Lean Construction 8 Wearne

download Lean Construction 8 Wearne

of 26

Transcript of Lean Construction 8 Wearne

  • 8/12/2019 Lean Construction 8 Wearne

    1/26

    A Supply Chain perspective

    Chris Wearne

    CH2M Hill Halcrow

    Lean in the Highways Agency

  • 8/12/2019 Lean Construction 8 Wearne

    2/26

    Lean in the Highways Agencya supply chain perspective

    A theme? - Every day is different but every day is the same?

    The secondee model - the supply chain perspective

    - new skills or a career move?

    Reflections from projects - Communications Cells

    - Improvement projects

    - Collaborative Planning

    Some messages to share - the HA Lean Initiative

    - what gets in the way, what works in public service

  • 8/12/2019 Lean Construction 8 Wearne

    3/26

    Lean in the Highways Agencya supply chain perspective

    HA set up Lean Division in 2009, 7 staff, started training autumn 2009

    HA invited suppliers to identify secondees to join HA team

    Secondees offered free training, with HA staff, to apply Lean in HA project work

    Secondee projects - MAC Area 10 DDA Improvements- MAC Area 10 Site Communications Cell- M25 DBFO DNs Consultancy Services

    Some added to their skill set, others changed course.

    Facilitator projects - MAC Area 12/14 Plant Management

    - MAC Area 10 Scheme development Communications Cells - M25 DBFO DNs Consultancy Services, handover

    - HA Departures from Standards process improvement- Boston Manor Viaduct Repair, Collaborative Planning- A1 Lobley Hill to Dunston Collaborative Planning, ongoing- M4 Managed Motorways Collaborative Planning, ongoing- HA Commercial Management reporting, ongoing

  • 8/12/2019 Lean Construction 8 Wearne

    4/26

    Case study 1/6 - Communication Cells, bridge refurbishment

    HA sought willing horse, a very capable Works Manager, to take on the idea.

    Unipart carried out a communications audit; the ratings were not good

    Discussion to design a Lean Daily Management System / Communications Cell

    Display set up at hut crossroads, meetings set up at 10.15am, brewtime

    Daily meeting attended by day to day managerslast planner

    Disciplines: blacktop , TM, fencing, barrier repairs, concrete, w/proof, design liaison

    The site personnel received training in facilitation and rotated the role

    Engagement assisted by altering site routines as little as possible

  • 8/12/2019 Lean Construction 8 Wearne

    5/26

    M6 Lowton Bridges Refurbishmentthe display board

    Board reviewed daily, every day the same Board reviewed weekly

    The telling feedback was when the Works Manager moved to a new site and

    had no cabins for a Communications Cell; he found his job much harder

  • 8/12/2019 Lean Construction 8 Wearne

    6/26

    Case Study 2/6 - MAC Area 10 Communications Cellsin use

    Two tiers, portfolio x 3 and managementFebruary 2011

  • 8/12/2019 Lean Construction 8 Wearne

    7/26

    Case study 3/6 - M25 DN Consultancy Services

    The M25 is the worlds busiest motorway.

    In May 2008 the HA let a 5bn contract to widen critical elements of themotorway and then the operate this for a period of 30 years.

    The widened lengths are junctions 5-7, 16-23, 2327, 2730; these to be

    completed for the London Olympics.

    Departments Nominee Consultancy Services (DNCS) are provided by HyderHalcrow Joint Venture (HHJV)

    HHJV were tasked with reducing their annual expenditure from 10m to just over8m, a reduction of nearly 20%

    Reduction of costs for reviewing design proposals was isolated as priority

    Understanding the process generated engagement, as well as reducing waste.

