Lean Principles Applied to Extended Value Stream Mapping

72
Lean Principles Applied to Extended Value Stream Mapping To Achieve a Costs Savings in the North American Automotive Industry by Daniel A. Ramos A Research Paper Submitted in Partial Fulfillment of the Requirements for the Master of Science Degree 10 Manufacturing Engineering 3 Semester Credits The Graduate School University of Wisconsin-Stout May 2010

Transcript of Lean Principles Applied to Extended Value Stream Mapping

Page 1: Lean Principles Applied to Extended Value Stream Mapping

Lean Principles Applied to Extended Value Stream Mapping

To Achieve a Costs Savings in the North American

Automotive Industry

by

Daniel A. Ramos

A Research Paper Submitted in Partial Fulfillment of the

Requirements for the Master of Science Degree

10

Manufacturing Engineering

3 Semester Credits

The Graduate School

University of Wisconsin-Stout

May 2010

Page 2: Lean Principles Applied to Extended Value Stream Mapping

Author:

Title:

The Graduate School University of Wisconsin-Stout

Menomonie, WI

Ramos, Daniel A.

Lean Principles Applied to Extended Value Stream Mapping to Acltieve

a Cost Savings il1 tlte Nortlt American Automotive Industry

Graduate Degree/ Major: Master of Science in Manufacturing Engineering

Research Adviser: James Keyes, Ph.D.

MonthfVear: May, 2010

Number of Pages: 72

Style Manual Used: American Psychological Association, 6th edition

Abstract

In 2007, Toyota surpassed General Motors as the world's largest automaker. This

signaled the beginning of a very challenging time for N O1ih America's automakers. Amidst a

worsening global economy and slumping consumer demand, the SUV and pick-up truck sectors

found themselves in deep crisis. Sales plummeted between 2007 and 2008. It became

imperative for these automakers to provide better value for consumers by implementing costs

savings. This paper deals with one such cost savings that was achieved through the application

oflean principles to an extended value stream. Value stream maps were used as the instrument

to study and identify improvement 0ppoliunities. The lean improvement methodology also

relied on value stream maps to model the proposed improved versions ofthe extended value

stream. By passing on part of the savings to the consumer, the automaker was able to provide

better value to its customers. As predicted by the literature, the lean principles for improving

2

Page 3: Lean Principles Applied to Extended Value Stream Mapping

extended value streams resulted in a successful cost savings implementation that benefitted the

automaker, its supplier, and most importantly consumers.

3

Page 4: Lean Principles Applied to Extended Value Stream Mapping

The Graduate School University of Wisconsin Stout

Menomonie, WI

Acknowledgments

First and foremost, I would like to thank my advisor Dr. Jim Keyes for his constant support,

4

guidance, and understanding throughout the thesis writing process. I would also like to thank Dr.

Danny Bee for his encouragement and sound advice during my studies at the University of

Wisconsin-Stout. I am paliicularly grateful to Dr. Pete Heimdahl for encouraging me to apply to

the Master of Science in Manufacturing Engineering. Last but not least, I would like to thank

my family for their suppOli.

Page 5: Lean Principles Applied to Extended Value Stream Mapping

5

Table of Contents

............................................................................................................................... Page

Abstract ....................................................................................................................... 2

List of Figures ............................................................................................................. 8

Chapter I: Introduction ............................................................................................... 9

Statement of the Problem ............................................................................... 10

Purpose of the Study ...................................................................................... 11

Assumptions of the Study .............................................................................. 12

Definition of Terms ....................................................................................... 13

Limitations of the Study ................................................................................ 16

Methodology .................................................................................................. 17

Chapter II: Literature Review ................................................................................... 19

North America's Awakening to Lean Manufacturing .................................... 19

Principles of Lean ........................................................................................... 20

Ford's Contributions to Lean Manufacturing ................................................. 20

The Beginnings of Lean Production ............................................................... 22

The Objective of a Lean Production System .................................................. 23

Jidoka: A First Pillar of the Toyota Production System ................................. 24

Just-in-Time: A Second Pillar of the Toyota Production System ................... 24

The Role of Standardization in the Toyota Production System ...................... 25

The Role Stabilization in the Toyota Production System ............................... 25

At the He31i of the Toyota Production System ............................................... 27

Value Stream Mapping ................................................................................... 27

Page 6: Lean Principles Applied to Extended Value Stream Mapping

6

Extended Value Stream Mapping ................................................................... 29

Extended Value Stream: Future States ........................................................... 30

Cooperation in Extended Value Streams ........................................................ 32

Chapter III: Methodology ......................................................................................... 34

Subject of the Study .... ................................................................................... 35

Instrumentation ... ... .... .......... ......................................................................... 35

Data Collection ...................................................................... .. ..................... 36

Data Analysis ................................................................................................ 37

Current state analysis (future state I) ................................................ 37

Future state II analysis ...................................................................... 42

Ideal state analysis ............................................................................ 46

Limitations of the methodology .................................................................... 52

Chapter IV: Results ................................................................................................... 54

Results of the CUlTent State Extended Value Stream Map ........................... 55

Table 1: Results of Extended Value Stream Improvements ......................... 55

Results ofIdeal State Extended Value Stream Map ..................................... 56

Results of the Lean Implementation ............................................................. 58

Chapter V: Discussion .............................................................................................. 60

Limitations of the Study ............................................................................... 61

Development of the Current State Extended Value Steam Map .................. 62

Development of the Ideal State Extended Value Stream Map ..................... 63

Future state II .................................................................................... 63

Ideal state .......................................................................................... 63

Page 7: Lean Principles Applied to Extended Value Stream Mapping

7

Implementation of the Ideal State Extended Value Stream Map .................. 65

Conclusions ............................................................................ .................. ...... 66

Recommendations ... .................................. : .................................................... 67

Center of knowledge .......................................................................... 67

Value stream manager .............................................................. .. ....... 67

Value stream continuous improvement ............................................. 67

Value stream mapping up-front ........................................................ . 67

References .............. ................................................................................................. 68

Appendix A: Takt Time Calculation ...................................................................... 70

Appendix B: Process Cycle Efficiency Calculation ........................................ ...... . 71

Appendix C: Expected Cost Savings Calculation ................................................... 72

Page 8: Lean Principles Applied to Extended Value Stream Mapping

8

List of Figures

Figure 1: Framex-Universal current state extended value stream map ....................... .40

Figure 2: Framex Facility current state value stream map .................................... .41

Figure 3: Framex-Universal future state II extended value stream map ...................... .44

Figure 4: Framex Facility future state II value stream map ................ .. ...... .. .......... .45

Figure 5: Framex-Universal ideal state extended value stream map .......................... .49

Figure 6: Framex-Mexico facility ideal state value stream map ................................ 50

Figure 7: Framex Canada facility ideal state value stream map ................................ 51

Page 9: Lean Principles Applied to Extended Value Stream Mapping

9

Chapter I: Introduction

The pressure on American vehicle manufacturers to remain competitive has never been

greater. Competition from foreign automakers and decreasing consumer demand have forced

domestic car companies to focus on reducing costs while revamping product lines to include

vehicles that are more appealing to consumers. In short, domestic car companies are striving to

provide better value in order to survive.

In The Machine That Changed the World, Womack, Jones, and Roos (1990) made the

case that lean manufacturing would eventually unseat the mass production model of the early

American automakers such as Ford and General Motors. American companies, the authors

asserted, would have to embrace lean manufacturing to remain competitive with their Japanese

counterparts. Indeed, in 2007, Toyota assumed the rank of the world's largest auto maker. It is

now clear that lean production philosophy, as embodied in the Toyota Production System, has set

a new standard of competition in the global automotive industry.

In NOlih America, auto makers and their suppliers are grappling with the problem of

having to reduce costs while increasing the value passed on to consumers. Adopting lean

manufacturing practices is not only a matter of being competitive these days, it is also a matter of

staying in business (Womack, 2009).

The SUV and pick-up truck sectors have been the hardest hit in this economic downturn.

High gas prices and lower demand have created an urgent need to implement costs savings to

make up for lost revenues. If auto makers and their suppliers can reduce costs, pali of those

savings can be passed on to consumers providing them with better value. These savings can also

help to improve profit margins.

Page 10: Lean Principles Applied to Extended Value Stream Mapping

10

Statement of the Problem

Framex is a Tier 1 supplier of body frames for pick-up trucks and SUV's. It operates

facilities in Mexico and Canada and supplies frames to Universal who is a leading US automaker

based in Michigan. As requested by the companies involved, the names "Universal" and

"Framex" have been used instead of the real company names. Framex's Canadian facility

specializes in the production of steel frames , while its Mexican facility specializes in the

production of aluminum frames. In 2005, when the pick-up platform was launched, the cost of

shipping aluminum frames from Framex Mexico to Michigan was considered relatively

inexpensive. At that time, the American dollar was stronger. Fuel and aluminum prices were

relatively low and a specialized teclmology approach was acceptable (Pinkham, 2005). These

conditions no longer held true in 2008.

The basic problem is as follows. 90% of the pick-up trucks built at Universal's Michigan

assembly plant are built with steel frames shipped from Canada. However, the other 10% are

aluminum frames shipped from Mexico. While Framex Canada is located 126 miles away from

Universal's Michigan location, Framex Mexico is located over 2000 miles away. Given the new

economic circumstances of 2008, it would be ideal if both types of frames could be shipped from

the Canadian Framex facility. However, moving Framex's entire manufacturing operations from

Mexico to Canada is simply not possible within the time constraints of this field problem.

This study will deal with the problem of reducing Universal's cost of purchasing

aluminum frames from Framex, currently shipped from Mexico. In March of 2008, Universal

asked Framex to implement changes to its manufacturing operations that will result in a

significant cost savings. Universal requires that the cost savings be implemented in time for the

new model year change due in August of 2008.

Page 11: Lean Principles Applied to Extended Value Stream Mapping

11

Purpose of the Study

The purpose of this study is to implement lean improvements in the manufacturing

operations of aluminum frames supplied by Framex to Universal ' s Michigan assembly plant.

These improvements needed to be implemented within a period of six months and result in a cost

savings for Universal. If Universal can reduce its costs, some of the savings can be used to

increase its profit margins. Some of the savings can also be passed on as incentives to

consumers, thereby providing better value.

To achieve the purpose of this study, the researcher will use a lean manufacturing

approach based on extended value stream mapping. The process of extended value stream

mapping in this study can be broken down into three sub-problems. The first sub-problem is to

establish the CUlTent state of Framex manufacturing and supply operations. The current state

extended value stream map will serve as a baseline for comparison with the proposed future

state. The second sub-problem will be to analyze the current state and propose changes that will

improve transpOliation links and optimize manufacturing locations. This will result in an ideal

state extended value stream map. The third sub-problem will be to carryout the lean

improvements and evaluate whether the implementation ofthe ideal state was successful.

