Bore mission of 4 June. First event Homestead observations only leading wave @ Homestead at 6:45 Z.
Leading Practices for Cross Bore Risk Reduction Leading...Leading Practices for Cross Bore Risk...
Transcript of Leading Practices for Cross Bore Risk Reduction Leading...Leading Practices for Cross Bore Risk...
Leading Practices for Cross Bore Risk Reduction
Gas Distribution Safety Focus
By: Mark Bruce, President, Cross Bore Safety Associationwww.crossboresafety.org
Leading Practices for Cross Bore Risk Reduction
• Requested from industry & regulator because of concerns showing need for a detailed guidance document
• Existing cross bore inspections and construction efforts have, in some cases reported an area cleared of cross bore risks, but cross bores were found subsequently.
• Requires high confidence cross bore reduction efforts.
• Verifiable QAQC’d processes, accurate GPS and GIS are recommended
• Accurate Verifiable Data is REQUIRED!
32 Chapters, 88 pages, 23 Figures, 33 References, 12 Example Notices
• Discuss installations resulting in cross bores• Illustrate the risks • Quantify the expected number of cross bores• Consequences • Benefits of cross bore risk reduction efforts• Development of Leading Practices by CBSA• Elements of Leading Practices• Final Leading Practices Availability November, 2019
Presentation Preview Focus Gas in Sewer Cross Bores
What’s the Cross Bore Problem?
• Trenchless installations do not “see” existing lines creating potential intersections
• Sewer utilities are often unmarked and excluded from most 811 requirements, leading to substantial risk.
• All types of buried utilities are at risk from cross bores.
• Gas - sewer cross bores have been the focus of most cross bore risk reduction.
Cross Bores - Recognized Since 1976 by NTSB
• 2 persons killed
• 4 persons injured
• Punctured 2-inch plastic main.
• Entered house through 6” sewer lateral.
• Bored through bottom of the sewer tile.
Cross Bores – Class 1, Typically Lays Dormant One Utility Intersects One Other Utility
Cross Bores Are At Risk From Drain Cleaning Actions
• Rotating cutting devices used to clear blocked residential and mainline sewers can cut cross bored utilities.
• Explosion, injury and death have resulted from ignited gas released from cross bores
• $30 million per explosion have been reported
Community Outreach - Web, Radio Spots, Letters, Videos, Sandwich Boards, Theatre Spots
• https://www.pse.com/safety/NaturalGasSafety/Pages/Blocked-Sewer.aspx
Online Links to Video:
• http://www.youtube.com/watch?v=jPAR-3YiSEM&feature=youtu.be
Click on Image to Play
HDD Drill Head for fiber optics penetrates gas
Sanitary Sewer Line
Gas Line
Class 2 Cross Bore – Immediate Explosion Risk Two Existing Utilities Intersected by Third Utility
←G
as F
low
s to
Hous
e
Cross Bore Explosion - Class 2 Cross Bore (see prior slide of this Class 2 cross bore)
Before
After
Potential Cross Bore Crossings - Gas In Sewer
Intersections Shown (16):• Sanitary sewers
• Storm sewers
• Yard drains
• Gutter drains
• Cleanouts
• Offset cleanouts
• Branched laterals
- Potential Intersection of Sanitary Sewer and Gas
Estimated Quantity of Cross Bores
• Gas Cross Bores in Sewers ≅ 0.4 per mainline mile• Total Estimated ≅ 300,000, U.S. & CA, open trench reduces risk• Cross bore risk occurs only with trenchless installations
• Approximately >70% of identified gas cross bores are of sewer lateralsbased on many projects, but percentage can be highly variable
• Gas pipelines, U.S. (2019) 2,558,000 miles *
• Transmission, U.S. 301,000 miles *
• Distribution, U.S. 1,307,000 miles *
• Gas Services, U.S. 922,500 miles *
* U.S. Department of Transportation (U.S. only)
• Prevents injuries and damages• Meets regulatory requirements, DIMP• Higher confidence the gas utility is safe,
encouraging continued demand from customers• Cost Effective, verification vs. damages and
related costs • Protects the utility enterprise value from
unplanned incidents and costs not in the rate base
Benefits of Cross Bore Risk Reduction Efforts
New Risk Reduction Inspection Projects –Consider Inspection of High Consequence Cross Bore Potentials First
• Schools
• Hospitals
• Assisted Living Facilities
• Large concentration of occupants
• Difficult to evacuate structures
GPS and GIS Mapping –Allows QA/QC from GIS Data Short Inspection
Bend
• Leading Practices Committee Members
• Greg Scoby – Cross Bore Consultants, LLC
• Annmarie Robertson – PHMSA
• Mark Wallbom, formerly Miller Pipeline / Hydromax USA
• Sub-Committees
• Construction – Mike Kemper, Mears Group - Quanta
• Data Management – Joe Purtell, Cues, Inc.
