LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

26
LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan

Transcript of LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Page 1: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

LCLS-II Cryomodules Production Plans

at Fermilab

Tug Arkan

Page 2: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Introduction

• 2 partners labs are collaborating with SLAC for the LCLS-II project:– Fermilab:

• Assemble 1 prototype 1.3 GHz CW module (May – December 2015)

• Assemble 16 production 1.3GHz CW modules (mid FY16 - mid FY18)

• Assemble 2 3.9GHz CW modules (late FY18)

– JLAB:• Assemble 1 prototype 1.3 GHz CW module

• Assemble 17 production 1.3GHz CW modules

• Total:– 35 Cryomodules (1.3GHz CW)– 2 Cryomodules (3.9GHz CW)

2

Page 3: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

LCLS-II Prototype Module Assembly

• Use existing ILC R&D 1.3GHz cavities:– Process and test bare cavities– Helium vessel welding to the cavity – Test some of dressed cavities in HTS and some in VTS post

helium vessel welding– Cavity String Assembly– Cold Mass Assembly Phase-I – Cold Mass Assembly Phase II, III – Cryomodule test (CMTF)

3

Page 4: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Planned LCLS-II Production Module Workflow

at Fermilab

1. Receive dressed, ready to be tested in vertical test stand (VTS) cavities from the vendors (Beamline under vacuum)

2. Visual Incoming Inspection at IB43. Install, leak check and test the cavities in VTS at IB1 4. Qualified Cavities go to CAF-MP9 cleanroom for cold end coupler

assembly. Non qualified cavities will be HPR'ed and re-tested.5. Some Cavities are then outfitted with tuner and magnetic shielding

outside of the cleanroom at MP9 and then go to HTS at MDB for horizontal test. Other cavities will stay in the cleanroom and ready to be assembled into a cavity string.

6. 8 qualified cavities, Magnet Spool Tube, BPM, Gate Valves, Interconnecting Bellows: Cavity String Assembly at CAF-MP9 Cleanroom

7. Cold Mass Assembly Phase-I at CAF-MP9 8. Cold Mass Assembly Phase II, III and prep for transport to CMTF at

CAF-ICB 9. Cryomodule Test at CMTF10. Prepare and Ship Module to SLAC at CAF-ICB

4

Page 5: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Parts Inventory Management

• Partner labs has agreed on a joint procurement plan to acquire the cryomodule components. Each lab is responsible for the procurement of a certain part required for the modules

• Fundamental power couplers: Receive ready to be room temp conditioning or ready to be assembled onto qualified cavities

• All vacuum parts will be 100% leak checked

• Stainless steel parts and hardware will be checked for permeability (10% sampling)

• Hardware mechanical QC with gauge thread etc. (10% sampling)

• Critical dimensions checks for all the parts and sub-assemblies (CMM, optical, laser tracker etc.)

• Responsible engineer will sign off the incoming parts routing form with conformance and non conformance reports attached.

• Accepted parts go to storage. Rejected Parts require decision for further action.

• Accepted parts will be sent to the production floor as kits. Parts/Hardware will be cleaned (UHV, UHV&particle free, standard) and sorted at the production areas.

5

Page 6: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

6

Parts / Fixture / Hardware Cleanroom Preparation

• Assembly hardware:– Wash/Rinse in the ultrasonic

bath– Blow clean with ionized

nitrogen under the Class 10 hood

– Dry in Class 10 hood– Transport into the Class

1000 ante clean room– Blow clean with ionized

nitrogen while monitoring the particulates count in the Class 100 sluice area

– Transport into the Class 10 assembly

Class 10 Hood

US cleaner

Continuous work

Page 7: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

7

Assembly Workflow @ CAF-MP9

Receive dressed Cavities

Receive peripheral parts

Assemble dressed Cavities to form a

String in WS1

Install String Assembly to Cold Mass in WS2

Transport the Cold Mass to CAF-ICB

Assemble cold end of the coupler to cavities in WS0

Page 8: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

8

Assembly Workflow @ CAF-ICB

Install the String assembly with the cold mass into the Vacuum

vessel WS4

Install the Cold Mass back to the Cold Mass Assembly Fixture in

WS3

Align Cavity String to the Cold Mass Support in WS3

Prepare in WS6 & Ship Completed

Cryomodule to CMTF for testing

Final assembly and QC at WS5

Page 9: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

9

CAF-MP9 Clean Room

• Cavity String Assembly Clean Room

• A ~250 square-meter clean room: – Class 1000 ante clean room area:

• Preparation of the dressed cavities for transportation into the assembly clean room.