  • 8/12/2019 Lean Construction 8 Wearne

    8/26

    M25Mapping the process, understanding the value

    Value Added Time concluded to comprise 7% of total elapsed time

    Essential but non Value Added Time comprises 12% of elapsed time

    Analysis highlighted scope and opportunities for potential improvement

  • 8/12/2019 Lean Construction 8 Wearne

    9/26

    M25What we did to address wastes

    Extent of Work In Progress, measured in days, reduced from over 22 days to under15 days. Maximum allowed is 28 days

    Works submissions reviews carried to a level of detail to reflect the level of riskattached to the submission ie high risk still processed by technical specialists,lower risk processed by DN / DNCS staff. ( addressing over-processing)

    Training day held to explain precise wording and intent of DBFO contract,attended by senior staff and technical specialists ( eliminating defects)

    Data input transferred from technical specialists to Document Management Group/IT / data specialists (addressing skill misuse)

    Cost reduction achieved due to release of 2No Review Managers, arising from re-

    organisation following rationalisation of the Review Process.(over-processing)

    Every submission is different but can be treated the same??

  • 8/12/2019 Lean Construction 8 Wearne

    10/26

    Case study 4/6 - Plant Management in MAC Area 12/14

    People

    Environment

    Materials/Machines

    Maintain focus / objectives

    Concern

    Management of fitters

    Opportunity

    Possible central team

    Involvement

    Harness knowledge

    from people on the

    ground

    Quick wins

    Early benefits

    Build confidence

    of the process

    Too many

    vehicles

    Concern

    Jarma/High Stone/SAGE

    interaction/Duplication

    Too manMaintaining 2 systems + applying sticking

    plasters rather than sorting one system out

    Evaluate Best Practice across areas

    4-Area

    co-

    Different responsibilities within area teams(a smokescreen of Team X dont do that)

    Methods

    No genuine cost control

    Plant & e ui ment under

    No control of small

    plant

    Si n off lant

    Plant & e ui ment not bein off-

    Disconnected processes (lots of hand

    offs, people not seeing the end to end

    Plant & equipment costs not being

    Allocatin cost

    Concern

    Utilisation/allocation - who does

    itnetwork/ lant/cost ca ture

    Equipment

  • 8/12/2019 Lean Construction 8 Wearne

    11/26

    Plant Management in MAC Area 12/14mapping the waste

    Process map: 39 handovers, 5 IT packages, lots of duplication, responsibilities unclear

    0.00

    2,000.00

    4,000.00

    6,000.00

    8,000.00

    10,000.00

    12,000.00

    WX54XSM

    GU59LZO

    KV59VPG

    BF59TXG

    GU59LZD

    PN59XXU

    KV59VHD

    YS08LSX

    Loading Shovel 26TTM VEHICLE 3.5TSC Tipper Ford Connect Van ISU - Vehicle - ISU VW Caddy SPRINTER 311 CDI SCDROPSIDE

    WelfareV an

    lump sum cost

    Allocated hours

    Idle hours

    Pareto of data for one plant depot

  • 8/12/2019 Lean Construction 8 Wearne

    12/26

    Plant Management in MAC Area 12/14The New Process

    Main features of new processeach item different, all treated the same

    All plant allocated to a named supervisor

    Single step system to book plant and fuel for individual orders

    Single stop Plant Co-Ordination system

    Single Plant Register, based in one IT system

    Cost Capture / Plant Administration support at Site / Depot, to capture income dueControl using X and Y, Measuring the Xs inputs

    X1 - % timesheets Right First Time, check fuel records etc admin team

    X2 - Number of items not allocated to Supervisor admin team

    X3 - Number of complaints re late / non delivery / unfit for use supervisors

    X4 - Number of plant - related safety incidents safety teamX5 - Number of items not used in month plant team

    X6 - No. items used 700/m, in month plant team

    X7 - No. items used

  • 8/12/2019 Lean Construction 8 Wearne

    13/26

    Case study 5/6 - Boston Manor Viaduct Repairs, 2012

    of all the gin joints,

    in all the towns, in all the worldshe has to walk into mine.

    Of all the viaducts,

    on all the routes, in all the network

    it has to be this one.