• Risk Analysis – Mark Wallbom, Hydromax USA
• Stakeholder - Tyler Boyles, Enbridge
• Legacy Installations – Brian Mattson, Digital Control, Inc.
• Legal – Mark Bruce, Hydromax USA
Leading Practices Committee Members
• American Gas Association, AGA
• Association of Equipment Manufacturers, AEM
• Distribution Contractors Association, DCA
• Gas Technology Institute, GTI
• National Underground Contractors Assoc., NUCA
• Midwest Energy Association, MEA
• Northeast Gas Association
• Southern Gas Association, SGA
• Western Energy Institute, WEI
Partial List of Reviewing Organizations Asked to Participate In Cooperation with CBSA
Leading Practices – Background Chapters
1. History of Cross Bores2. Financial and Social Costs3. Current Practice Gaps4. Installation Equipment at Risk of Creating Cross Bores5. Results of Cross Bores and the Timeline6. Responsible Party’s Opportunity to Minimize Cross
Bore Risk and Impacts7. Regulatory Opportunities8. Regulatory Rate Support9. Sources of Cross Bore Information
Leading Practices –Technical Recommendation Chapters
10. Cross Bore Risk Reduction Goals
11. Outline of Risk Reduction Project Tasks12. Legacy Risk Determination
13. New Construction Risk Reduction
14. Data Preservation, Accessibility and Security
15. Data Use Across the Enterprise
16. Quality Control
17. Project Metrics
18. Public Outreach
- Continued -
Leading Practices –Technical Recommendation Chapters, (cont.)
19. Access to Sewer Systems, Public Right of Way and Private Property20. Scoping for Cross Bore Risk Reduction Inspections21. New Construction Inspections22. Robotic Mainline and Launched Lateral CCTV Inspections23. Manual Push CCTV Inspections24. Vacuum Excavation Used for Cross Bore Risk Reduction25. Pull Back Camera Use26. Ground Penetrating Radar Use27. Other Emerging Tools for Future Consideration
- Continued -
Leading Practices –Technical Recommendation Chapters, (cont.)
28. Locating Field Work29. Proximity Determinations30. Clean Out Installation Use31. Occupant Notifications----------------------------------------------------------------------------------------
SummaryReferencesDefinitionsAppendix A: PublicationsAppendix B: Examples for Notices, Door Hangers and Letters
Risk Modeling & Prioritization / Project Flow Chart
Sewer Inspection Challenges
Accessing Sewers from Structures
Cross Bore Intersections – Sanitary and Gas
GIS Based Data Recommended
Proximity Determinations
GPS / GIS Mapping
• Recommended GPS Accuracy - better than
12” equipment• Requires differential correction capability• Differential correction is free in some
states using mobile internet connections• Frequently achieve 4” (10 cm) accuracy
• Use offsets to accommodate multipath from reflected GPS signals
• Urban canyons are difficult to achieve 12” accuracy
Public Awareness & Form Samples (consider multi-language when appropriate)
PSE natural gas work
What you can expect:
Puget Sound Energy will be working in your neighborhood to:
Replace the existing natural gas main to ensure continued safety and reliability of the natural gas system serving your area
Connect a new customer to the natural gas system
Extend the natural gas main in the street to facilitate the connection of a new customer to the natural gas system
Decommission an existing natural gas line that’s no longer being used
Relocate a segment of existing natural gas main to make way for a local public improvement project
Complete maintenance work on existing natural gas equipment
6D�QD�BNLLHSSDC�SN�BNLOKDSHMF�NTQ�VNQJ�R@EDKX�@MC�DEjBHDMSKX��and our crews will do their best to reduce impacts to you and your neighbors.
• Work is expected to begin _____________________________
___________________ and last approximately ______ day(s)/
week(s). Work hours are generally _______________
SGQNTFG�>>>>>>>>>>>>>>>��>>>>>>>>�@ L �SN�>>>>>>>>�O L
q�����2HFMR��BNMDR�@MC�NQ�SQ@EjB�BNMSQNK�k@FFDQR�VHKK�FTHCD�UDGHBKDR�and pedestrians safely through the work zone. We’ll work to maintain access to driveways whenever possible. If access is SDLONQ@QHKX�AKNBJDC��VD�KK�BNNQCHM@SD�VHSG�XNT�@R�MDDCDC �
pse.com
continued
Digital vs. Manual Reporting
Cross Bore Report - GIS Based
Cross Bore Info Online
Stakeholders Addressed
• Stakeholders Interests are Included• Public & Public Outreach• Utility Planning• Utility Project Managers• Installing Contractor
• Inspection Company• Vacuum Excavation• Quality Control• Mapping• Drain Cleaners
• IT and Data Preservation• Regulators, Rates and Requirements
CBSA’s Leading Practices for Cross Bore Risk Reduction
Get the Leading Practices through your participating organization or through the Cross Bore Safety Association
www.crossboresafety.org
Questions