Long Beach Transit
All-Electric Bus Recommendation
Board Meeting
February 25, 2013
![Page 2: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/2.jpg)
LBT Project Goals
1. Assess risk for a viable, effective & reliable all-
electric ZEB to address alternative fuel policy
2. Achieve reliable, safe & environmentally sound
service levels that are equal to or greater than the
current fleet
3. Introduce appealing, iconic all-electric buses that
increase ridership, improve the transit experience,
and enhance the image of Long Beach and LBT
4. Deploy all-electric buses that provide a cost-
effective solution for LBT (life-cycle costing)
5. Support FTA’s TIGGER goals by maximizing
reductions in GHG emissions and energy costs
![Page 3: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/3.jpg)
Project Milestones Task Milestone Date
Project Kickoff 06/05/12
Market Analysis Completed 8/15/12
Issue Bus & A&E RFP 10/01/12
Bus Proposal Submittal Due Date 12/5/12
Bus Proposal – Round 1 evaluation complete 12/20/12
Seek LBT Board Approval 02/25/13
Bus Contract and NTP 03/01/13
Proto-Type Coach Delivery 10/01/13
Charging Station Completion 12/31/13
Deploy Final Buses 02/09/14
Issue Station RFP 4/01/13
Station Proposal Submittal Due Date 5/01/13
Station Proposal Evaluation & Decision 6/01/13
LBT Board Approval 5/27/13
Station Contract and NTP 6/1/13
Complete Installation of Charging Stations 12/31/13
Complete Data Collection & FTA Reporting 03/01/16
![Page 4: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/4.jpg)
Project Scope
Up to (10) 35’ – 45’ all-electric coaches based
on APTA white book & LBT specialized equip
Must meet LBT’s Passport operating profile
Open to en-route and/or depot charging solutions
– Solution – open architecture, should be able to use across
multiple platforms & manufacturers in future;
– Design and installation oversight of equipment;
– Maintenance support for charging equipment
Provide training, diagnostic equip, Capital &
Maintenance plan including 1 year assessment
LBT looking towards this project to evaluate its long-
term viability
![Page 5: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/5.jpg)
Modeling Tools
Route Modeling – CTE collected route data and developed model to
determine energy requirements
– Factors battery size, motor size, vehicle weight,
speed, distance, grade, time, etc.
Rate Modeling – CTE established an energy cost model
– Based on SCE Rates and amount of charging at
given times of day, week, season, etc.
Established a basis to evaluate energy cost
& performance of proposed solutions
![Page 6: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/6.jpg)
Request for Proposal
RFP Issued Oct. 1 – APTA White Book updated with all-electric
propulsion, charging infrastructure specifications,
and LBT coach requirements
Written to increase number of responses – Open to conductive and inductive charging
– Open to en route or depot charging solutions
Rec’d 5 responses on December 5th – BYD - Complete Coach Works
– DesignLine Corp - EBUS, Inc
– Proterra
![Page 7: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/7.jpg)
Evaluation Process
LBT - 3 Evaluation Teams – One lead & up to 4 subject matter experts
– A total of 14 LBT employees read and discussed
proposal providing input on same
CTE provided technical evaluation – Technical overview of each proposal
– Modeled each proposal to assess performance on
LBT’s Passport route
– Calculated annual energy costs for each proposal
based on Rate Model
![Page 8: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/8.jpg)
Evaluation Criteria
Overall Proposal 10%
Experience of firm & Response to Inquiry 20%
Technical Design / Coach Operational
Considerations 15%
Technical Design / Charging Station Operational
Considerations 15%
Passenger & Community Considerations 10%
Maintainability / Product Support 10%
Pricing & Life Cycle Costs 20%
![Page 9: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/9.jpg)
BYD & Proterra – short listed
Questions / Clarifications
Invitation for Presentation – Demonstration of Solution
– Review of responses
Life Cycle Cost Analysis Included – WVU – TCRP C15 model
– Compare with Diesel, CNG & Gas Hybrid
– Considers…
• Capital: Bus, Infrastructure, Major components
• Operating: Fuel (fluid / electricity), Estimated
Scheduled & Unscheduled Maintenance
• 12 year life
![Page 10: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/10.jpg)
BYD Motors Inc.