    Airport Site Olympic Park

  • 8/12/2019 Lean Construction 8 Wearne

    14/26

    Boston Manor Viaduct Repairthe 7 week Olympic challenge

    Background - Government under pressure

    Hosepipe bans, record rains and flash floods

    G4S and a shortage of security guards

    Border Agency and a discussion over policyDelays at the airports

    965m long, 17 span, plate girder bridge

    Investigation found cracks, April 2012

    Cracks seen as high risk, due to weld method

    7.5 T weight limit, 33 major repairs needed

    Need to open for Olympic traffic, 13 July

    Daily updates to the Permanent Secretary

    Roles & ResponsibilitiesThe Principal Contractor was Connect Plus, client the Highways AgencyThe Lean support consultants were Navitas Project Solutions + Halcrow

  • 8/12/2019 Lean Construction 8 Wearne

    15/26

    Boston Manor Viaduct, first stage, Collaborative Mapping

    What is requiredscope / sequence + instruction for steelwork

    Confirmation of issues

    Improve communication & flow

    Shared vision on scope

    Programme to deliver for Olympic 2012

    Clarity on process until 13 July deadline

    Clarity on roles and dependencies / who we affect

    Identify key deliverables for Design, Construction and the Client

  • 8/12/2019 Lean Construction 8 Wearne

    16/26

    Boston Manor Viaduct, second stage, Collaborative Programming

    Continuous re-programming almost on a daily basis, used magnets, steel cabinColour codes used to show the accountabilities of disciplines / parties

    Wall display used it as a visual aid - to aid parties to map what was in their minds

    A programmer emailed this out daily to all stakeholders

    Agreed to set up daily production meetings (7 days a week) on site / conference call

  • 8/12/2019 Lean Construction 8 Wearne

    17/26

    Boston Manor Viaduct, third stage, daily Production Meetings, 9am

    Daily meetings covered investigation, design, manufacture and construction tasksAll key stakeholders involved dailyup to 15 people. Every day the same

    Execute the PlanDoCheckAct cycle, improve, improve; repair cycle 30 - 9 days

    Key tasks were shown as status complete or not complete and reasons captured.

    Reasons were analysed and mitigation actions put in place on a daily basis.

    Tasks were captured for all Stakeholders including the HADN, Netserv, PM etcCapture reliability of planned tasks completion and reasons for non completion

    On Tuesday 10thJuly, co-ordination meetings held 9am. 5pm, 7pm, 9pm

  • 8/12/2019 Lean Construction 8 Wearne

    18/26

    Boston Manor Viaduct, shared information to aid collaboration

    Each stage of the repair was numbered and shown using magnetsA corresponding 3D snapshot was also produced and positioned next to the magnetic

    programme showing the key steps

    Board also used for shift handoverto show progress status of various repairs(concerns / causes / countermeasure) and what was expected during the next shift.

    The information on the walls was used as part of site induction for new starts, to aid

    understanding of the requirements

  • 8/12/2019 Lean Construction 8 Wearne

    19/26

    Boston Manor Viaducts - Benefits

    Boston Manor Viaduct was open for use by the Olympic traffic on the 16th July

    Created a collaborative working environment under intense pressurised conditions

    (nobody fell out, everyone kept calm, even when we shut the M4)

    Reliability improved throughout doing the same things, 40 times, getting better

    From Graham Daltons blog what did we learn? that Lean techniques really work

    Message from the Permanent Secretary on behalf of the Prime Minister to the Highways

    Agency: I want to pass on my personal thanks to all those who worked so hard to

    repair the M4 bridge and get it open again in time for the Olympics. You

    showed real determination to get the job done in time, working through

    the night to do so. I was delighted to get the news very early this morning

    0%

    20%

    40%

    60%

    80%

    100%

    0001111111111222222222230000000001111

  • 8/12/2019 Lean Construction 8 Wearne

    20/26

    Would you recommend on other schemes

    Definitely will recommend 3

    Probably 6

    Undecided

    Probably not

    Will not recommend

    Team understood what project success was

    Strongly agree 4

    Agree 5

    Neutral

    Disagree

    Strongly agree

    Key feedback from 9 questionnaires

    Magnetic board was very useful, it gave more flexibility than an IT programmeOsborne