– Class 10/100 sluice area• Parts and Fixtures final preparation

to enter the Class 10 assembly area.

– Class 100 area • Parts and Fixtures preparation for

assembly.

– Class 10 assembly clean room area

Class 1000

Class 10

Rail

Class 100

Page 10: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Cleanroom Infrastructure

10

Vacuum / Gas Manifold

Class 1000 cleanroom for the dressed/qualified cavity preparation to enter the cleanroom

Page 11: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

11

Cold Mass Assembly

Spreader bar fixture is used to support, lower and raise the GRHP

String assembly rail is aligned to the center of the spreader bar fixture. We plan to add a second rail in WS2

Page 12: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Cold End Coupler Assembly (WS0)

• Leak check the dressed qualified cavity (received beamline under vacuum)

• Backfill the cavity• Leak check the coupler pair in the processing stand as

delivered from SLAC (or as received from the vendor)• Backfill• Remove a cold end coupler from the stand• Assemble cold end coupler to the cavity using particle free

flange assembly (PFFA) procedures.• Pump down, leak check, RGA• Total duration: 7 days• 2 cleanroom techs, ~0.7 day per 1 cavity/coupler • Goal: 2 cavities/couplers assembly per day, 4~5 days to

complete 8 cavities + 2 days for extra QC

12

Page 13: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

13

String Assembly-I (WS1)

• Gate Valve (GV1) to Cavity Assembly: 1 day– Sub-assembly of the right angle

valve

– Installation to the support post and vacuum hose assembly

– Leak check

– Alignment to the cavity beam line flange

– Particulate free flange assembly (PFFA) procedures

– Assemble the gate valve to the cavity

Align 8 cavities for string assembly: 1 day

Page 14: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

14

String Assembly-II (WS1)

• Cavity to Cavity Assembly with the interconnect bellows:– Assemble vacuum hose to the

cavity. Pump down and Leak check. Backfill

– Align the interconnect bellows to the cavity field probe end beampipe flange

– Assemble with PFFA

– Align the bellows to the cavity coupler end beampipe flange

– Assemble with PFFA

1 day per interconnecting bellows, total = 7 x 1 = 7 days

Page 15: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

String Assembly III (WS1)

• Magnet+BPM+GV2 assembly and leak check (1 day)• Magnet subassembly to the 8 cavity string (1 day)• Pump down, bag the bellows, leak check. Backfill (1 day)

• Total duration: 13 days– 4 techs direct hands-on assembly

– 2 techs cleaning parts/hardware (UHV & Particle free)

– All 6 cleanroom techs fully qualified to do hands-on assembly

15

Page 16: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Cold Mass Assembly at CAF-MP9 (WS2)

16

• Work outside of the clean room before the string was lifted off the rail to the cold mass support: (Phase-I)– Transport the cavity string to the adjacent rail (0.5 day)– 2-phase helium pipes & bellows cut/welding (1 day)– Cavity magnetic shields installation (0.5 day)– Tuner installation (2 days)– Cavity insulation installation (0.5 day)– Temperature sensors instrumentation and RF cables installation (1

day)– Cavity helium vessel lugs needle bearings and housings installation

(1 day)– Various leak checks / pressure tests of the helium circuit (1 day)– Various electrical checks (1 day)– Various RF checks (2 days)– Total duration : ~10 days

Page 17: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

17

Cold Mass Transport

• After the cavity string is picked up off the rail and partially assembled to the cold mass support, the cold mass assembly is transported to the Vacuum Vessel Assembly Area at CAF-ICB (~5km from CAF-MP9).