A lean manufacturing approach is expected to yield benefits for Universal, Framex, and

most importantly for the consumer. As with any lean implementation, a reduction of non-value

added activities is expected as a results of process improvements. A leaner transpOliation

network is also expected as a main outcome including reduced inventories and lead times.

Page 12: Lean Principles Applied to Extended Value Stream Mapping

12

Assumptions of the Study

This study assumes that Universal and Framex will share the burden of financing any

investments required for this cost savings initiative. In other words, the researcher assumes that

Universal and Framex will work cooperatively. This assumption is fundamental to a successful

extended value stream implementation (Dolcemascolo, 2006).

It is also assumed that changes in manufacturing location or equipment will not affect the

quality or reliability of the product. This assumption provides the rationale for not planning for

product validation after the lean implementation is done.

This field problem will be focused on improving the extended value stream. The

researcher assumes that lean production is already taking place within each of the individual

manufacturing locations. Theoretically, the implementation of lean manufacturing within

individual facilities should happen before the extended value stream can be optimized (Jones &

Womack, 2002).

Furthermore, this study assumes that market conditions will remam stable once the

project is completed. Market conditions include cost of materials, fuel prices, and labor. Stable

market conditions also include a stable consumer demand. If market conditions change

drastically immediately after the project is complete, the benefits may not materialize as

anticipated.

Lastly, it is assumed that Universal only pays the cost of shipping of finished goods from

Framex to its pick-up truck assembly plant. Any transportation of PaIts between Framex

facilities is paid by Framex.

Page 13: Lean Principles Applied to Extended Value Stream Mapping

13

Definition of Terms

Changeover time. The time required to adjust a piece of manufacturing equipment to

enable it to make a different product. It is measured as the time between the last good piece of

the previous product to the first good piece of the next product being made at a workcell or

workstation (Duggan, 2002).

Current state extended value stream map. An extended value stream map representing

what is actually in the status quo. It is based on data obtained from observations (Jones &

Womack, 2002).

Cycle time. The time that elapses between two consecutive parts exiting a process O\Tash

& Poling, 2008).

Extended value stream. The series of steps, both value added and non-value added,

required to bring a product or service from material inputs to the customer. These include steps

between facilities and within facilities, as well as transp0l1ation links (Jones & Womack, 2002).

ERP System: Enterprise Resource Planning system (Nash & Poling, 2008).

Facility value stream map. Same as a value stream map. The use of word facility is

used in contrast to extended value map (Jones & Womack, 2002).

Future state I. An improvement over the CUlTent state where all the facilities In an

extended value stream have been converted to lean production (Jones & Womack, 2002).

Future state II. An improvement over the current state where all the facilities in an

extended value stream have been converted to lean production and transp0l1ation has been

optimized (Jones & Womack, 2002).

Heijunka. The discipline of leveling the quantity and mIX of parts being produced

(Rother & Shook, 1999).

Page 14: Lean Principles Applied to Extended Value Stream Mapping

14

Ideal state. An improvement over the current state where all the facilities in an extended

value stream have been converted to lean production, transportation has been optimized, and

location of facilities has been optimized (Jones & Womack, 2002).

Inter-modal cross-dock. A cross-dock that unloads cargo from a truck and loads this

same cargo onto a train (Jones & Womack, 2002).

Jidoka. Refers to automation smart enough to detect defects and halt production when

they occur (LikeI', 2004).

Kaizen. Incremental improvement to a process or a product within a manufacturing

context (Rother & Shook, 1999).

Kaizen burst. This is a planned improvement initiative usually identified on a future

state value stream map (Rother & Shook, 1999).

Kanban. A request signal to produce or withdraw upstream materials in a production

process (Rother & Shook, 1999).

Lead-time. The amount of time elapsed between the order of a product or service to the

time of delivery (Jones & Womack, 2002).

Lean manufacturing. An approach to production based on the philosophy of eliminating

all waste from production operations. In lean manufacturing, production only occurs when there

is a demand from a downstream process (Rother & Shook, 1999).

Non value-added worl{. Work done by a supplier that the customer is not willing to pay

for (Rother & Shook, 1999).

Pacemaker process. The process that receives the production orders and originates the

pull signal for the value stream (Rother & Shook, 1999).

Page 15: Lean Principles Applied to Extended Value Stream Mapping

15

Process cycle efficiency. The ratio of value added time to the total lead-time for a value

stream map

Pull production. The production of pat1s based on a signal received from a downstream

process (Womack & Jones, 1996)

Push production. The production of pat1s without a signal received from a downstream

process (Rother & Shook, 1999).

Tald time. The rate of production required to keep up to the rate of customer orders

(Rother & Shook, 1999).

Tier 1 supplier. A company that sells to an auto maker

Value.

Value can only be defined by the ultimate customer. It is only

meaningful when expressed in terms of a specific product (a good

or a service, and often both at once), which meets the customer's

needs at a specific price at a specific time. (Womack & Jones,

1996, p.16)

Value stream. The series of steps, both value added and non-value added, required to

bring a product or service to the customer (Jones & Womack, 2002).

Value stream map. A diagrammatic representation of a value stream from material

inputs to the delivery of finished good to the customer. Value stream maps contain symbols and

information characterizing the flow of materials and infonnation within a facility. In the case of

extended value stream maps, the transp0l1ation links and multiple facilities are included

(Womack, 2006).

Page 16: Lean Principles Applied to Extended Value Stream Mapping

16

Value-added work. Work done by a supplier that the customer is willing to pay for

(Nash & Poling, 2008).

WIP: Work in process. Unfinished parts accumulated between processes waiting to be finished

(Nash & Poling, 2008).'

Limitations of the Study

This paper will not analyze which product family will result in the value stream with the

best improvement oppOliunities. Instead, the value stream selection is driven by a customer

request.

In this study, the extended value stream is limited to Framex's North American supply of

aluminum pick-up frames to Universal's assembly plant in Michigan. Many value streams exist

between Universal and Framex, consisting of several products and locations, but these will not

be studied here.

Any proposed changes to the extended value stream must be implemented within 6

months: between March and August of2008. This rapid return on investment strategy

demonstrates the urgency that Universal places on this project. In contrast, a typical return on

investment period is one year.

A lean transformation of the individual plants would be a multi-year project and does not

fit with the timing requirements. The researcher will limit this study to lean improvements that

benefit the extended value stream. Lean initiatives within plants will only be undeliaken if they

support improvements to the extended value stream.

All lean initiatives will need to be implemented within the limitations of the existing ERP

system. No significant changes to information systems will be considered in this study.

Page 17: Lean Principles Applied to Extended Value Stream Mapping

Finally, the details of the business case that support the lean implementation will not be

addressed. Instead, the researcher will limit the analysis of the value stream to lean

manufacturing metrics.

Methodology

17

In this study, the researcher used an extended value stream mappmg methodology

developed in Seeing the Whole (Jones & Womack, 2002). In this book, the authors deal with

improvements to a value stream that involves multiple manufacturing locations. This scenario

corresponds closely to the relationship between Universal and Framex in the context of their

NOlih American operations.

In general, value stream mapping consists of three steps (Rother & Shook, 1999). The

first step involves the analysis of the current state. A current state map records what is actually

happening initially at the level of manufacturing and transpOliation operations. Lean metrics

such as non-value added time and travel distances are recorded. This data is used later as a

baseline to determine whether the value stream has become leaner.

Page 18: Lean Principles Applied to Extended Value Stream Mapping

18

The second step consists of proposing lean improvements. Lean principles, such as one­

piece flow, reduction of waste, and minimization of transportation links, are the basis for lean

improvement ideas. In the third step, the plans for improving the value stream are implemented

and a future state is achieved. The objective is to achieve a value stream that is as close as

possible to ideal state. The same metrics that were used to characterize the cUlTent state are re­

evaluated to see whether the value stream has in fact become leaner and whether non-value

added work has been reduced. In general, the value stream methodology also allows for

continuous improvement. Rother and Shook (1999) call this "the present becomes future" cycle

(p. 101). In the case of this study, a single iteration of the future state will be attempted due to

time constraints.

Page 19: Lean Principles Applied to Extended Value Stream Mapping

Chapter II: Literature Review

North America's Awakening to Lean Manufacturing

19

Although lean production has been practiced by Toyota since the 1950s, the widespread

study of lean in North America started in the early 1990s with the publication of The Machine

ThaI Changed the World (Womack et aI., 1990). That book surveyed the global automotive

industry and compared global efficiencies and trends. It documented the fact that some Japanese

manufacturers were applying fundamentally different concepts in their approach to vehicle

development and manufacturing. Ultimately, The Machine ThaI Changed the World came to

represent something of an awakening for the North American auto industry. Womack and his

research team at MIT in the early 1990's employed the term "lean" to describe this business

model pioneered by Toyota. Since then, interest in lean manufacturing has resulted in a steady

stream of books, articles, and seminars on the topic, all explaining the Toyota Production System

(Blanchard, 2007). It is clear that lean has gained acceptance in the North American

manufacturing community, despite the fact that widespread implementation of lean is still a work

in progress.

Essentially, lean manufacturing seeks to produce a product that is exactly what the

customer wants, when the customer wants it, while minimizing all non-value added activities in

production (Womack & Jones, 2005). In the literature, value is simply defined as what the

customer is willing to pay for. Non-value added activities are generally understood to be either

waste, or incidental activities that are necessary but add no value to the product. The best

example of a non-value added activity is quality assurance. Quality inspections do not add value

to a product; they merely detect defects before they reach the consumer.

Page 20: Lean Principles Applied to Extended Value Stream Mapping

20

Principles of Lean

The Lean Institute lists five principles of lean philosophy (Lean Enterprise Institute,

2008). These are:

1. Value should be specified from the point of view of the customer, and it should

relate to a specific product family

2. The value stream must be identified. This means identifying all the actions and

steps that need to happen to bring a product to the customer

3. Make the value-creating steps flow. This requires optimizing the value stream for

the product family. Batch production and depal1mentalization of skills are

impediments to flow

4. Produce according to customer pull. Once the production system has been setup

according to the above principles, production can be scheduled in accordance to

actual customer demand

5. Pursue perfection. This principle acknowledges that there are endless

opportunities for improvements. A truly lean enterprise will engage in continuous

improvements of the value stream

Ford's Contributions to Lean Manufacturing

Lean manufacturing is modeled mainly after the Toyota Production System. However,

even Toyota bOlTowed some concepts from Henry Ford (Womack et aI., 1990). Although Ford

is known as the inventor of mass production, he also originated the concept of continuous flow

(he called itjlOYI' production) which is an important building block for lean production. His flow

production concept was best exemplified by his car assembly line at Highland Park. In this line,

vehicles traveled along a moving conveyor setting a constant pace for assembly operations. In

Page 21: Lean Principles Applied to Extended Value Stream Mapping

21

order to feed the main line he had to organize feeder processes in a way that approximated

cellular manufacturing, where components were assembled in areas of continuous flow. Toyota

would later take note of these practices and integrate them into their own production philosophy.

