Lean Aircraft Initiative Plenary Workshop · LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE...
Transcript of Lean Aircraft Initiative Plenary Workshop · LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE...
Lean Aircraft InitiativePlenary Workshop
The Role of the ScheduleDevelopment Process
October 8, 1997
Capt Ross McNuttMIT
Capt McNutt PD100897- 2 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Overview
l Structure Method and Objectivesl The Schedule Development Storyl Schedule Processl Small Group Discussions
Capt McNutt PD100897- 3 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Schedule Development Phases
Planning Phase Contracting Phase Development Phase
Project Approval
ContractSigned
FirstProduction
Item
Develop Initial Project Schedule
Select Contractor and
Develop Contract Schedule
Actual Development
Schedule
Capt McNutt PD100897- 4 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Defense Product
Development Processes
Modernization Planning Process
Req DefinitionProcess
Users AcquisitionReview Process
Req Validation Process
Idea GenerationProcess
Acquisition PlanningProcess
Contracting Process
Development Oversight Process
MarketingProcess
Proposal Generation
Process
Product and Process
Development
Contractors
Program Office
PentagonPPBS
Process
Resource Planning
Planning
Contracting
Development
AcquisitionOversightProcess
Capt McNutt PD100897- 5 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Schedule Process
Research Methodology
l Objectives– Identify the important factors involved in the development of
project schedules– Determine the effect of those factors on project outcomes
l Three Surveys - Different levels and roles in process– Contractor Program/Project Managers 104– Program Office Program/Project Managers 151– Pentagon Program Element Monitors 62
– 317 Project Surveys Completed
l Case Study – Post Acquisition Reform Development Effort– Demonstration of Current Schedule Process
Capt McNutt PD100897- 6 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Initial Schedule Development
in the Planning Phase
Planning Phase Contracting Phase Development Phase
Project Approval
ContractSigned
FirstProduction
Item
Develop Initial Project Schedule
Select Contractor and
Develop Contract Schedule
Actual Development
Schedule
Capt McNutt PD100897- 7 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
User’s Desired Date
SpecifiedFuture Date
“ASAP”
Program Element Monitor Survey
80% 20%
Capt McNutt PD100897- 8 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Operational Need Date
Program Element Monitor Survey
Future orProjectedDeficiency
CurrentOperationalDeficiency
70% 30%
Capt McNutt PD100897- 9 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Ranking of Program
Objectives (1st to 4th)
Superior Performance Low Acquisition Cost
Low Operation Costs Shortened Schedule
PEM and SPO Surveys
FourthThirdSecondFirst
100
80
60
40
20
0FourthThirdSecondFirst
100
80
60
40
20
0
FourthThirdSecondFirst
100
80
60
40
20
0FourthThirdSecondFirst
100
80
60
40
20
0Axi
s: N
umbe
r of
Pro
gram
s R
espo
ndin
g
Capt McNutt PD100897- 10 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Mode Rank
SuperiorPerformance 1st
LowAcquisition Cost 2nd
Low Operational Cost 3rd
ShortenedSchedule 4th
Program Objective Significance Table
X
.03
<.001
<.0001
X
.05
<.01
X
.36 X
Perf Acq Cost Ops Cost Schd
* Using the Non-parametric Wilcoxon Rank-sign Test PEM and SPO Survey’s N=209
Capt McNutt PD100897- 11 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Factors Influencing the
Projects’ Starting Date
Program Element Monitor Survey
User's DesiresLeadership Desires
Expect Dev FundingExpect Prod FundingService Planning
Technology DevelopmentDep on Another ProgramEngineering DevelopmentTesting RequirementsManuf Process DevelopSupport Requirements
No Some Defining Impact Impact Impact
1
2
3
Mean7654321
Capt McNutt PD100897- 12 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Factors Influencing the
Length of the Initial Schedule
User's Desired ScheduleExpected Dev FundingExpected Prod Funding
Testing RequirementsEngineering Development
Leaderships Desires Technology DevelopmentDep on Another ProgramService Force Planning
Support RequirementsManuf Process Dev 2.9
3.0
3.4
3.5
3.6
3.6
4.0
4.0
4.4
4.6
7654321
1
2
3
4
Government Project Manager Survey
4.8
No Some Defining Impact Impact Impact
Capt McNutt PD100897- 13 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Relative Order of Information
Used for Initial Schedule
Expected Dev Funding
Expert Judgment