    Lean programme, having programme on wall for all to seeOsborne

    Collaborative planning and programming. Engagement and positive participation of all

    partiesHA

    Daily programme + collaborative meetings brought all parties together + communicating

    well. Ensured each party knew what was expected of them - clear actions - Connect+

    Regular planning resource programming on highly visual basis - Connect+

    Tracking tasks through 24hrs was a good tool to use - Hyder/HA

    Wall chart programme - Connect +

    Boston Manor Viaduct - Feedback

  • 8/12/2019 Lean Construction 8 Wearne

    21/26

    Case study 6/6Collaborative Planning, adapted to suit

    M25 Bearing scheme developmentall we did was attack the gaps between activitiesthrough SMART targets in meeting minutes.

    Dartford Tunnels safety works5 contracts, no Management Contractor(weekly production meeting, monthly programming)

    A1 Lobley HillDunston, scheme development(weekly production meeting, monthly programming, demountable display)

    A19 Seaton Burn, MAC Improvement, asked to set up by attendee at A1 start-up(weekly production meeting, monthly programming)

    M4 Managed Motorways , scheme development

    (weekly production meeting, monthly programming)

    M1 1916 Managed Motorways, scheme developmentThis now mandated across all HA Major Projects

    The challenge is to apply a proportionate level of Lean

  • 8/12/2019 Lean Construction 8 Wearne

    22/26

    A mind map for Continuous Improvement

    The greatest waste is the waste we do not see Shingo

    We know its there Lean can isolate it Managers can act

    Labour

    Plant

    Materials

    Waste

    Labour

    Plant

    Materials

    Labour

    Plant

    Materials

    CW, based on figure by Dan Ward, Constructing Excellence

  • 8/12/2019 Lean Construction 8 Wearne

    23/26

    The HA Lean Initiativewhat could have been done differently?

    Clients have the best view of suppliers wastes and vice versa more joint working

    HA staff see that they should have started applying Lean internally earlier

    Easy to over process - project initiation, benefits capture, knowledge transfer

    Elements of contract coverage - eg control of variances - not aligned to Lean

    Relationship of Lean to procurement decisions, supplier assessment must be clear

    Demonstrating savings, auditably, requires current state data which may not exist

    Some lack of appreciation of the value of savings to client, made by the supply chain

    Basic Lean5S, Coll Planning, Comms Cellshas delivered more than 6 - Sigma

  • 8/12/2019 Lean Construction 8 Wearne

    24/26

    A supply chain perspective, parting thoughtsrisks and blockers

    There are managers who will not welcome an outsider into their project

    It all starts well and goes back to sleep once the initial energy has dissipated

    Making the changes can be too much, e g for busy managers

    It only takes one or two key opinion formers to make things difficult

    One persons job is.another persons waste

    The first visible result can be the costs for the Lean Practitioner

    Once there are savings, there can be a fight for the credit or a share

    If there is need for a lean project it must mean that someone is no good?

  • 8/12/2019 Lean Construction 8 Wearne

    25/26

    Lean in the HAa supply chain perspective, enablers and keys

    The financial savings are there and are real, but the engagement is as valuable

    Lean journeysorganisations, projectsare better with a map than a prescribed route

    Lean projects themselves need to be proportionate; why not 3 hours?

    The savings come slower than you thinkbut can easily be 10 - 20 times the cost

    Collaborative Planning generates engagement and benefits fastestin under an hour

    Standardisation can be achieved as effectively by a baseline as a straightjacket

    Every day is differentbut every day is the same

    To transfer knowledge - the best library is no substitute for direct infection

    My mission isto infect

  • 8/12/2019 Lean Construction 8 Wearne

    26/26

    Lean in the HAa supply chain perspective

    Any questions?

    Thank you

    [email protected]