Some of Ford's practices have even been described as approximating lean production

within an emerging mass production system (Womack et ai., 1990; Dennis, 2007). Ford's

accomplishments were revolutionary for the times. Ford's mass production system increased

productivity by fine-tuning the division of labor, decreasing capital expenses through large size

batching, and infrequent changeover times. Standardized work practices were another major

component of the success of the Ford system. Standardized work at Ford subscribed to the "one

best way" philosophy pioneered by W. Taylor. Taylor took the responsibility for work

procedures out of the hands of the operators and mandated that the industrial engineers would

henceforth design the work. Here again Ford helped to lay the groundwork for a lean approach.

Toyota would later adopt standardized work, but not as a static approach. Instead, at Toyota,

standardized work involves continuously improving work procedures mainly with the help of the

people on the assembly line (Liker, 2004).

These were the tenets of Ford's mass production system that at the beginning of the

twentieth century were on their way to displacing the traditional craft approach to vehicle

production (Dennis, 2007). In so doing, Ford was making industrial history by making cars

relatively affordable while providing higher paying jobs to low skilled labor. Ford's mass

production system was so successful that it essentially became the benchmark for vehicle

production in the first half of the twentieth century in North America and Europe. Automotive

industrialists visited from all over the world to see Ford's mass production system, including

Toyota (Womack et ai., 1990).

Page 22: Lean Principles Applied to Extended Value Stream Mapping

22

The Beginnings of Lean Production

Mass production remained unchallenged until about the 1960s when a new production

system, pioneered by Toyota, started to increase its market share at the expense of the American

big three (Womack et aI., 1990). The post-war 1950s was a time of economic hardship in Japan

characterized by limited access to capital funds and impOliation of goods. The Toyota motor

company, who had been put to work assembling military trucks by the Japanese wartime

government, was now returning to its core business of manufacturing civilian vehicles. In a bid

to study America's successful automotive industry, Eji Toyoda visited Ford's Rouge Plant in

Detroit in 1950. What he saw there was impressive. Neveliheless, Eji Toyota was clever

enough to understand that mass production was wholly unsuited for Japan's post war reality.

Not only was Japan's car market smaller than America's, it was also more diverse in its needs.

Furthermore, bOlTowing capital in the quantities necessary to finance a mass production

operation would not have been possible as post-war Japan was cash strapped. Right from the

stmi, Toyota's operating principles were forged in an environment marked by extreme scarcity.

Toyota recognized that in order to produce cars for its domestic market it would have to

do more with less. It needed to take a radically different approach from what Eji Toyoda

observed at Ford (Liker, 2004). Furthelmore, Japan's economic situation along with Toyota's

own cash flow problems were of such a magnitude that Toyota saw itself forced to ask for one

qumier of its workers to retire. This move resulted in a strike that would eventually result in a

deal where Toyota signed-up to secure employment for its remaining staff. Toyota would now

have to devise a survival strategy that hinged on getting the most from its remaining resources:

namely modest capital assets and a permanent work force.

Page 23: Lean Principles Applied to Extended Value Stream Mapping

23

The Objective of a Lean Production System

After the strike of 1950, Toyota would be guided by one overarching objective: to

eliminate all waste while producing exactly what the customer. wants (Liker, 2004;

Dolcemascolo, 2006). All other effo11s in the Toyota Production System would support this

objective. Taiichi Olmo, former Chief Engineer at Toyota and architect of the Toyota Production

System, identified seven wastes of manufacturing that the Toyota Production System would seek

to el iminate. The elimination of these wastes is the basis of the guidel ines for implementing lean

improvements in value streams. These wastes are reported by Dolcemascolo (2006, p. 4):

1. Overproduction

2. Transpo11ation

3. Unnecessary inventory

4. Inappropriate processing

5. Waiting

6. Excess Motion

7. Defects

Page 24: Lean Principles Applied to Extended Value Stream Mapping

24

Jidoka: A First Pillar of the Toyota Production System

The fact is that Ohno was not staliing from scratch III his quest to match Ford's

productivity. In addition to being inspired by Ford's continuous flow invention, Ohno was

drawing on the ideas of his Toyota predecessors. Most notably, Ohno would eventually integrate

Jidoka as one of the pillars of the Toyota Production system. The concept of Jidoka, or

automation with intelligence, was in fact pioneered by Sakichi Toyoda, Eji's uncle in the late

1800s when Toyoda was in the business of fabricating looms for the textile industry (Mass &

Robertson, 1996). This concept was a great technological leap as well as a philosophical tour­

de-force. Essentially, when a thread broke in the weaving process, the loom was not allowed to

go on producing defective material (waste). This became the original instance of Jidoka.

Just-in-Time: A Second Pillar of the Toyota Production System

The other pillar of the Toyota Production System, Just-in-Time (lIT), came from

Japanese observations of American supermarkets during the early visits of Taiichi Ohno in the

year 1956 (Liker, 2004). The Japanese observed that supermarket shelves were easily

replenished in the US. When the product was below a certain level, this would trigger re­

stocking of the item. There was only enough stock on hand to supply to the immediate

customers. The significance of JIT was that it was integrated into the Toyota Production System

in the form of Kanban tools. These Kanban tools are the signaling apparatus that allows a pull

system to exist (Jones & Womack, 2002). This is completely different from the mass production

approach of having multiple orders sent simultaneously to multiple manufacturing locations in

the production process. In a JIT operation, an upstream process only produces when a

downstream is asking for a unit of production. This simpler and more efficient solution to satisfy

demand is at the heart of pull production.

Page 25: Lean Principles Applied to Extended Value Stream Mapping

25

The Role of Standardization in the Toyota Production System

While JIT and Jidoka are known as the pillars of the Toyota Production System, the

foundation of the Toyota Production System consists of standardization and stability (Dennis,

2007). Like in the mass production system, standardization ensures that work is carried out in a

predictable and well thought-out manner. Unlike in the mass production system, in the Toyota

Production System, the purpose of standards is not to impose a static way of doing things. The

opposite is in fact true (Nicholas & Avi, 2006). In the Toyota Production System, standards

exist so they can be continuously improved. Through Kaizen sessions, a cross-functional team

gets together to target improvements based according to strategic company direction (lmai,

1997). The purpose of a Kaizen session is primarily to eliminate waste by making incremental

improvement to processes. The intimate knowledge held by workers is critical to the success of

Kaizen sessions.

The Role Stabilization in the Toyota Production System

In the lean system, even before there can be standardization there must be stability

(Dennis, 2007). The Toyota Production System emphasizes the importance of a stable

environment. Without a stable environment, any lean improvements would be swept away in the

chaos of clutter, unpredictable breakdowns, and material fluctuations. Several key disciplines

were integrated into the lean production system by Ohno to reinforce stability. 5-S, for example,

is a visual management tool that is meant to eliminate clutter and helps to see what is out of

place (Gapp, Fisher, & Kobayashi, 1998). In 5-S, there is a place for everything, and everything

has its place. The power of 5-S comes from the fact that it is a visual tool: it can provide an

assessment at a glance. A person can see immediately if their environment is out of place

because a 5-S'ed environment has visual markers for the storage location of things. Most

Page 26: Lean Principles Applied to Extended Value Stream Mapping

26

importantly, 5-S makes underlying problems apparent so they can be addressed . In this respect,

5-S is also a star1ing point for discovering and solving problems.

A discipline meant to prevent unforeseen downtime is Total Productive Maintenance, or

TPM (Black & Hunter, 2003). In a Total Productive Maintenance environment, workers

themselves take responsibility for performing basic maintenance on the equipment they operate

on a daily basis. This seemingly small contribution from the operators makes a big difference on

the reliability of the equipment and most importantly to the overall stability of the operations.

Breakdowns do not occur as often and operators can concentrate on adding value to the product

instead of dealing with downtime due to unreliable equipment.

Lastly, the practice of heijunka as a stabilizing discipline helps to level the demand on

production (Liker, 2004; Rother & Shook, 1999). Firstly, the production mix is leveled to avoid

making one large batch of one pali followed by another large batch of another pal1. Batching

ultimately leads to hidden quality issues. In a lean operation, it is preferable to mix the type of

pal1s produced by running small batches more frequently . Heijunka also means stabilizing the

volume thus avoiding spikes in production. Instead of making the number of parts exactly as

requested in the daily release schedule, the manufacturer should use historical demand data in

order to make a daily average number of pa11s while keeping a standard inventory of pm1s.

Page 27: Lean Principles Applied to Extended Value Stream Mapping

27

At the Heart of the Toyota Production System

At the heaIt of the Toyota Production System, there is one important idea: that people

make all the difference. Through their creativity and their engagement, workers provide the

driving force that sustains lean manufacturing (Dennis, 2007). Unlike in the mass production

system, lean manufacturing personnel are involved in making decisions about the processes that

they operate. In fact, the Toyota philosophy is to push down the responsibility for improving

processes. Not only are plant workers encouraged to paIticipate in decision-making, they are

expected to do so. Through process kaizens, associates engage in waste reduction, problem

solving, and cost savings. Employee suggestion programs, for example, are a common way for

employees to be involved in the improvement of the company. Thus in a lean production

environment, all employees, even those doing repetitive work, are expected to think critically

about their work and contribute to the continuous improvement of work standards. For this

reason, some have called the Toyota Production System the Thinking Production System (Liker,

2004).

Value Stream Mapping

Value stream mapping was originated by Mike Rother and John Shook in collaboration

with James Womack (Womack, 2006). Rother and Shook's value stream map idea was based on

a similar a technique used by Toyota called in/ormation and materials jlovv diagrams. In

configuring value stream maps, Rother and Shook intended to capture process information,

materials flow, and information flow for a given product family. Although value stream maps

were developed within the context of the automotive industry, they have become popular in other

fields such as health care and the service sector.

Page 28: Lean Principles Applied to Extended Value Stream Mapping

28

The value stream mapping process begins with a map of the current state. The current

state should faithfully depict the operations as they are happening at the present time (Rother &

Shook, 1999). Both value and non-value added steps are shown in, a value stream map.

Information flows also appear and are considered just as important as material flows. Icons are

used to depict processes, material flows, and information flows. In addition, part accumulations

in the fOlm of WIP, inventories, and safety stocks also appear in the value stream. Special

alTOWS are used to depict "pull" or "push" production. In addition to icons, value stream maps

also record lean metrics inside data boxes located beneath process icons. Data boxes typically

include cycle times, changeover times, and travel distances. The types of metrics used to

populate the data boxes are chosen according to the specifics of the value stream being mapped

and the industry under consideration. In general, a timeline is also plotted along the bottom of

the value stream to track metrics used for cumulative quantities such as total lead time, total

travel distance, and total value added time. These cumulative quantities help to characterize the

value stream and serve as a baseline for later comparison.