Contractor Proposed Schd
Historical Similar-Program
Bottom-Up Schedule Dev
Parametric Modeling
Comparable Commercial 3.0
3.5
4.2
4.5
4.7
5.2
5.4
7654321
1
2
3
4
5
Government Project Manager Survey
No Some Defining Impact Impact Impact
Capt McNutt PD100897- 14 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Scheduling Tools Used
Milestone
Gantt
Critical Path Manag
PERT
Other Tools
System Center-based 1.5
1.7
3.2
4.2
4.7
5.2
7654321
1
2
3
4
5
Government Project Manager Survey
NotUsed
OccasionallyUsed
ExtensivelyUsed
Capt McNutt PD100897- 15 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Evident Across Many
Project Categories
l Same General Trend Occurs Across – All Program Sizes
- ACAT I, II, and III
– All Levels of Technological Advance- Revolutionary, New Generation,
and Incremental Improvements
– All System Types- Aircraft, Spacecraft, Electronic Systems, Munitions
Capt McNutt PD100897- 16 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Planning Phase
Schedule Results
Planning Phase Contracting Phase Development Phase
- Schedule is not seen as a high project priority
- Planned schedules determined by expected budget allocations - not development related requirements.
Project Approval
ContractSigned
FirstProduction
Item
Select Contractor and
Develop Contract Schedule
Actual Development
Schedule
Capt McNutt PD100897- 17 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Schedules in the
Contracting Phase
Planning Phase Contracting Phase Development Phase
Project Approval
ContractSigned
FirstProduction
Item
Select Contractor and
Develop Contract Schedule
Actual Development
Schedule - Schedule is not seen as a high project priority
- Planned schedules determined by expected budget allocations - not development related requirements.
Capt McNutt PD100897- 18 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Government Specified
Schedule in RFPs
“ Did the Government, through its RFP or other means, specify an expected project schedule to the contractors?”
Program Element Monitor Survey
Schedule Not
Specified
SpecifiedExpectedSchedule
80% 20%
Capt McNutt PD100897- 19 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
1.8
3.7
3.8
3.9
5.6
7654321
1
2
3
Factors Influencing Contractor Proposed Schedules
No Moderate Sole Impact Impact Determinant
Contractor Survey
Customer’s Desired Schedule
Expected Development Funding
Expert Judgment/Bottom-up Analysis
Historical Similar Programs
Comparable Commercial Development
Capt McNutt PD100897- 20 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
3.1
3.4
3.4
3.7
4.2
4.6
7654321
Contractor Ability to Influence Program
Program or Product Concept
System PerformanceRequirements
Program Schedule
Overall Budget or Funding Profile
Trade-offs between Perf, Cost, and Sched
Acquisition Strategy
No Some Very Large Impact Impact Impact
Contractor Survey
1
2
3
4
Capt McNutt PD100897- 21 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Importance of Schedule For
Source Selection
“Was development time a significant evaluation criteria during your source selection?”
Mean = 3.6Government Program Manager Survey
Development Time In Source Selection7654321
30
20
10
0
Not Somewhat VeryImportant Important Important
Capt McNutt PD100897- 22 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Contractor Incentive to Bid a
Different Schedule
5711
56
554
Incentive to Bid a Different Schedule7654321
60
50
40
30
20
10
0
Nu
mb
er
of
Res
po
nd
ents
A Strong No A StrongDisincentive Incentive Incentive
Contractor Survey
Capt McNutt PD100897- 23 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Contractor Bid Schedule
Vs Government Plan
Mean = 0.9
Percent Difference of Contractor Proposed Schedule
70
60
50
40
30
20
10
0
Contractor Survey
100
806040200-20
-40
-60
-80
-100
Nu
mb
er o
f R
esp
on
den
ts
Capt McNutt PD100897- 24 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Schedules of Proposals
Received By Program Offices
Contractor Proposal Schedules Compared to Initial Government Estimate
200
175
150125
100
75
50
250
>15% 5% to 15% Within 5% to 15% >15%Shorter Shorter 5% Longer Longer
Number of
Proposals Received
Program Managers Survey
Capt McNutt PD100897- 25 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Schedule Results of the
Contracting Phase
Planning Phase Contracting Phase Development Phase
Project Approval
ContractSigned
FirstProduction
Item
Actual Development
Schedule - Schedule is not seen as a high project priority
- Planned schedules determined by expected budget allocations - not development related requirements.
