiency varianceP19.78 favorable
P19,920 240 hours = P83 per hour
Variable Manufacturing Overhead Variances Summary
Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate
240 hours 240 hours 239.76hours × × × P83 per hour $4.00 per hour $4.00 per hour
= P19,920 = P96,000 = P94,000
Spending varianceP136.8 unfavorable
Efficiency varianceP19.78 favorable
.90 hour per kg siomai 266.40 kg of siomai = 239.76
hours
Variable Manufacturing Overhead Variances Summary
Variable Manufacturing Overhead Variances: Using Factored Equations
Variable manufacturing overhead spending varianceVMSV = AH (AR - SR) = 240 (P83 per hour – P82.43 per hour) = 240 hours (P.57 per hour) = P136.8 unfavorable
Variable manufacturing overhead efficiency varianceVMEV = SR (AH - SH) = P82.43 per hour (240 hours – 239.76 hours) = P82.43 per hour (.24 hours) = P19.78 unfavorable
Variance Analysis andManagement by Exception
How do I knowwhich variances to
investigate?
Larger variances, in dollar amount or as a
percentage of the standard, are
investigated first.
A Statistical Control Chart
1 2 3 4 5 6 7 8 9
Variance Measurements
Favorable Limit
Unfavorable Limit
• • •• •
••
••
Warning signals for investigation
Desired Value
Exhibit9-9
Advantages of Standard Costs
Management byexception
Advantages
Promotes economy and efficiency
Simplifiedbookkeeping
Enhances responsibility
accounting
PotentialProblems
Emphasis onnegative may
impact morale.
Emphasizing standardsmay exclude other
important objectives.
Favorablevariances may
be misinterpreted.
Continuous improvement maybe more important
than meeting standards.
Standard costreports may
not be timely.
Invalid assumptionsabout the relationship
between laborcost and output.
Potential Problems with Standard Costs
-