Lean Times in Oil and Gas
-
Upload
advisian -
Category
Engineering
-
view
1.734 -
download
0
Transcript of Lean Times in Oil and Gas
www.advisian.com
Lean times in oil and gasFrugal strategies for emerging as a stronger playerKai Eberspaecher, Senior Associate, Advisian6th June 2016
Exploration has become expensive
Oil price more than halved since 2014
Advisian / 2
Exploration has become expensive
Advisian / 3
Source: IHS
2015 lowest annual level of new discoveries since 1952
1999
2001
2003
2005
2007
2009
2011
2013
2015
0
1000
2000
3000
4000
Average Rig Count
Companies are challenged and take action
International rig count is back to 1999 level
Advisian / 4
Source: Baker Hughes
Companies are challenged and take action
Advisian / 5
Recent Press Headlines:
Shell's BG Risk Starts to Pay as Output Added, Costs SlashedSource: Bloomberg
Exxon, Chevron results weakenSource: Australian
Beach Energy makes $31 million through Merger with DrillsearchSource: Rigzone
What can be done (without spending a lot)?
Advisian / 6
Process improvement
Increased Drilling
Efficiency
Standardisation
Production optimisation
Engineering Design Processes
Portfolio Management Processes
Advisian / 7
Embedding change has to be sustainable
Behaviors
Values
BusinessProcesses
People
ManagementSystem
PerformanceCulture
ResultsBehaviours
Advisian / 8
Example 1: Cycle Time ImprovementAn operator in North America was losing revenue on a drilling program of 400–600 wells per year. Recently drilled and completed wells were sitting idle, awaiting tie-ins.
From:• Good process• Unclear
accountabilities• Silos across the
execution chain
To:• Aligned process
tracking progress• Clear roles and
responsibilities• Training and
coaching• Integrated
execution approach
Aligning various departments and standardising hand-offs, allowed the operator to realise in excess of $ 1 million revenues by eliminating idle time. Drill &
suspend
Complete
Tie-in Produce
Advisian / 9
Example 2: Production ImprovementA large independent E&P operator’s assets included a significant number of production wells. To achieve the company’s growth target existing production had to be optimised.
From:• Absence of daily production
targets• Production data integrity
issues• Lack of actionable
operational performance reporting
• Deficiencies in well operator training
• Well operators attrition through retirement, promotions and resignations.
To:• Implemented production
optimisation system• Visual published production
targets with trends• Key metrics embedded in
operational performance reporting and follow up actions embedded (e.g. root cause analysis)
• Established well operator training manual
Arrest of natural production decline rate established at the start of the project and a 1 – 3 % increase in production observed. Payback was $15 for every $1 spent.
Train Measure
Display
Advisian / 10
Example 3: Lean EngineeringAn operator needed a different approach to meet economic hurdles for hundreds of well sites and associated reserves.
From:• Bespoke well site
design with repetitive engineering activities
• Unclear roles and responsibilities
• Silos from concept to execution
To:• Standardisation
with smart customisation of components
• Design once, use many times
• Lean design and execution process
Reduction of 20% capex per well site and full lifecycle cost reduction of 15%. Improved design cycle time by 30%. Operator saved $4 million on a typical 15 well program.
Standardise
Apply Save
Advisian / 11
Example 4: Portfolio ManagementBrownfield project execution of downstream operator needed to be improved. In the project portfolio risk identification outpaced risk mitigationactivities.
From:• Execution not aligned with
available funding• Nonactionable
communications• Separate engineering and
execution schedules• Cumbersome processes• Unclear roles and
responsibilities
To:• Integrated
engineering and execution schedules
• Prioritised projects with aligned funding
• Clear roles and responsibilities
25% reduction in project cycle times without impacting safety, quality or cost.
Schedule Simplify
Clarify
Summary
Advisian / 12
Now is the time to make changes for the futureExisting structures and processes can be challenged to future proof the business
Changes must not compromise safety and asset integrity performanceAny changes should improve safety and asset integrity of the underlying operations
Four examples presented impacting CAPEX, OPEX and
ProductionSustainable change is achieved by
creating new behaviours
Improvements made in this environment are necessary to assure
survivalIt is unlikely that the next upswing in
commodity prices will allow inefficiency to prevail
DISCLAIMERThis presentation has been prepared by a representative of Advisian.The presentation contains the professional and personal opinions of the presenter, which are given in good faith. As such, opinions presented herein may not always necessarily reflect the position of Advisian as a whole, its officers or executive.Any forward-looking statements included in this presentation will involve subjective judgment and analysis and are subject to uncertainties, risks and contingencies—many of which are outside the control of, and may be unknown to, Advisian. Advisian and all associated entities and representatives make no representation or warranty as to the accuracy, reliability or completeness of information in this document and do not take responsibility for updating any information or correcting any error or omission that may become apparent after this document has been issued.To the extent permitted by law, Advisian and its officers, employees, related bodies and agents disclaim all liability—direct, indirect or consequential (and whether or not arising out of the negligence, default or lack of care of Advisian and/or any of its agents)—for any loss or damage suffered by a recipient or other persons arising out of, or in connection with, any use or reliance on this presentation or information.
Advisian / 13
Thank you