- Contracting phase incentives enforce expected
schedule and eliminate possible alternatives.
Capt McNutt PD100897- 26 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Schedules in the
Execution Phase
Planning Phase Contracting Phase Development Phase
Project Approval
ContractSigned
FirstProduction
Item
Actual Development
Schedule - Schedule is not seen as a high project priority
- Planned schedules determined by expected budget allocations - not development related requirements.
- Contracting phase
incentives enforce expected schedule and eliminate possible alternatives.
Capt McNutt PD100897- 27 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
4.7
4.3
3.4
7654321
Changes Due toUnforeseen Events
Performance
Cost
Schedule
Least Likely Most LikelyTo Change To Change
1
2
3
Government Program Manager Survey
Capt McNutt PD100897- 28 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Mean = 3.4 Ease of Lengthening Schedule
7654321
60
50
40
30
20
10
0
Ease of Changing Schedule
ShorteningMean = 5.6 Ease of Shortening Schedule
7654321
60
50
40
30
20
10
0
NotDifficult
VeryDifficult
NotDifficult
VeryDifficult
Government Program Manager Survey
Capt McNutt PD100897- 29 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Available Schedule-Related
Incentive Fees
On Time CompletionEarly Completion
Mean = 1.5 Percent of Contract
2520151050
Early Completion
Mean = 3.0 Percent of Contract
100
90
80
70
60
50
40
30
20
100
2520151050
Num
ber
of
Res
pond
ents
Num
ber
of R
espo
nden
ts
100
90
80
70
60
50
40
30
20
100
Government Program Manager Survey
Capt McNutt PD100897- 30 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Contractor View of
Incentives
4.3
4.4
4.4
4.4
4.7
7654321
A Strong No A StrongDisincentive Incentive Incentive
Contractor Survey
Reduce Total Program Cost
Reduce Unit Cost
Shorten Schedule
Exceed Performance Req.
Exceed Reliab/Maintenance
Capt McNutt PD100897- 31 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Program Slip
Government Program Manager Survey
Schedule Slip (Months)
80
60
40
20
0604020-20
Num
ber
of
Pro
gram
s
-10 100 5030 70 80
Capt McNutt PD100897- 32 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Program Slip Per Year
40
30
20
10
0
Average Slip Per Year (Months per Year)
Government Program Manager Survey
Num
ber
of
Pro
gram
s
30
24
18
12
60-6-12
Capt McNutt PD100897- 33 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Program Slip
Major Acquisition Programs
Rand Database: All DoD Major Acquisition Programs since 1965
Program Schedule Change (Months)
140120100806040200-20
70
60
50
40
30
20
10
0Num
ber
of
Pro
gram
s
Capt McNutt PD100897- 34 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Execution Phase
Schedule Results
Planning Phase Contracting Phase Development Phase
Project Approval
ContractSigned
FirstProduction
Item
- Development phase result - one way program slips.
- Schedule is not seen as a high project priority
- Planned schedules determined by expected budget allocations - not development related requirements.
- Contracting phase
incentives enforce expected schedule and eliminate possible alternatives.