The power of value stream mapping comes from its usefulness in integrating and

representing all the important elements of the lean enterprise (Tapping, Luyster, & Shuker,

2002). Once the current state value stream map has been drawn, improvement oppo11unities can

now be identified in a visual manner in conjunction with an assessment of the metrics. With

respect to improving the current state value stream, Rother and Shook (1999) take the view that

the main objective in a lean enterprise is simply for any process to only make what the next

downstream process requires, within the sho11est lead-time, at the highest quality, and at the

lowest cost. To attain this lean objective, they identified the following lean principles for

achieving a lean future state value stream map (Rother & Shook, 1999, p. 44)

Page 29: Lean Principles Applied to Extended Value Stream Mapping

1. Produce to the takt time

2. Develop continuous flow wherever possible

3. Use supermarkets where continuous flow does not extend upstream

4. Send the customer schedule to only one production process: the pacemaker

5. Level the production mix

6. Create pull by releasing consistent increments of work at the pacemaker process

7. Develop the ability to make every part every day. (p.44)

Extended Value Stream Mapping

29

The extended value stream map goes a step further. In the extended value stream map,

the flow of value is mapped from the supplying facilities through to the customer's facility

(Womack & Jones, 2002). Transportation between supplying facilities and transpOliation to the

customer's facility is considered. A closed loop supply network is formed with product moving

down stream and demand moving upstream. The concept of extended value stream mapping

does not require the practitioner to map the supply chain back to the extraction of raw materials

from the ground. For practical purposes, the extended value stream map can be limited to the

number of suppliers that are useful to the value stream manager (Drickhamer, 2003).

Just as in facility value stream mapping, extended value stream mapping stalis with a

representation of the CUlTent state. Since the flow of materials and information between facilities

is the main consideration in extended value stream mapping, the focus of lean improvements

shifts to addressing issues at interfaces between facilities. These include minimizing

transpOliation between facilities and minimizing inventories of finished goods (Jones &

Womack, 2002). In order to achieve the goal of a lean extended value stream, Jones and

Womack (2002, p.43) proposed the following guidelines:

Page 30: Lean Principles Applied to Extended Value Stream Mapping

30

1. Produce at a rate that is consistent with the customer' s takt time

2. Keep minimal inventory

3. Minimize the number of transport links

4. Minimize the amount of information processing while ensuring clarity of available

information

5. Minimize the lead time to deliver a product to the customer

6. Changes made to improve the extended value stream map should ideally have no

associated cost or at worst have very little associated cost

Extended Value Stream: Future States

When making improvements to an extended value stream, the very first step is to address

the implementation of lean production in the individual facilities (Jones & Womack, 2002).

Building a lean supply chain staris from the bottom up. Any company in the supply chain that is

not prepared to implement lean within its own facility will be of little help in sustaining an

extended value stream. The term future state I, therefore, describes the state of the supply chain

when all suppliers have convelied to lean production within their own facilities.

Future state II, on the other hand, deals with transportation and communications links

between facilities. In their book Seeing the Whole, Jones and Womack (2002) recommend direct

transportation links between upstream suppliers and downstream customers, instead of

intermediate warehousing or cross-dock facilities. Moreover, just as with value stream mapping

within a single facility, it is recommended that suppliers and customers be linked by a kanban

type of information flow meant to establish a pull system between upstream suppliers and

downstream customers. These are analogous to kanban loops within a facility. For instance,

Page 31: Lean Principles Applied to Extended Value Stream Mapping

31

large once-a-week batch loads should be replaced by milk runs whose transportation loops

connect several facilities.

Before achieving a Future state II, suppliers and customers must work cooperatively

toward a lean extended value stream. It is critically important that suppliers and customers strive

toward what Dolcemascolo (2006, p. 39) refers to as an "open book policy". Suppliers and

customers need to disclose oppOliunities for improvements. Ultimately, this means cost

information may also have to be shared in order to select lean improvement projects that make

sense for all. For example, if a supplier is buying raw material at a high price, but the customer

can negotiate a lower price, then there is obviously an oppOliunity for improvement. Without

disclosure of costs, this simple extended value stream improvement could not happen. This open

book policy then leads to the possibility of re-drawing the extended value stream map on a

collaborative footing. Only then can extended value stream maps be truly optimized.

Beyond future state II, there is one last type of future state called the ideal state (Jones &

Womack, 2002). In the ideal state, the overriding principle is to compress the value stream as

much as possible while bringing the value stream closer to the end customer. This literally

means bringing production operations geographically closer together as well as closer to the

customer. This is similar to including all operations within a single workcell. Compressing the

extended value stream and moving it closer to the customer, however, has to be balanced against

the possibility that the customer may be located in a high cost region. In this case, moving

operations may be undesirable due to labor costs in the high cost region. Unless new labor

saving technologies can be used , moving to all operations to a high cost region cannot be a

foregone conclusion. High local labor costs may well justify keeping supplier operations in a

Page 32: Lean Principles Applied to Extended Value Stream Mapping

32

lower cost region. Striking this balance represents a major improvement opportunity for the

extended value stream.

Cooperation in Extended Value Streams

Sharing the costs of investments is discussed in the literature as an element of extended

value stream improvement that is sometimes necessary. The concept is simple. A supplier sells

a product to a customer for a profit, despite the existence of waste in supplier's pOliion of the

extended value stream. In theory, value stream improvements should not cost anything to

implement (Tapping et aI., 2002). In practice, however, extended value stream improvements

can often involve significant changes to manufacturing locations and equipment and therefore

investments may be required. It is unlikely that a supplier will pay for these changes despite a

positive return on investment. If the value stream improvements disproportionately benefit the

customer rather than the supplier, it becomes even more unlikely that the supplier will make such

investments. In this scenario, the customer will need to assist the supplier in making the

necessary changes. Jones & Womack (2002) characterize this collaboration as the need to have

the "winners compensate the losers" (p.73). This suggests that extended value stream thinking

should occur early in the development of plant operations to avoid in-eversible non-lean extended

value streams. It also suggests that changing economic conditions, like currency fluctuations,

fuel price increases, and labor costs, should prompt the periodic review of extended value stream

maps.

Extended value stream mapping, therefore, provides a visual summary of how value

travels between supplying facilities into the customer's facility. In order to implement lean

production in the extended value stream it is necessary to have lean implemented in the

individual locations first. Using the principles developed in the Toyota Production System,

Page 33: Lean Principles Applied to Extended Value Stream Mapping

33

which seeks to eliminate waste, a lean future state for the extended value stream map can be

achieved. The last step in improving the extended value stream is to consider the possibility of

compressing the extended value stream and bringing it closer to the customer. Cooperation

between customer and suppliers is critical to realizing and Ideal State.

Page 34: Lean Principles Applied to Extended Value Stream Mapping

34

Chapter III: Methodology

The purpose of this study was to implement lean improvements in the manufacturing

operations of aluminum frames supplied by Framex Mexico to Universal's Michigan assembly

plant. Universal required that Framex implement a costs savings within six months of its

original request. Cost savings resulting from product changes were out of the question since

Universal wanted to carryover the frame design into the new model year - also because of cost

savings. This meant that process, logistics, and manufacturing locations all needed to be taken

into consideration when Framex was investigating possible lean improvements. The

methodology prescribed by Jones and Womack (2002) was adopted because it addressed the

specific areas where Framex had to find cost savings.

This chapter will identify the subject of the study in terms of an extended value stream. It

will also identify value stream maps as the instrument used to collect data and analyze the

extended value stream. Next, this chapter will demonstrate how lean principles discussed in the

literature were used to generate improvement ideas for the extended value stream. Finally, an

ideal state extended value stream map will be created by working through future states I and II,

according to the methodology al1iculated by Jones & Womack (2002) in Seeing the Whole.

Page 35: Lean Principles Applied to Extended Value Stream Mapping

35

Subject of the Study

The subject of the study was the extended value stream consisting of the Framex

manufacturing facility located in Mexico and the transportation of aluminum frames up to

Universal's pick-up truck assembly plant in Michigan. At the outset of the study, Framex was

purchasing aluminum coils that were stamped into components PaIts (brackets, gussets, cross

members, etc.) and then were welded into frame sub-assemblies. The three sub-assemblies were

then bolted together and finally e-coated for corrosion protection. The frames assemblies were

then put into containers and shipped via truck over to Laredo, Texas where a cross-docking

operation took place. The containers were removed from the truck and transferred onto a train

that would transpolt the frames the rest of the way to Michigan.

Instrumentation

The instrument used to study the extended value stream under investigation was the value

stream map. Value stream maps are used to provide a visual representation of the value stream.

Processes, material flows, and information flows appear on the value stream map. Extended

value stream maps also include transpOlt link infOlmation as well as information about

geographic locations. In addition, value stream maps also contain information about the takt

time that sets the production pace for the value stream under investigation. In this study, the takt

time is constant. Improvements to the extended value stream map had to conform to a constant

takt time of 63.4 seconds, per appendix A.

The value stream map is also used to collect lean metrics data, which quantifies the

elements in a value stream. For example, value added and non-value added times were recorded

for each process. Because it is a visual instrument, a value stream map is well suited for quick

visual reference and efficient analysis. Furthermore, value stream maps also have a temporal

Page 36: Lean Principles Applied to Extended Value Stream Mapping

36

element. In general, a value stream will be represented either in a current state map or in a future

state map. Extended value stream mapping methodology makes use of several future states:

future state I, future state II, and finally the ideal state value stream map.

Data Collection

The following lean metrics were selected in order to establish a method for evaluating

and comparing the lean states of the extended value streams:

1. Lead times (days)

2. Value added time (seconds)

3. Process cycle efficiency (percentage)

4. Raw materials inventory (days)

5. Work in progress inventory (days)

6. Finished goods inventory (days)

7. Transportation distance (miles)

8. Transp0l1ation time (days)

Standard data taken from work instructions was used to populate the value stream data

boxes. Cross-functional meetings that included production supervisors, logistics personnel ,

project managers, and sales personnel were held. The purpose of the meetings was to plan and

implement the costs savings. Each member was responsible for validating the data obtained

from documented sources. Once the data was compiled, the extended value stream maps were

populated by entering the data into the data boxes in the value stream maps.

