LCLS Photon Systems ETC and Methodology
-
Upload
jacob-carey -
Category
Documents
-
view
21 -
download
2
description
Transcript of LCLS Photon Systems ETC and Methodology
John Arthur
Photon Systems [email protected]
October 9, 2007 1
LCLS Photon Systems ETC and Methodology
• LCLS Photon Systems• Schedule Overview• Milestones• ETC• Risks
John Arthur
LCLS Photon Systems Manager
John Arthur
Photon Systems [email protected]
October 9, 2007 2
Far Experimental Hall – Cavern for 3 experimental hutches
Front End Enclosure – Underground facility for X-ray diagnostics and mirrors
Near Experimental Hall – Sub-basement facility for 3 experimental hutches
X-Ray Transport Tunnel – 200m tunnel to transport X-rays to FEH
Photon Systems Areas
John Arthur
Photon Systems [email protected]
October 9, 2007 3
Photon Systems
WBS 1.05, 2.05 X-ray Transport, Optics, Diagnostics (XTOD)
Group located at LLNL, Donn McMahon, CAM
Transport the x-ray beam, in vacuum, to experimental stations
Condition the x-ray beam, with attenuators and apertures
Analyze the x-ray beam, with sophisticated diagnostics
John Arthur
Photon Systems [email protected]
October 9, 2007 4
Photon Systems
WBS 1.06, 2.06X-ray Endstation Systems (XES)
Stefan Moeller, CAM
Provide basic infrastructure required for experimenters
Build instrument for Atomic Physics experiments
Advanced x-ray detector R&D
John Arthur
Photon Systems [email protected]
October 9, 2007 5
Photon Systems
WBS 1.02.03, 1.06.04Injector laser and XES laser systems
Bill White, CAM
Coordinate laser design and acquisition throughout LCLS
Injector laser work nearly complete
John Arthur
Photon Systems [email protected]
October 9, 2007 6
Photon Systems
WBS 1.05.02, 1.06.02X-ray Area Controls and Data Acquisition
Gunther Haller, CAM
Controls and DAQ hardware, cables, and software for the X-ray experimental area
John Arthur
Photon Systems [email protected]
October 9, 2007 7
Photon Systems
WBS 2.01.01.05, 2.01.01.06X-ray Commissioning ManagementJohn Arthur, CAM
LOE manpower for 2 LCLS Physicists managing X-ray commissioning
WBS 2.06.03X-ray CommissioningHal Tompkins, CAM
LOE manpower for SLAC and LLNL personnel during X-ray commissioning process
John Arthur
Photon Systems [email protected]
October 9, 2007 8
Design process, included in Project P3 scheduleInterface Control Documents specify which group has responsibility for each systemPhysics Requirements Documents are written by the LCLS Physics group specifying subsystem needsEngineering group holds Design Reviews, and writes Engineering Specification Documents to detail how each PRD is to be satisfied
Physicists and Engineers approve component assembly and testing prior to installation
System Design Management
John Arthur
Photon Systems [email protected]
October 9, 2007 10
LCLS Installation and Commissioning Time-Line
SS OO NN DD JJ FF MM AA MM JJ JJ AA SS OO NN DD JJ FF MM AA MM JJ JJ
Linac/BC2 Install
Linac/BC2 Commissioning
LTU/Und/Dump
Install
20072007 20082008
CF Early Occupancy
LTU/Und Commissioning
Flux milestone
AA SS OO NN DD
20092009 20102010PPS
X-ray tunnel/FEH Install
CD-4(7/30/10)
PPS
FEE/NEH Commissionin
g
Tunnel/FEH Commissioning
JJ FF MM AA MM
FEE/NEH Install
FEH X-rays
milestone
John Arthur
Photon Systems [email protected]
October 9, 2007 11
Major Startup Activities
Commission FEE 6/09 - 8/09
FEE flux measurement 7/09
Commission NEH 8/09 - 9/09
Commission tunnel/FEH 11/09 - 2/10
X-rays in FEH 2/10
John Arthur
Photon Systems [email protected]
October 9, 2007 12
Installation costsBased on experience in 2006 Injector installation
Hardware install estimate done top-down and bottom-up
Cable plant install estimated using R.S. MeansFabrication/procurement
Costs based on quotes and experience with similar types of prototypes at SLAC and LLNL
Engineering and CommissioningTimetable for completion well understood
Photon Systems Cost Estimation
John Arthur
Photon Systems [email protected]
October 9, 2007 13
Photon Systems ETC
WBSActuals Thru
June 07Estimate to Complete
Budget at Complete
1.02 Injector System 3,867,088 100,926 3,968,0141.05 X-RAY Transport & Diagnostics 15,157,356 12,612,914 27,770,2701.06 X-RAY End Stations 2,247,103 14,911,831 17,158,935
TEC Total 21,271,548 27,625,671 48,897,2192.01 LCLS Project Mgmt, Planning and Admin 582,459 996,084 1,578,5432.02 Injector System 203,567 489,149 692,7152.05 X-RAY Transport & Diagnostics 943,788 2,573,529 3,517,3172.06 X-RAY End Stations 889,422 9,262,978 10,152,400
OPC Total 2,619,236 13,321,740 15,940,976TPC Total 23,890,784 40,947,411 64,838,194
43% doneCommissioning
still to come
John Arthur
Photon Systems [email protected]
October 9, 2007 14
Risks
Late changes to design requirements
Atomic Physics design not finalized
Radiation Physics requirements not final
<$200k, <4mo impact
Mitigate through formal design process
AMO design will be finalized in 3 months
John Arthur
Photon Systems [email protected]
October 9, 2007 15
Risks 2
Offset mirror system Mirrors are specialized long-lead procurements
Precision mirror controls still in development
<$300k, <6mo impact
Mitigate through generous schedule
John Arthur
Photon Systems [email protected]
October 9, 2007 16
Summary
XTOD is in procurement phase, XES still in design
XTOD and XES have suffered delays due to CR
New plan allows recovery with extended project,
phased completion
Risks to major project milestones are low