(1~1.5 days, 4 mechanical techs)

Page 18: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Cold Mass Assembly at CAF-ICB (WS3)

• Assembly Tasks: (Phase-II)– Put the cold mass on the 4 support spreader bar fixture

(0.25 day)– Assemble Magnet (0.5 day)– Align cavity string (laser tracker) (2.5 days)– Complete the interconnect magnetic shielding

assembly (1 day)– Complete the coupler heat shields intercepts assembly

(0.25 day)– Complete cooling straps assembly to the cavities HOM

(0.25 day)– Complete the harnessing of the instrumentation wires &

RF cables (0.5 day)– RF Checks (1 day)– Various electrical checks (0.25 day)– Weld the magnet current leads to the magnet

instrumentation box (0.25 day)– Various leak checks of the helium circuit (1 day)– Total duration : ~8 days

18

Page 19: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Assembly on Big Bertha at CAF-ICB (WS4)

• Assembly tasks: (Phase-II)– Install and weld lower 50K aluminum shields (1 day)– 30 layers of MLI as blankets (1 day)– Trim insulations around main couplers, magnet and cold mass

support posts (1 day)– Electrical checks (0.5 day)– RF checks (1 day)– Slide vacuum vessel onto the cold mass (0.25 day)– Align cold mass to the vacuum vessel (laser tracker) (2 days)– Weld magnet flanges and JT valve (0.5 day)– Various leak checks (1 day)

– Total duration : ~7 days

19

Page 20: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Final Assembly Phase-III (WS5)

– Install warm part of the main power couplers (8 days)– Route & terminate instrumentations wires and RF cables to

the feedthrough flanges (3 days)– Install coupler pumping lines/pumps & leak check (1 day)– Pump down and leak check insulating vacuum (2.5 days)

– Total duration : ~15 days

20

Page 21: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

21

Cryomodule Transport Preparation (WS6)

• Transport completed Cryomodule from CAF-ICB to the CMTF : 1 days

• Shipping preparation to SLAC: 3 days

Page 22: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Module Transportation to SLAC

22

• Shipping fixture and end cans need to be designed and fabricated. (similar to XFEL design). Use the prototype modules for shipping tests

• Ship Modules with cavity string under vacuum; insulating vacuum backfilled with nitrogen slightly above atmospheric pressure; warm end couplers under vacuum

Page 23: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

LCLS-II 1.3 GHz Module Assembly at CAF

WS1: 13 days

WS2:10 days

WS3: 8 days

WS4:7 days

WS5: 15 days

23

WS6: 1~3 days

Total = ~60 days (peak rate)

WS0: 7 days

Page 24: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Module Assembly Weekly Workflow

24

Cleanroom Assembly: Start: Week #1Complete: Week #4

Cold Mass Assembly: Start: Week #5Complete: Week #12

Module #n Module #n+1

Cleanroom Assembly: Start: Week #5Complete: Week#8

Cold Mass Assembly:Start: Week #9Complete Week #16

Module #n+2

Cleanroom Assembly: Start: Week #9Complete: Week #12

Cold Mass Assembly:Start: Week #13Complete Week #20

It takes ~12 (60 days) weeks to assemble a module. Excluding any sick modules that need to be reworked, there will be max 3 modules in the production line at the same time

4 weeks throughput

4 weeks throughput

Page 25: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

CAF Mechanical Tech Workforce for LCLS-II

• Cleanroom Techs (Total of 6 are needed)– Current:

• 3 cleanroom techs, fully trained and experienced

– Goal:• Hire 3 new contract

mechanical techs and train them

• Cold Mass Techs (Total of 8 are needed)– Current:

• 2 cold mas techs, fully trained and experienced

– Goal:• Hire 6 new contract

mechanical techs and train them

25

Page 26: LCLS-II Cryomodules Production Plans at Fermilab Tug Arkan.

Summary

• Cryomodule Assembly Facility (CAF) infrastructure require minor upgrades for LCLS-II modules assembly. We are in the process of making the necessary upgrades.

• Some of the existing fixtures need to be modified. Some new fixtures need to be designed and fabricated.

• CAF core mechanical technician group is small but very well trained and experienced.

• Qualified manpower especially touch labor shortage is a major issue. Current plan is to hire contract mechanical technicians and train them. Training period is ~1 year for a fully qualified cleanroom tech and ~6 months for a cold mass assembly tech.

• Contract tech high turnover rate is a risk

• Support groups (electrical, QC, material handling) are also understaffed

• We are in the process of hiring full time and contract staff to remedy understaffing problem

• We will test the CAF infrastructure feasibility during the prototype module assembly

26