Page 37: Lean Principles Applied to Extended Value Stream Mapping

37

Data Analysis

The lean principles discussed in the literature provided guidance in identifying lean

improvements to both facility and extended value streams. Working meetings were held to bring

together the team with the aim of bringing the extended value stream in line with lean principles

as stated in Seeing the Whole (Jones & Womack, 2002). The following lean principles for

extended value streams were used to drive improvements at every step of the way toward the

ideal state:

1. Produce at a rate that is consistent with the customer's takt time

2. Keep minimal inventory

3. Minimize the number of transpOli links

4. Minimize the amount of information processing while assuring the clarity of available

information

5. Minimize the lead-time to deliver a product to the customer

6. Changes made to improve the extended value stream map should ideally have no

associated cost or at worst have very little associated cost

The future state principles used to step through the progression of future state I, future state II,

and finally the ideal state were:

1. Future state 1: implement lean production within the individual facilities

2. Future state II: install pull between facilities & install loops between facilities

3. Ideal state: geographically compress the value stream

Current state analysis (future state I). The analysis of the CUlTent state extended value

stream map was conducted using lean principles. The analysis of the current state began

immediately with a focus on improving transportation links i.e. working toward a future state II.

Page 38: Lean Principles Applied to Extended Value Stream Mapping

38

This is because the Framex facility had essentially implemented lean production. Therefore, in

this study the CUlTent state and future state I are the same.

The first step in the analysis of the current state was to create an extended value stream

map. This allowed the team to locate the areas where the value stream was not lining-up with

lean principles. The following key elements were identified as essential to building a current

state extended value map:

• The transp011ation link between the aluminum supplier and Framex

• The Framex Mexico facility

• The transp011ation link between Framex Mexico and the inter-modal (truck-to-train)

cross-dock at Laredo, TX

• The transp011ation link between the cross-dock at Laredo and the Universal assembly

plant in Michigan

The current state extended value stream was consequently mapped with these elements as

shown on Figure 1. Lean metrics data for each of the elements was obtained in order to

complete the value stream map. The cross-functional team members obtained the data by

consulting and validating process documentation. It was then handed over to the project

manager to populate the value stream map with the data. Obtaining the lean metrics data for the

Framex facility , however, required an extra step. A separate facility value stream map for

Framex Mexico (Figure 2) had to be created. Once again the data for the facility value stream

map was provided by the cross functional team. Once the facility value stream map was created,

the aggregate lean metrics were used in data box for Framex Mexico in the extended value

stream map (Figure 1). The facility and the extended value stream maps were analyzed using

lean principles.

Page 39: Lean Principles Applied to Extended Value Stream Mapping

39

The analysis yielded several key observations. The facility value stream map for Framex

(Figure 2) showed that the value added time of 188 seconds relative to the lead-time of23.0123

days resulted in an extremely low process cycle efficiency of 0.0194%. Looking fUliher

upstream within the Framex value stream, the team felt that the safety stocks of raw materials

(10 days) and finished goods (10 days) were too high and that an oPPOliunity existed to improve

process cycle efficiency by reducing inventory. However, getting rid of the safety stock would

require management buy-in. The safety stocks were put in place to deal with unforeseen supply

problems and rush orders that had occurred in the past year.

The extended value stream map in Figure 1 made it clear that the transpOliation link

between Framex and Universal had become a problem. In response to urgent calls from

Universal, Framex had to fly material to Michigan six times in the last year. This transpOliation

link included trucking, a cross-dock, and then rail transpOli. The team felt that the transpOliation

lin1e between Framex and Universal was too unreliable and time consuming. The lead-time for

that transpoliation link was 14 days, which was perceived by all to be essentially inventory on

the road. The cross-dock in particular had been a source of delays at customs. When the

extended value stream was evaluated, the value added time of 118 seconds vs. the total lead-time

for the extended value stream of 37 days resulted in a process cycle efficiency of 0.0121 %,

worse than for the facility value stream.

Page 40: Lean Principles Applied to Extended Value Stream Mapping

..." ~. 00 ..... 'TJ ;;J 3 (1)

x 2 ::s < (1)

;;; '" (")

c ~ ;:;. on Ei ro (1)

x ro ::s 0-(1)

0-

< '" c (1)

on

@ '" 3 3 '" "0

VA/T'" 118.0seconds RM,., 1a.Od; IMP = 3.0 day> FG· 10.0 day> peE = 0.0194%

- - - - -

CURRENT STATE.igx

Frarrex

MEXICAN

HQ

Framex - Universal Current State

Extended Value Stream Map

!l..£.l.~ IN niTl ll. [ .!>TATE 1 FN:Jl.mr S.\R£

~'ll'KiSED TO BE Cc»."\TRTED TO

LEA'\' Il::('I)!;,,-:nOX A'\' .\S.\."\1i l'TIO:-; [);

TI-lIS STlUY IS T1L\T TI ll' S [S ,\LItE.\DY

IN I'I...Kl : . TI IERH1)RE H.!Tl"RE ST,\TE 1

[STIlE CURREl'.T ST:\TE

~- - --~ ~ Distance Traveled: 556 rri. TransportTirre:2d¥

INTER MODAl CHAN'GE

=<§ NVA= 2d<l)S

I- - § -Distance Traveled: 1669 rri. Transport Time: 10 cia)-s

Plant MI. USA

I Distance Traveled: ~ ,

- - - - - - - - - - - - -~R- - - - - - -- - -

23.0d~ 2.0da)S 1O.0d¥ llead Tirre = 37.0da)5

(118.0seconds) I LOda)S I flAIT= 118.0secoods

travel 0-----0 o-ofCE = 0.0121%

0.114 niles 556 niles 1669 rriles iTrarrsporl Tirre:: 12 da)oS

IFG = 14.0 day>

/RM = 00da)S

M-<P = 23.0 d<l)S

jtra-.eled:: 2225.1 niles

.j::,. o

Page 41: Lean Principles Applied to Extended Value Stream Mapping

.." oS' ::: 0:;

~ '"Ii ;;5 :3 (1)

>< ;;;> £:. q () c =l (1)

;::. V>

5)" (D <: ::»

~ V>

~ C>

:3 :3 C>

"0

ALUMINUM COW'ANY

, I

I I

.1

10 days

10. 000

do,

[-~ ,

01

STAMPING

Mn.NUAL

TRANSFER

T etal CIT = 2 seconds Value Add. 2 seconds NV A - 0 s.econds

Olst3ncc Travel ed: Oft

2.0000 s('conds

, '-

F/?A reM

CURRENT 5T AT E.igx

/

Framex Facility Current State

Value Stream Map

Customer DOm.1I'Kt

100000 piCCe-s pCI' Yesr (Tal<2 Time 63.4 seconds)

------0.-----,

3 days

Distance Traveled: 200ft.~~c:~~nds

3.0 000

d.,

Distance Travoled: 80 ft.

250.0000 seconds

80.0000 r seconds I

FINAL

ASSEMBLY

BOLTING

,o~TATION

Total CIT ::: 50 s econds Value Add: 24 seconds NVA::: 26 seconds Distance Traveled: 20 ft