Capt McNutt PD100897- 35 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Defense Product
Development Process
Modernization Planning Process
Req Definition Process
Users
AcquisitionReview Process
Req Validation Process
Idea GenerationProcess
Acquisition PlanningProcess
Contracting Process
Development Oversight Process
MarketingProcess
Proposal Generation
Process
Product and Process
Development
Contractors
Program Office
PentagonPPBS
ProcessResource Planning
Planning
Contracting
Development
AcquisitionOversightProcess
Capt McNutt PD100897- 36 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Schedule Planning Inputs
Modernization Planning Process
Req Definition Process
Users
AcquisitionReview Process
Req Validation Process
Idea GenerationProcess
Contracting Process
Acquisition PlanningProcess
Development Oversight Process
MarketingProcess
Proposal Generation
Process
Product and Process
Development
Contractors
Program Office
PentagonPPBS
ProcessResource Planning
ORD POM
Marketing
MAJCOM POM Input
Proposed ORD
AcquisitionOversightProcess
Capt McNutt PD100897- 37 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Schedule Planning Outcomes
Modernization Planning Process
Req Definition Process
Users
AcquisitionReview Process
Req Validation Process
Idea GenerationProcess
Acquisition PlanningProcess
Development Oversight Process
Contracting Process
MarketingProcess
Proposal Generation
Process
Product and Process
Development
Contractors
Program Office
PentagonPPBS
ProcessResource Planning
ORDPOM
Marketing
Acq Plans
APB
MAJCOM POM Input
Proposed ORD
AcquisitionOversightProcess
Capt McNutt PD100897- 38 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Contracting Process
Modernization Planning Process
Req Definition Process
Users
AcquisitionReview Process
Req Validation Process
Idea GenerationProcess
Acquisition PlanningProcess
Contracting Process
Development Oversight Process
MarketingProcess
Proposal Generation
Process
Product and Process
Development
Contractors
Program Office
PentagonPPBS
ProcessResource Planning
ORDPOM
Marketing
Acq Plans
APB
RFP
ProposalContract
MAJCOM POM Input
Proposed ORD
AcquisitionOversightProcess
Capt McNutt PD100897- 39 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Development Process
Modernization Planning Process
Req Definition Process
Users
AcquisitionReview Process
Req Validation Process
Idea GenerationProcess
Acquisition PlanningProcess
Contracting Process
Development Oversight Process
MarketingProcess
Proposal Generation
Process
Product and Process
Development
Contractors
Program Office
PentagonPPBS
ProcessResource Planning
ORDPOM
Marketing
Acq Plans
APB
RFPProposal
ContractCSCS
Program Reviews
MAJCOM POM Input
Proposed ORD
AcquisitionOversightProcess
CARSProgram Reviews
Capt McNutt PD100897- 40 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Defense Product
Development Process
Modernization Planning Process
Req Definition Process
Users
AcquisitionReview Process
Req Validation Process
Idea GenerationProcess
Acquisition PlanningProcess
Contracting Process
Development Oversight Process
MarketingProcess
Proposal Generation
Process
Product and Process
Development
Contractors
Program Office
PentagonPPBS
ProcessResource Planning
ORDPOM
Marketing
Acq Plans
APB
RFPProposal
ContractCSCS
Program Reviews
MAJCOM POM Input
Proposed ORD
AcquisitionOversightProcess
CARSProgram Reviews
Capt McNutt PD100897- 41 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Preliminary Conclusions
l Schedule Process Outcomes– Schedule is not seen as a high project priority
– Planned schedules determined by expected budget allocations - not development related requirements.
– Contracting phase incentives enforce schedule and eliminate possible alternative schedules.
– Development phase result - one way program slips.
Capt McNutt PD100897- 42 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE Other Schedule
Related Research
l Areas Researched But Not Presented At This Time– Barriers to shortening schedules– Effects of schedule planning factors on
schedule performance to plan– Causes and impacts of program instability
on program schedules– Program example: Post-acquisition reform
case study
Capt McNutt PD100897- 43 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
Small Group Discussions
l Small Group Discussion 15 Minutes– Planning Phase– Contracting Phase
– Development Phase– Overall Process
l Questions to be DiscussedDo these data and conclusions match your experiences?What are the implications of these data on schedules and cycle time reduction?(If time permits: What can be done in each phase to change the results?)
l Report by Group Leaders 2-3 Min/each– One table from each phase with comments from others– Each table completes a written table report
Capt McNutt PD100897- 44 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT LEAN AIRCRAFT INITIATIVEINITIATIVE
LEAN ENTERPRISE
“The most important way technology could enhance our military capability would be to cut
the acquisition cycle in half.”
Chairman of the Joint Chiefs of Staff - Packard Commission 1986
“Even if one member makes a lot of progress in becoming lean, neither that member nor
the stream as a whole will reap the full benefits if another member falls short”
James Womack and Dan JonesHarvard Business Review March 1994