LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 1 LBT672: Arcetri...
-
Upload
alissa-cullis -
Category
Documents
-
view
213 -
download
1
Transcript of LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 1 LBT672: Arcetri...
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 1
LBT672:Arcetri progress report
A. Riccardi, M. Xompero, D. Zanotti, A. Puglisi, C. del Vecchio, P. Ranfagni, P.
Stefanini
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 2
Overview
• Sketch of LBT672 connections• Arcetri activities and people• P45 work progress• Progress of AdSec-related SW
development• Arcetri optical test facility progress• Schedule
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 3
AUXILIARY BATTERY 6U
POWER SUPPLY 9U
HEXAPOD CONTROLELECTRONICS 6U
3U
3U
ETHERNET SWITCH 2U
FIELD I/O 3U
GENERAL SWITCH 3U
HEXAPOD CABLES
HEXAPOD CABLES
FREE
42U
spider-armrack
Tel. p
ow
er
LBT672 with 1st light AO
TCS
AO Supervisor
TCS
BCU of W-unit
LBT672BCUs+PB
Hexapod
RT commConf/diag commPower Lines
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 4Tel. p
ow
er
LBT672 with multiple AO sys
AUXILIARY BATTERY 6U
POWER SUPPLY 9U
HEXAPOD CONTROLELECTRONICS 6U
3U
3U
ETHERNET SWITCH 2U
FIELD I/O 3U
GENERAL SWITCH 3U
HEXAPOD CABLES
HEXAPOD CABLES
FREE
42U
TCS
AO Supervisor
TCS
BCU of W-unit
spider-armrack
LBT672BCUs+PB
Hexapod
BCU of LBTI
BCU of NIRVANA
AO-selector BCUon elev. platform
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 5
LBT672 & Arcetri Activities• AdSec contractual activities (contract#AO104)
– A1) Development and test of proto and final units– A2) Numerical simulations (Shell FEA)– A3) Software development (configuration,
characterization and diagnostic)– A4) Metrology and test equipment (Shell flattening)– A5) Closed-loop test (Arcetri Test Tower)– A6) Mountain integration and test– A7) Commissioning on the telescope
• People:– A. Riccardi (system, SW, test)– M. Xompero, D. Zanotti (SW, test)– A. Puglisi (interface to AO supervisor)– X. Xxxxx (Diagnostic data SW) (15/03/2005)– P. Ranfagni (Test equipment)– C. Del Vecchio (FEA)– P. Stefanini (Mechanical components)
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 6
A1: test of P45 in ArcetriP45 + MMT crate-electronics (till mid May 2004)
Noise test of new capsens (typical 1.7nm rms @ 40m gap)Flattening of P45 shell (14nm rms, 3% extra power)Test of digital damping concept (0.7ms settling @ 68m gap)Flattening with bias magnets (17nm rms)
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 7
A1: test of P45 in ArcetriP45 + LBT crate-electronics (from mid May 2004)
+ Power Backplain
Noise with large spectral features and crosstalk with coil
Large noise due to crosstalk with new switching power supplies
Most of the Microgate (hardware) and Arcetri (software) effort for noise analysis and optimization in order to freeze asap final electronic layout
• reorganization of ground connections• optimization of ADC, DAC and capsens sample-hold timing• optimization of analog filters including anti-aliasing• optimization of current driver response
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 8
A1: test of P45 in Arcetri
Optimized P45+final crate electronics: early Feb 2005
flat noise spectrumtypical noise 1.3nm rms @ 40m gap (old crates: 1.7nm rms)typical noise 3.5nm rms @ 68m gapstep response with 0.55-0.65ms settling time @ 68m gapchopping of ±70m (±7arcsec) @ 128m gap (to be optimized)
Electronics definitively frozen and sent to production
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 9
A3: LBT672 SW development
AO supervisor
RT diagnostics
BCU of W-unit
RT DSPsoftware
RT reconstructorProvided by MG, currentlyunder debugging in Arcetriwith P45+W-BCU:• modal recontructor • modal filtering• actuator command conv.• FF computation wrt caps pos• Ctrl current integration
limits for:• Mode coeffs and coeffs• capsens pos• act cmd• act force• FF force1st implementation: if out of limits skip the actual frame,keep the old data and increase a counter for slow diagnosticsFuture implementation: keep the old value for data out oflimits, use the new data for others
Limits computedby FEA of stress by C. del Vecchio(stress inf. Functions, on progress)
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 10
A3: LBT672 SW development
AO supervisor
AdsecConfiguration SW
(IDL)
AdsecDiagnostic SW
(C,C++)
AdsecCalibration SW
(IDL)
BCU of W-unit
RT DSPsoftware
FF matrix (done and tested)Flattening (need opt for 672)Optical Interaction matrix(to be written)
1sec sampling data:• Temperatures• Voltages• Coil damages10ms sampling data:• capsens positions• actuator currents• RT fault detection
Dow
nlo
ad d
ata
done
Handlin
g a
nd p
ost
pro
cess
tbw
Configuration files (txt,fits) forany configurable parameter:• ref square wave• ctrl filter coeffs• coil efficiency• ff matrix• ecc (about 30 files, actually)
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 11
A4+5: Optical tests
Main target:Test and characterization of the
Optical Closed Loop for the Complete and Final AO System
before 1st light
Adaptive Secondary Tests:•Optical Flattening and calibration•Optical behavior at “mountain” ambient temperature•Dynamical Behavior at “mountain” atmospheric pressureWFS Optical Test:•Optical interaction with LBT672•Optical Closed loop operation
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 12
A4+5: Optical tests
F2
F1
F/15.0
F/1.221
37
13
mm
10
64
.7m
m
911mm
Lab
Winch
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 13
A4+5: Optical tests
Delay in the ref-optics holder(not yet designed)
Ref-optics alreadydelivered. Currentlyunder assembling inArcetri (P. Stefanini)
3cm
2cm
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 14
Solved critical issues• Hardware of new crate electronics (including
Power BP) has been debugged and optimized
• Suitable grounding connections have been determined
• Bias magnets have been implemented and tested
• Digital damping has been successfully tested– AO at large gap (less sensitivity to
contamination)– Chopping (to be optimized, see Xompero talk)
• Optical test tower has been erected and is mechanically and thermally stable
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 15
Work to do for LBT672• Test of multiple crate behavior on P45• Complete the diagnostic software• Optical closed loop of P45+W for software
and hardware validation at system level• Detailed definitions of operative modes
es. chopping mode: who provide sync, how?es. offloading of static aberrations
• Detailed definition of mountain operations:Accessibility to secondary locationTelescope facilities (semi-clean room with electric lines, cooling lines for Adsec test and maintenance)Optical alignment procedureCommissioning: detailed sequence of operations
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 16
Schedule
LBT AO progress report meeting – Firenze, 21-24 Feb 2005 A. Riccardi: LBT672 17
The end