50.0000

PAINTING

CORROSION

<f,ROTECTICN

T olal CIT ::: 24 seconds Value Add: 12 seconds

~~~~c~2 ;:~~ed: 300 ft

10.0000 seconds 24.0000 seconds 'Lead Time = 23.0123 days

l 24.0000 I I 12.0000 seconds I AIT = 118.0000soconds

seconds RM= 10.0 day-:;

rIP:::3.0dSYS

FG= 10.0 days

~CE::::I 0.0194%

~

Page 42: Lean Principles Applied to Extended Value Stream Mapping

42

Future state II analysis. To redraw the extended value stream map (Figure 3), the

general concept that the team pursued was moving away from using rail transport and instead

shipping finished goods by truck directly from Mexico to Michigan. Cutting out the cross dock

was in line with the principle of reducing the number of transport links. Two transpOli links

were in fact eliminated: the cross-dock and the rail transport. The elimination of the cross-dock

would also allow a pull system to be established between facilities: another aim of lean extended

value streams. This is shown by a transpOli loop in the extended value stream map in Figure 3.

This transport loop, with a transpOli time of seven days, was expected to eliminate the need for

expedited shipments.

Shipping via trucks, however, posed a brand new problem. Trucks would be about two

times more expensive than shipping by rail on a per frame basis. The solution that the team

came up with was to increase containerization density. In other words, if the same trailer could

take twice as many palis then there would be no cost penalty for using truck transpOli.

UnfOliunately, the finished goods containers were owned by Universal and they did not agree to

make changes to the finished goods containers. The finished goods containers had to conform to

standard sizing for material handling purposes. Therefore, future state II was conceived using

existing finished goods racks while shipping twice as many trucks per day. It was recognized

that this was a sub-optimal solution to the density issue and a permanent solution would have to

be found in the ideal state, prior to implementation. The future state II with new trucking

arrangement is shown on the extended value stream map in Figure 3. Future state II was not

implemented. However, it was a necessary intermediate step toward the ideal state.

Page 43: Lean Principles Applied to Extended Value Stream Mapping

43

Neveliheless, moving away from rail transpOJi was step in the right direction because of

the smaller amount of inventory on the road at any given time. Trucks would now only take

seven days to make it to Michigan vs. the 14 days using intermodal transpOJi. This improvement

in lead-time was expected to increase the process cycle efficiency of the extended value stream.

The inventory of finished goods at Framex Mexico facility (Figure 4) could now be potentially

decreased by a corresponding seven days at the facility i.e. from 10 days to three days.

However, management at Framex Mexico plant was not in favor of going to three days of

inventory and settled on six days of inventory as a precautionary measure. This decrease in

finished goods inventory down to six days at the Framex facility is shown on Figure 4.

Page 44: Lean Principles Applied to Extended Value Stream Mapping

.." ~.

"" '-v

'TJ ;; 3 (1)

~ C :J

< (1) ""1 V> :»

2' 2 eli V> :;; co (1)

x co :J a. (1)

a. < '" c (1)

~ ""1 (1)

'" 3 3 :» -0

10 days

.ay

Framex - Universal Future State II

Extended Value Stream Map

-----------------~-----------,

TllInsport Time:::: 0.0 days

RM= 0.0 da" W1P =3 0 days FG:::: 6 .0 days

'2)(JOAY w Distance Traveled: 2225 ml. Transport Time: 7 days

---------lIiiIij

Unlve.sal

Pickup Assembly Plant

M .USA

travel 0-0--0 v \{ V-\

Lead T1 me:::: 26.0 days

VAfT = 118 seconds

peE:::: 0.0172%

I";:>lant Time = 19 days

Transport Time:::: 7.0 days

RM= 10.0 days

WIP =9.0 days

FG= 7.0 days

traveled:::: 2225.0 miles

~ ~

Page 45: Lean Principles Applied to Extended Value Stream Mapping

..." ALUMNUM COWANY

~. M::XICO

<Ii :k 'Tl ...., ~

3 (1)

X 'Tl :>:> ~ ~.

2' C ...., (1)

en .... ~ ro <: ~

C (1)

~ ...., (1) ~

3 3 ~ '0

~I f I

I

i

10 days

,0'

STArvPlNG

WANUAL TRANSFER

IT otal CfT = 2 second Ivalue Add: 2 seconds NVA=O~

~.

~

Framex Facility Future State II

Value Stream Map

------D-----r FINAL

ASSEtvSLY

BOLTING

o:!TATIC>l

I~~:~~ C:::;d~ ;~ ::~;~s NVA = 26 secondS

PAINTING

CORROSION ~ROTECTION

Total CfT = 24 second tVa~ue Add: 12 seconds tFNA=T~ iQ pcs

Customer Demand: 100000 pieces per Year

(Takt Time 63.4 seconds)

ead Time = 9.0123 days

A I T = 118_0 seconds

CE 0.049595%

ransporl Time = 0_0 days

M= 0.0 days

IP = 3_0 days

G=6.0days

~ VI

Page 46: Lean Principles Applied to Extended Value Stream Mapping

46

Ideal state analysis. In the ideal state map as shown on Figure 5, the cross-functional

team concentrated on the principle of moving the value stream closer to the customer while

being mindful of cost implications. The obvious idea initially proposed by the team was to

manufacture the aluminum frames in Canada and then ship them to Michigan. After all, the

Canadian facility was already shipping steel frames to Universal. This idea however was

considered not feasible for several reasons. First, labor costs in Canada would be several times

higher than in Mexico and given that welding operations were labor intensive, this was

considered as not feasible by the team. Furthermore, the welding equipment at Framex Mexico

was a shared asset with other production programs and it could not leave Mexico. To complicate

matters fUliher, the welding equipment in Canada had the same problem: it was strictly for steel

applications and could not be converted, as it too was shared with other production programs.

Moving the entire Mexican operations to Canada, or to the US for that matter, was an even more

remote proposition.

The break-through solution that the cross-functional team proposed was to take

advantage of some, but not all, of the existing capabilities in Canada. In paliicular, the

operations that Framex Canada could undeliake were the final bolting assembly and the e­

coating operations. This would allow sub-assemblies to be shipped in high-density WIP bins to

Framex Canada for final assembly prior to being shipped to Universal in Michigan. Since the

design of the aluminum frame and the steel frame where only slightly different, the final bolting

assembly station in Canada could be retooled for a very modest cost so it could process both

designs. The business case showed that the cost of retooling the bolting station could easily be

recovered from the cost savings. The e-coating operations could also be done at Framex Canada

with no tooling or equipment changes. All that was needed was a small readjustment of the

Page 47: Lean Principles Applied to Extended Value Stream Mapping

47

chemistry in the e-coating process to accommodate coating both steel and aluminum frames.

Both bolting and e-coating operations were highly automated in Canada so labor costs were not

an issue. Therefore, in the ideal state, optimization of the extended value stream meant that only

final assembly and e-coating would be done at Framex Canada (Figure 7), while stamping and

welding would remain at Framex Mexico (Figure 6). This is how the project team was able to

comply with the lean principle for extended value streams of geographically "compressing" the

value stream.

Page 48: Lean Principles Applied to Extended Value Stream Mapping

48

Moving the final two operations to Framex Canada also addressed the issue of

containerization density. Now Framex Mexico was a supplier to Framex Canada lined by a pull

loop (see Figure 5). Framex Mexico would be shipping welded sub-assemblies instead of

finished goods. These smaller sub-assemblies could be nested to increase containerization

densities by more than 200%. The cost of transportation via trucks would be more than

compensated by the increase in containerization densities . However, in order to ship nested sub­

assemblies from Mexico to Canada, new WIP containers to be owned by Framex were needed.

The business case showed that, although expensive, new WIP containers would pay for

themselves. However, the team concluded that the burden of the investment should be shared

with Universal. The costs of the new WIP container were discussed between Universal

purchasing and Framex sales. It was determined that a net cost savings for the overall extended

value stream was achievable and Universal agreed to compensate Framex for the costs of the

new WIP containers. This agreement made it possible to move forward with the implementation

of the ideal state. This solution had a positive effect on the value stream map for Framex Mexico

since no finished goods stock would be needed there in the ideal state as shown in Figure 6.

Instead, the team decided to keep a supermarket of aluminum sub-assemblies at Framex Canada

in case of fluctuations in the supply of components from Framex Mexico.

Page 49: Lean Principles Applied to Extended Value Stream Mapping

Framex - Universal Ideal State

Extended Value Stream Map emMe" can ~~------~D/~~~ ________ ~I8.~ /JJlJllnum ~

Company

Me;.ico

I I

/

,,' ,.,.

CANADA

(Q\lTARIOJ

VQ5d~ NEW WIP BINSWILL DOUBLE'W:1REGIONAL V OPTIMIZED SUPPLIER DENSITVBETWEEN MEXICO AND ...... __

CPJIJ/!lDA -. -. - ____ _

IE. TRANSPORT COST BETW EEN MEXICO AND CANADA ARE HALVED

TRUCK LEAVE MEXIC~;DAVNO ~\

TOIai crr. 17.0123~

ValueAdd: 118 s.

ONGER 2YJD;V \AI ~ Distance Tra'wel'ed: 2324 01 . Transport Time: 7 d~ RM: Sd. WP: 3d. FG:2d.

_S.0 r--000 17 .0123~ (118.0 se<:onds)

day s

-tra\el

23241T'i1es

_ 0.5,--

looc

day

s ~

126

nil es

Lead Time' 22.5123 d~

VAiT' 116.0 . e<:onds

PCE = 0,0199'%

Tr""sport Time· 7.5 ~

RM·10.0d.

IMP - 3.0d.

FG· 2.0d.

Ir8\eled = 2450 nil es

Figure 5. Framex-Universal ideal state extended value stream map

49

Page 50: Lean Principles Applied to Extended Value Stream Mapping

'"t"J ~" ,,; ?­

~ :>:> 3 (t)

x $: (t) x r:;" o Qj> (")

.:< Q. (t) :>:>

'" tJ ~ < :>:> C (t)

~ .... (t) :>:> 3 3 :>:>

"0

~ T /

/ /

5"",

,./ '"

.-~.~

,--v' ST AMPI NG

MANUAL TRANSFER

TGlalCfT· 2~

Va.ocAdd. 2~~

W I." 06CCond$

Dil.l:tTIC.(l Tr ..... eIod: OU .

,---

~.

./

Framex Mexico Facility Ideal State

Value Stream Map

,-----0----, ,

·a,., Add. ED S«ORb. ,- -OicnCIfICO T~ 200 II .

W A :Ie 170 SCCOI'lC2t

r..t3rcoTr,wc/cd: BOn.

eu,101nC'f Otrnond:

laxx:o p~ par Yor (Tak'lTme63."~)

l X1Q.\Y

Vl o

Page 51: Lean Principles Applied to Extended Value Stream Mapping

~ ::: <1:i

:"l '"T']

@ 3 (b

x ()

"" ::s "" c.. "" ;;;> ~.

Q ~ (b ::0

t.n £l' (b < ::0

::: (b

t.n

~ "" 3 3 "" "'0

Fr2Imcx~XICO

5 days

BOLTING

Q~TATION

Total err :: so seconds

Value Add' 24 seconds t-NA - 26 seconds

Framex

CANADA

Framex Canada Facility Ideal State

Value Stream Map

PAINTING

CORROSION

O ~ROTECTION

Total err:: 24 seconds VCllue Add: 12 seconds

NVA - 12 seconds Distance Traveled: 20 It

0""

5.0

d,y

I S I 50.0 seeonds

24 .0 seeonds

Dislance Traveled: 300 ft.

24.0 seconds

12.0 seconds I 2.0 days

I

Customer Dem;,nd:

100000 plecos perVo"r (Ta1o:J Time 63.4 seconds)

Lead Time:: 7.0 days

l IVA IT:: 36.0 seconds

RM:: 5.0 days WIP :: 0.0 dB'1S

FG:: 2.0 days

peE:: 0.0195%

VI

Page 52: Lean Principles Applied to Extended Value Stream Mapping

52

Limitations of the Methodology

The value stream maps that were used did not integrate the business case analysis. This

was a significant limitation of this methodology. In this study, the project manager was in

charge of leading the cross-functional team in the development of value stream maps. On the

other hand, sales were in charge of the business case analysis. Sales used a spreadsheet to keep

track of the business case. As a result, two types of documents were used to communicate how

the cost savings were achieved. At times, this caused some confusion. Most people knew how

to interpret one or the other of the documents - not both.

Another limitation of the methodology was that value stream maps display single values

for lean metrics as opposed to statistical distributions. The accuracy of lead times for shipping,

for example, was questioned many times by management. The historical data had simply not

been collected in a disciplined way to provide the confidence in the data that was sought. As a

result, there was some risk that the ideal state would not materialize exactly as planned.

NeveltheJess, the cross-functional team was confident that the ideal state was configured

correctly and that the cost savings would be achieved successfully.

Furthennore, the application of the methodology was limited by the fact that there was no

time for anyone person to walk the full length of the value stream in order to confirm all of the

lean metrics, as recommended by the literature. Especially with an extended value stream, this

would have been very difficult to do. Instead, data was taken from documents such as standard

work instlUctions, shipping records, and inventory logs. It was the responsibility of team

members to validate their data contributions.

Page 53: Lean Principles Applied to Extended Value Stream Mapping

53

Finally, the idea of neatly developing the various future states in sequence, instead of in parallel,

was not practical. The team felt that future states I, II, and the ideal state could be done in

parallel. Often all three maps were worked on side-by-side. Fortunately, no one felt that the

results were compromised by taking this approach.

Page 54: Lean Principles Applied to Extended Value Stream Mapping

54

Chapter IV: Results