BYD eBus Proposal • Ten BYD eBus battery electric buses
• Length: 40 ft
• Passengers: 35 seated/23 standees
• Curb Weight: 30,423 lbs
• Batteries: 324 kWh Iron-Phosphate /
includes a 7.5 yr warranty
• Range: up to 118 - 163 miles (calculated)
• Aluminum Body
• US-specified bus to be Altoona tested,
beginning March/April
• Ten BYD manual plug-in 80 kW depot
chargers
• Full Charge: 4 hours
• BYD ISE standard charging adapter
• WAVE Inductive en route option
• Buy America: 70-75%
– Completed Pre-buy America audit
![Page 11: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/11.jpg)
WAVE Inductive Charging
• LBT will use WAVE system as opportunity charging to
extend vehicle range at Queen Mary Stop
• System is currently in development, but shows
significant promise for LBT
![Page 12: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/12.jpg)
Proterra
EcoRide BE35 Proposal • Ten Proterra Eco BE35 battery
electric buses
• Length: 35 ft
• Passengers: 35 seated/25 standees
• Curb Weight: 29,180 lbs
• Batteries: 66 kWh Lithium-Titanate
• Range: up to 30 miles
• Composite body
• Altoona tested – February 2012
• Two Proterra 500 kW automated en
route charging stations
• Full Charge: < 10 minutes
• Proprietary charging interface
• One Proterra 50 kW manual plug-in
maintenance charger
• Full Charge: 1.5 hours
• Buy America: 80%
![Page 13: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/13.jpg)
Company Profiles
BYD Motors Proterra
Ownership BYD Company Ltd (China) Private Equity
Organization • US subsidiary to BYD Company
Ltd., a publicly held Chinese
Company
• US company
Core Businesses • Batteries / Energy
• Electric cars & Buses,
• Solar Panels
• Electric Buses
Employees ~ 200,000 ~160
Founded 1995 2004
Bus Manufacturing • China (Chassis)
• CA (proposed - 2014)
Greenville, SC
Key Suppliers • BYD America (batteries) in LA
• BYD Company Ltd (chassis)
• Altairnano (batteries)
• Eaton (transmission, charger)
Coaches Sold-to-date 1,000 32
Coaches Delivered-to-date 365 14
Max Service Miles 62,500 20,000 (Foothill)
Total In Service Miles (2012) 7.4 million 90,000
![Page 14: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/14.jpg)
Customer Profiles
BYD Company Ltd Proterra, Inc.
Customer Sold Deliv’d Customer Sold Deliv’d Shenzhen Bus Group, China 742 502 StarMetro, Tallahassee, FL 5 3
Hunan Transit, Changsha, China 101 101 City of Seneca, SC 4
Xian Transit, Xian, China 52 42 RTC, Reno, NV 4
KMB Bus, Hong Kong 29 15 RTA, Worcester, MA 3
Torokbalint, Hungary 20 6 Foothill Transit, Pomona, CA 3 3
BarcelonaTransit, Barcelona, Spain 20 6 VIA, San Antonio, TX 3 3
Expresso, Bogada, Columbia 10 8 San Joaquin RTD, Stockton, CA 2 1
Taiwan Xinzhu Transit, Taiwan 10 4
Schiermonnikoog, Friesland, Finland 6 4
Apple, Cupertino, CA 5 2
Shaoguan Transit, Shaoguan, China 5 5
ATM, Milan, Italy 2 2
SMRT, Singapore 2 1
London Transit, London, England 2
Movia, Copenhagen, Denmark 2
Hertz, Los Angeles, CA 1 1
Schiphol Airport, Amsterdam 1 1
Veolia Transport, Helsinki, Finland 1
Indumoto, Chile 1 1
Buquebus, Uruguay 1
Huizhou Dayawan District, China 1 1
TOTALS 924 702 TOTALS 24 10
![Page 15: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/15.jpg)
$10,340,000 $10,950,000
$12,410,000
$14,090,000
$15,810,000
$18,220,000 $17,700,000
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
$18,000,000
$20,000,000
Diesel CNG Gasoline Hybrid BYD BYD (2) Proterra Proterra (2)
Dol
lars
Vehicle Capital Other Capital Unscheduled CostsScheduled Costs Total Fuel Costs Other Variable CostsTotal
Life Cycle Cost Analysis
![Page 16: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/16.jpg)
Ready to Move Forward BYD Best Solution
– Life Cycle Costs lower
– Company experience &
financially healthy
– Battery risk, minimal w/safe
technology & 7 ½ yr warranty
– Maximum flexibility in routing
and optimum time for charging
Opportunity charging – Manual depot chargers &
WAVE inductive
– Much lower cost to deploy
opportunity charging than high
voltage, “fast” charge solutions
Budget
Coaches & Chargers 9,642,616
WAVE Solution 1,886,000
Program Mgmt 650,000
Installation 963,500
Contingency 600,000
Miscellaneous 207,884
Total 13,950,000
![Page 17: LBT Staff Recommendation for Electric Bus Project, 02/25/13](https://reader033.fdocuments.in/reader033/viewer/2022042814/552cb84b4a7959c37c8b47b1/html5/thumbnails/17.jpg)
Questions And Answers