The purpose of this study was to implement lean improvements in the manufacturing

operations of aluminum frames supplied by Framex to Universal. Framex is a frame

manufacturer that operates out of Mexico and Canada. Universal is a major US vehicle

manufacturer whose pick-up truck assembly plant is located in Michigan and buys frames from

Framex. Universal requested that improvements be implemented within a period of six months

resulting in a cost savings for Universal.

In order to achieve the purpose of the study, the Framex cross-functional team employed

an extended value stream mapping methodology guided by lean principles. First, a current state

extended value stream map was constructed based on lean metrics obtained by the cross­

functional team. Then, extended value stream maps were created for the future state II and for

the ideal state.

This chapter will address each of the three sub-problems presented at the beginning of

this paper. First, the results of the current state extended value stream map will be presented.

Next, the results of lean improvements will be shown in terms of the future state II and ideal

state. Finally, the success of the implementation of the ideal state will be assessed by reporting

to what extent the lean metrics materialized according to the proposed ideal state. The costs

savings achieved will be repOlied.

Page 55: Lean Principles Applied to Extended Value Stream Mapping

55

Results of the Current State Extended Value Stream Map

The first sub-problem consisted of establishing the CU1Tent state of Framex manufacturing

and supply operations. This sub-problem was addressed by creating an extended value stream

map (Figure 1) that connected Framex Mexico to its customer Universal located in Michigan.

Lean metrics were collected based on what was actually happening in the value stream. The first

row in Table 1 shows the lean metrics collected for the current state.

Table I

ReslIlls o/Exlellded Vallie Slreolll!lIIpro\'elll enIS

Lean metrics

Transport Transport

Value Process Raw Finished distance

Lead added c}c1e materials goods Transport Transport finished

EVSM State time time eflkiency inventory WlP inventory distarce times goods

( days) (sec.) (%) ( days) (days) (days) (miles) (days) (miles)

Current State 37.0 118 0.0121 10 10 2225 14 2225

Future State 2 26.0 118 0.0172 10 6 2225 7 2225

Idea I State 22 .5 118 0.0199 10 2 2450 7.5 126

Implemented 21.5 118 0.D208 10 3 2 2450 6.5 126

Noles. EVSM = Extended Value Stream Map. Transport distance = distance from Franl ex final shipping facility

to Universal receiving plant. Transport time = transportation time between Framex fina I shipping fac il ity to

Universal receiving plant. In purchase contracts, transport of finished goods is paid by UniversaL See last two

columns.

time

finished

goods

(days)

14

7

0.5

0.5

framex Universal

Daily Daily

Transport Transport

costs costs

($) ($)

0 7231

0 8900

4900 252

4900 252

Page 56: Lean Principles Applied to Extended Value Stream Mapping

56

For the current state in pa11icular, the ratio of the value added time (118 seconds) to total lead­

time (37 days) resulted in a process cycle efficiency of 0.0121%. The lead-time of 37 days,

which is inversely prop0l1ionai to the process cycle efficiency, breaks down into days of

inventory and days of parts in transit. The inventory consisted of 10 days ofraw materials in the

form of aluminum coils, three days of WIP in a supermarket of stamped components, and

another 10 days of finished goods safety stock. FUl1hermore, the transp0l1ation time was made

up of two days for trucking to Laredo, two days for the cross-docking operation, and still another

10 days of rail transp0l1 to Michigan.

Results ofIdeal State Extended Value Stream Map

The second sub-problem consisted in analyzing the current state and proposing changes

that would improve transportation links and optimize manufacturing locations. The result was an

ideal state extended value stream map as shown on Figure 5.

This second sub-problem was addressed by re-configuring Framex as a regionally

optimized supplier. This was done by first proposing a future state II extended value stream map

that replaced intermodal shipping by a direct trucking route to Michigan. The resulting lean

metrics for the future state II are shown in the second row in Table 1. The ideal future state

integrated the transportation improvements, and took the final step toward an ideal state by

proposing that the finishing operations and the shipping point be moved to Framex Canada.

The improvements to the current state that resulted in a future state II involved the

elimination of the cross-docking operation as well as rail transit. The decision was made to

deliver finished goods via truck directly from Framex Mexico to the Universal assembly plant in

Michigan. Direct trucking would now take seven days instead of the previous 14 days. The

transp0l1ation time, and therefore the lead-time, was now decreased by seven days. The finished

Page 57: Lean Principles Applied to Extended Value Stream Mapping

57

goods inventory could have been reduced from 10 days down to three days but management

decided to take a cautious approach that saw the finished goods inventory reduced to six days.

The decrease in days of finished goods and days of transport resulted in a new lead-time of 26

days for future state II. The ratio of the value added time (118 seconds) to the new total lead­

time (26 days) resulted in an improved process cycle efficiency of 0.0 172% for the future state

II.

The ideal state lean improvements involved reducing the number of trucks per day

required to ship frames to Universal. This was achieved by shipping sub-assemblies instead of

fully assembled finished frames. Framex Mexico became a supplier to Framex Canada who was

now the new shipping point. The advantage of this was that nested sub-assemblies could be

shipped in much higher densities from Framex Mexico to Framex Canada in new WIP

containers. Framex Canada would continue to ship finished goods in Universal's standard size

shipping containers. The results was that the twice a day trucking could be reduced to once per

day trucking. This resulted in cutting the transportation costs down by half relative to future

state II. The transpOltation time between the two Framex facilities remained at 7 days. A minor

drawback resulted that 0.5 days would be necessary to ship finished goods between Framex

Canada and Universal at a distance of 126 miles.

The new shipping arrangement, however, had to be supported with final bolting and e­

coating at Framex Canada. There was no longer a need to keep an inventory of finished goods in

Mexico. That meant that the 6 days of finished goods that used to exist in Mexico were

eliminated in favor of keeping only 2 days of finished goods inventory at Framex Canada. In

order to deal with demand surges, management at Framex decided that raw materials that used to

number 10 days at Framex Mexico would now be shared as five days of aluminum coils in

Page 58: Lean Principles Applied to Extended Value Stream Mapping

58

Mexico and five days of sub-assemblies in Canada. Figures 5 through 7 show the new raw

materials aITangement at the Framex facilities while Table 1 shows a total of 10 days of raw

material. The resulting ratio of value added time of 188 seconds to 22.5123 days lead-time

resulted in an improved process cycle efficiency of 0.0199%.

Results of the Lean Implementation

The third sub-problem was to can·yout the lean improvements and evaluate whether the

implementation of the ideal state was successful.

The final sub-problem was accomplished by fully implementing the ideal state extended

value stream map. Three weeks were required to stabilize the lean metrics at the target levels of

the ideal state. The resulting process cycle efficiency exceeded the planned value from ideal

state extended value stream.

One further improvement was made at the request of the plant Manager at Framex

Canada. The plant manager believed that seven days of transport time could be improved. A

call for bids was held in order to find a faster and more reliable transport company. Several

companies were found that would guarantee shipments with only 6.5 days of transit time. One of

these was chosen. Therefore, the new ratio of value added time of 118 seconds to the new total

lead-time of 21.5 days now resulted in a process cycle efficiency of 0.0208%. The results were

that the lean metrics were either met or exceeded during implementation.

Page 59: Lean Principles Applied to Extended Value Stream Mapping

59

As far as achieving a costs savings, Universal now was receiving pmis shipped from

Framex Canada, which meant they only needed to pay for freight travelling 126 miles instead of

2225 miles. In the implemented state Framex was paying most of the transportation costs.

However, because of high-density WIP bins, Framex could transport material more efficiently

than Universal could in the current state. This resulted in a 29% cost savings for the overall

extended value stream to be shared between Universal and Framex. Extended over the expected

life of the program, the resulting cost savings was estimated at $2.5 million. A cost savings

calculation for the extended value stream is shown in Appendix C. Even after Universal

compensated Framex for their internal shipping costs increases, for WIP containers, and for

modest retooling, Universal still achieved a large cost savings. Compensation was handled

tlu'ough increased piece prices paid to Framex.

Page 60: Lean Principles Applied to Extended Value Stream Mapping

60

Chapter V: Discussion

The purpose of this study was to implement lean improvements in the manufacturing

operations of aluminum frames supplied by Framex to Universal. Universal requested that

improvements be implemented within a period of six months resulting in a cost savings for

Universal.

Chapter I covered the economic and market conditions that drove Universal, the vehicle

manufacturer, to seek cost reductions in the value stream that linked its pick-up truck assembly

plant to Framex. Chapter II surveyed the literature relating to the development of the Toyota

Production System and established the lean principles used in this paper. Chapter III explained

the extended value stream mapping methodology used to produce lean changes to the Framex­

Universal value stream. The analysis presented in chapter III resulted in a proposal for an ideal

state extended value stream map, which was subsequently used as the standard for the

implementation of the cost savings. The results of the implementation were presented in terms

of lean metrics in Chapter IV.

This chapter will first restate the limitations of the study. It will then discuss the results

and provide perspective on the findings of this paper. The conclusions will highlight the major

achievements of this study. Finally, recommendations for improving the practical applications of

lean principles to extended values streams will be made.

Page 61: Lean Principles Applied to Extended Value Stream Mapping

61

Limitations of the Study

In this study, the value stream being investigated for improvements and cost savings was

selected by the customer. This means no analysis was undertaken to determine which of the

possible product families would be the best suited for value stream improvements.

The extended value stream that involved the supply of aluminum frames to Universal's

Michigan assembly plant was identified as the subject of the study. Other value streams that

existed between these two companies were not addressed in this paper.

A firm time restriction existed in this study. The changes and improvements had to be

completed within a six-month period between March and August of 2008. This end date

coincided with the rollout of the new model year. The new model year was not a complete

redesign of the pick-up truck. In fact, many pat1s, such as the frames, required no changes.

FUl1hermore, the implementation of lean production in the individual facilities was

outside the scope of this study. Changes within facilities were only unde11aken if they were

meant to supp0l1 improvements to the extended value stream. This was the case with inventory

reduction. This was also the case with the retooling of the bolting station at Framex Canada.

The facilities were already using pull production and one-piece-flow so this limitation did not

affect the results.

The details of the business case were not presented. The logic behind the business case

was driven largely by the extended value stream improvements. In some cases, however, the

value stream had to change in order to ensure that the business case remained positive. This was

the case when the team realized it would have to increase shipping density to compensate for

increase transp0l1ation costs .

Page 62: Lean Principles Applied to Extended Value Stream Mapping

62

A limitation that was not recognized at the outset as being significant was the fact that

value stream maps did not contain costs data. This limitation became apparent when extended

value stream map changes were presented to management. Management was consistently

looking for business case information to justify the value stream changes. The lack of a side-by­

side presentation of costs slowed down the initial buy-in for the proposed changes.

Development of the Current State Extended Value Stt"eam Map

The creation of the current state extended value stream map increased the cross­

functional team's awareness of its supply operations. Before getting together to create sketches

of the value stream, the flow of value from Framex to Universal was unclear. Once the lean data

was collected and mapped on the value stream map, the team became more confident in

proposing improvement ideas and more skillful at identifying opportunities. Extended value

stream mapping helped the team to see the whole operation and understand how it could be

improved.

In this study, the team approach to value stream mappIng was crucial. Each team

member was able to bring specialized knowledge to the table in order to ensure that the value

stream maps were representative of what was actually happening in the plant and in the logistics

routes. The creation of the current state map was pivotal in terms of getting the cross-functional

team to speak the language of value stream mapping. On the other hand, the sales function was

also a key success factor because sales people were the link to customer cooperation and cost

sharing.

Page 63: Lean Principles Applied to Extended Value Stream Mapping

63

Development of the Ideal State Extended Value Stream Map

Future state II. The creation of the future state II value stream map was straightforward.

Using the lean principle of reducing transportation links led the team to the logical conclusion

that the cross docking operation should be eliminated. Doing this would allow a geographically

extended pull loop to be implemented between Framex and Universal. FUlihermore, the team

felt that 14 days of transport time was excessive. Even before the value stream maps were

drawn, this transportation link was known for causing unnecessary delays.

Ideal state. The creation of the ideal state map began with a challenge that arose from the

future state II map. Although the removal of the cross-dock resulted in decreasing the transport

time from 14 days to seven days, the problem remained that two trucks per day would now be

required to meet the daily requirements. Two trucks per day had the effect of increasing

transport costs relative to the current state. This increase in transport costs did not fit with the

expectations set by the literature that states that lean improvements should not incur costs. The

team concluded that lean metrics and costs needed to be looked at concurrently because

improving a single individual lean metric on its own would not automatically lead to overall

lower costs.

The team accepted the challenge to find a way to turn the transportation improvements

into a costs savings. This is how the idea of increasing the shipping density came up. The team

concluded that the only way to increase shipping density was to ship sub-assemblies instead of

full assemblies and then to have the parts assembled as close to the customer as possible. This is

how Framex Canada was drawn into the extended value stream map.

Page 64: Lean Principles Applied to Extended Value Stream Mapping

64

The way the future state II scenario naturally evolved into an ideal state was a pleasant

surprise to the team. This development confirmed that the theory developed in Seeing the Whole

(Jones & Womack, 2002) cOlTelated well with real life and that the team was on the right track.

With the implementation of increased densities, the transportation costs were now lower

by about 29% relative to the current state as shown on Table 1. Since Framex Canada was the

new ship point, keeping a finished goods safety stock in Mexico no longer made sense. The lean

principle of compressing the value stream in order to bring it closer to the customer motivated

the team to keep sub-assemblies in Canada in the form of raw materials. That way they could be

used to respond quickly to a surge in demand.

The literature also proved correct regarding the need for cooperation between supplier

and customer. The cost of WIP containers represented a significant investment that Framex

could not take-on alone. It was in Universal's best interest to compensate Framex for the cost of

WIP containers and for its increased transpOli costs. This ensured that costs savings were

implemented. The team member from sales was pivotal in negotiating this cost recovery from

the customer. This also showed that in general, improvements to the extended value stream may

require significant investments to be recovered through costs savings.

Page 65: Lean Principles Applied to Extended Value Stream Mapping

65

Implementation of the Ideal State Extended Value Stream Map

It took the team less than one month to work through the various stages of value stream

mapping and arrive at the ideal state extended value stream map. By April 2008, value stream

maps, business cases, and timelines had been firmed. Procurement and design of the WIP

containers and equipment modifications had been kicked-off.

In August when the changes had to be rolled-out, there was still some unceliainty as to

whether the actual implementation would match with the ideal state. In the first couple of weeks

after rollout, the target lean metrics were not immediately realized. It took about three weeks to

reach the target metrics. In the case of transportation, a last minute improvement opportunity

was recognized by management whereby the transportation time from Mexico to Canada was

decreased by one day, resulting in yet another improvement in the process cycle efficiency.

Page 66: Lean Principles Applied to Extended Value Stream Mapping

66

Conclusions

The results of this study were a success from the point of view of lean metrics as well as

cost savings. All parties involved benefited from this success.

The process cycle efficiency in the implemented state, i.e. the time spent on doing value

added work, increased by 72% relative to the current state. This improvement was driven by the

reduction in lead-time which itself was due to transp0l1ation improvements and bringing the

extended value stream closer to the customer.

Overall transp0l1ation costs decreased by 29%: from $7231 per day to $5152 per day.

Since Universal only had to pay for finished goods transportation, their transportation costs

dropped from $7231 to $252 per day. The cost savings achieved by Universal in this way were

used to compensate Framex for their increase in transportation costs and for their investments.

The costs saving generated by applying lean principles to this extended value stream over five

years, the life of the program, were expected to be $2.5 million. The expected cost savings

calculation is shown in Appendix C

A win-win-win scenario occurred here. Framex was awarded a higher piece price to

cover a share of the cost savings plus investment recovery. Universal's operating costs

decreased as result of buying frames at a lower total cost, including product and transportation

costs. Perhaps most importantly, consumer benefitted because they could now get better value

on their purchase of a new pick-up truck due to incentives supp0l1ed by the manufacturer's lower

operating costs.

Overall, the conclusions of this paper match with the outcomes predicted in the literature.

Cooperation between Framex and Universal, including sharing in the cost savings, motivated all

parties to work toward a leaner extended value stream. The process cycle efficiency increased at

Page 67: Lean Principles Applied to Extended Value Stream Mapping

67

each step of the value stream map development. The only major unforeseen development was

the transpoliation cost increase in future state II that fortunately resulted in net transpoliation

cost decrease in the ideal state.

Recommendations

The following recommendations are based on the lessons leamed during the planning and

implementation of the extended value stream lean improvement.

Center of knowledge. A value stream mapping team with specialized knowledge should

be established in order to assist future improvements or costs savings exercises that require

special knowledge of the application oflean principles to extended value stream.

Value stream manager. Project managers should be trained as value stream managers

and should be responsible for the continuous improvement of the value stream. In the

automotive industry, project managers have unique cross-functional knowledge that would make

them the ideal value stream manager. Executive management needs to support their role as value

stream managers in order for this recommendation to be implemented successfully.

Value stream continuous improvement. A standard set of lean metrics should be

selected based on careful consideration of customer values and requirements. Then, a database

should be established to store and maintain lean metrics. Periodic updates to the lean metrics

should occur in order to support periodic reviews of extended value stream maps. This would be

the basis for the continuous improvement of value stream maps.

Value stream mapping up-front. Regional optimization using extended value stream

mapping should also be considered before plant locations are built. Value stream mapptng

would be a useful too when planning new greenfield or brownfield expansion projects.

Page 68: Lean Principles Applied to Extended Value Stream Mapping

68

References

Black, J. T., & Hunter, S. L. (2003). Lean mam!facturing systems and cell design. Dearborn, WII:

Society of Manufacturing Engineers.

Blanchard, D. (2007). Lean on me. Industry Week, 256(12), p53-54.

Dennis, P. (2007). Lean production simplified (2nd ed.). Boca Raton, FL: Productivity Press.

Dolcemascolo, D. (2006). Improving the extended value stream: Lean/or the entire supply

chain. New York, N.Y. : Productivity Press.

Drickhamer, D. (2003). Best practices - see the big picture. Industry Week, 252(3), 57.

Duggan, K. J. (2002). Creating mixed model value streams. New York, N.Y.: Productivity

Press.

Gapp, R., Fisher, R., & Kobayashi, K. (2008). Implementing 5S within a japanese context: an

integrated management system. Management Decision, 46(4), pp. 565-579.

Imai, M. (1997). Gemba kaizen: a common sense low-cost approach to management. New York,

N.Y.: McGraw-Hill.

Jones, D. T., & Womack, J. P. (2002). Seeing the whole. Brookline, MA: Lean Enterprise

Institute.

Lean Enterprise Institute. (2008). Principles a/lean. Retrieved from

http://www.lean.org/WhatsLean/Principles.cfm#specify

Liker, J. K. (2004). The toyota vl'ay. New York, N.Y.: McGraw-Hill.

Marr, K. (2009). Toyota passes general motors as ·world's largest carmaker. Retrieved from

http://www.washingtonpost.com/wp-

dyn/content/aliic1e/200910 1 121 1 AR20090 121 01216.html

Page 69: Lean Principles Applied to Extended Value Stream Mapping

69

Mass, W., & Robertson, A. (1996). From textiles to automobiles : mechanical and organizational

innovation in the toyoda enterprises, 1895-1933. Business and Economic History, 25(2).

Nash, M. A. , & Poling, S. R. (2008). Mapping the total value stream: The complete guide to

production and transactional mapping. New York, N.Y.: Productivity Press.

Nicholas, J., & A vi, S. (2006). The portal to lean producNon: principles and practices for doing

more with less. Boca Raton, FL: Taylor & Francis.

Pinkham, M. (2005). Caution: Profitability potholes ahead. MetalCenter News, 45(5).

Rother, M., & Shook, J. (1999). Learning to see. Brookline, MA: Lean Enterprise Institute.

Tapping, D., Luyster, T., & Shuker, T. (2002). Value stream management: Eight steps to

planning, mapping, and sustaining lean improvements. New York, N.Y.: Productivity

Inc.

Womack, J. P. (2006). Value stream mapping. Manufacturing Engineering, 136(5), 145-155.

Womack, J. P. (2009). The end of an era. Retrieved from

hup://www.lean.org/common/display/?0=J005

Womack, J. P., & Jones, D. T. (1996). Lean thinking: Banish ·waste and create wealth in your

corporation. New York, N.Y.: Simon & Schuster.

Womack, J. P., & Jones, D. T. (2005). Lean consumption. Harvard Business Report, 83(3), p.

58-68 . Womack, J. P., Jones, D. T., & Daniel Roos. (1990). The machine that changed the world. New

York, N.Y.: Free Press.

Page 70: Lean Principles Applied to Extended Value Stream Mapping

Properties - Map3

Categoties -Custom Data

Entelptise

l"m!ml ----.

Appendix A

Takt Time Calculation

Setup 'I Tlmeline 1 Graph 1

Available Work Time

Hours Per Shift :

Break Minutes Per Shift :

Shifts Per Day:

Da;'S Per "'l/eek:

Days Per Month:

Takt Time

8

40

5

20

Customer Demand---------

[IiJilllilll / IYear

4 t¥4l weeks

Takt Time -----------

63.4 [ seconds

pieces / piece

Display Format: [63 seconds G T akt Goal I Percentage

Inventory Lead Time : [ Based on T akt Time

1 I Cancel I I Help ~ ___ ~ L ____ ~ OK

70

Page 71: Lean Principles Applied to Extended Value Stream Mapping

Appendix B

Process Cycle Efficiency Sample Calculation

For the implemented ideal future state ...

PCE = VAT Implelllellted L dT' ea lme

118sec. PCEilllplelllell/(xl = 7 3333h

2 1. 5 days .' ours day

3600sec.

hour

118sec. PCEilllplelllellttri = 7 3333h 3600 xl 00%

21 Sd . ours sec.

. aysx x day hour

PCEilllplelllellled = 0.0208%

71

Page 72: Lean Principles Applied to Extended Value Stream Mapping

Appendix C

Expected Cost Saving Calculation

For the extended value stream ...

Cos tSa v ings Pr ogmlllLife = DailySavings x 5 years

Cos/Savings Pr ograllll,ife = (TransporlalionCostscllrrelllSlale - TramporlalionCosts IclealSlale) X 5 years

· $7231 $5152 24 o days CoslSavtngsprogralllLife = (-- - ) x 5years x -----"---

day day year

· $2079 24 o days CostSavtngs Pr ograllll,ife = ( ) x 5 years x -----"---

day year

· $2079 Cos/SavtngsPr ogralllLife = (---) x 1200days

day

CostSavings ProgralllLife = $2,494,800

72