LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019....

36
LATEST SEISMIC ABC APPLICATIONS September 10, 2019 Toorak Zokaie, Ph.D., P.E. Earthquake Engineering Specialist & Dorie Mellon , P.E. Accelerated Bridge Construction California Department of Transportation

Transcript of LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019....

Page 1: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

LATEST SEISMIC ABC APPLICATIONS

September 10, 2019

Toorak Zokaie, Ph.D., P.E.Earthquake Engineering Specialist

&Dorie Mellon, P.E.

Accelerated Bridge ConstructionCalifornia Department of Transportation

Page 2: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

CALTRANS SEISMIC CONNECTIONS RESEARCH & APPLICATION

• PC Column Connections• PC Girder Connections• Applications• ABC System Bridge Tests• NGB2 Research• MTD 20-20 & Design Examples• SDC 2.0

2

Page 3: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

2008

2019

Caltrans PC & ABC Seismic Research Contracts

3

Page 4: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

LAUREL STREET OCROUTE 780, VALLEJO, CA 2018

Column to Cap Connection UNR CA14-2176

Girder Continuity Connection

ISU CA16-2265Precast Column

Precast Wide Flange Girder

Precast Drop Cap

4

Page 5: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

5

Next Generation of Bridge Columns for ABC in High Seismic Zones

M. Tazarv, M. Saiid Saiidi

UHPC Filled Duct Connections

Plunged-No-Coupler (PCN)

UNR CA14-2176

Page 6: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

SEISMIC PERFORMANCE OF PRECAST GIRDER-TO-CAP FOR ABC OF INTEGRAL BENTS

Extended Unstressed Strand Girder Continuity

Connection

J. Vander Werff, R. Peggar, Z.Cheng, S. SritharanISU CA16-2265

6

Page 7: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Independentanalysis of ISUresults helped toverify the findingsand can be used todevelop otherconnections in thefuture.

Independent Analysis

7

Page 8: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

MULTI-SPAN PRECAST ABC PILOT PROJECT LAUREL STREET OC (REPLACE) 2018

Insert location map

Route 780 Vallejo CADesign-Bid-Build

Low Bid Procurement8

Page 9: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

CONNECTION DETAILS ON PLANS

20 #14 bars thread through 4” ID

UHPC filled ducts

Column to Cap

Girder Continuity

Girder Continuity established by 8 overlapping prestressing strands

extending out of the precast girder.

9

Page 10: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

FABRICATION & ERECTION TOLERANCES BUILT INTO THE PLANS

1’ 8” formed hole for 12” shear key

Vertical tolerance in CIP locations

#14 bars (1.88” deformed

diameter) in 4” ID ducts

Location, spacing and orientation of columns

critical

10

Page 11: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

UHPC IMPLEMENTATION

• Proprietary Procurement – Ductal JS1000• 14 ksi @ 4 days• 21 ksi @ 28 days

• Close coordination with FHWA and Lafarge during design and specification development

• Prequalification• Work Plan• Full Scale Mock Ups

• #14 reinforcing bar pull out test• UHPC placement

Page 12: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

ABC GUIDANCE & TOOLS

• Checklists• Design Guidance• Standard Details• Special Provisions• Checklists• Design Examples

UHPC IMPLEMENTATION CHECKLIST

ABC PRECAST BRIDGE ELEMENTS CHECKLIST

Page 13: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

PULL OUT TEST #14 REINFORCING BAR IN UHPC FILLED DUCT

• Yield at 145 kips• Peak load at 215 kips• Rebar achieved ultimate strength• Rebar remained bonded throughout testing• No pullout of bar, UHPC, or corrugated duct• Elongation of bar along debonded length

13

Page 14: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

CAP/COLUMN ASSEMBLY MOCK UP

14

UHPC was placed as directed on the plans

Page 15: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

All spaces filled, uniform distribution

of fibers and accurate rebar location

CUT THROUGH MOCK UP FOR INSPECTION

15

Page 16: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

PREASSEMBLY OF CAP AND COLUMNS AT THE PRECAST YARD

Preassembly required of full size columns proved problematic

CT allowed contractor to use short columns and template compatibility

“Bullet” used to guide rebar

into ducts

16

Page 17: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Column placement template

Construction - Precast Column Placement

Columns pinned at the bottom

17

Page 18: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Construction - Bent Cap Placement

18

Page 19: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Construction - Grouting of Column Pins & Placement of UHPC in Drop Cap

24 cubic feet of UHPC placed in column to cap

connection voids

Non-shrink grout used at base of column

19

Page 20: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Construction - Girder Erection

Extended Strands for Continuity Connections

20

Page 21: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Laurel Street OC – Structure Complete January, 2018

21

Page 22: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

MULTI-SPAN PRECAST ABC PILOT PROJECT ROUTE 46/99 SEPARATION (REPLACE) 2019

Shafter, CA

22

Page 23: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

ROUTE 46/99 SEPARATION, SHAFTER, CA, 2019

Unstressed Strand Loop Girder Continuity ConnectionISU CA16-2265

23

Threaded bars through strand loops

Page 24: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

24

Experimental and Analytical Seismic Studies of Bridge Piers with Innovative Pipe Pin Column-Footing Connections and Precast Cap Beams Mehrsoroush, M. Saiid Saiidi, CA14-2281

Pipe pin at base of columnRoute 46/99 Separation ABC Pilot Project

Page 25: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

25

Experimental and Analytical Seismic Studies of a Two-Span Bridge System with Precast Concrete Elements and

ABC Connections

J. Benjumea, M. Saiid Saiidi, A. ItaniReport No. CCEER 19-02

Page 26: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

26

Page 27: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

(4) Grouted Duct Connection• Previous research: UW-WDOT • Guarantee strength and stability during erection of the girders and deck panels• High early strength, non-shrink grout ( ̅𝑓𝑓𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑡𝑡28𝑑𝑑 = 10.5 𝑘𝑘𝑘𝑘𝑘𝑘)

•Introduction •Bridge System •Tests Results •Conclusions

27

Page 28: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

(5) Girder-to-Cap Beam Connection for Positive Seismic Moment• Previous research: Iowa State U.-Caltrans • Moment resistance provided by the extended strands and dowel bars• 2-stage CIP diaphragm: Stage 1 (concrete 𝑓𝑓𝑓𝑓𝑓 = 4,000 𝑝𝑝𝑘𝑘𝑘𝑘)

Stage 2 (UHPC 𝑓𝑓𝑓𝑓 = 21.5 𝑘𝑘𝑘𝑘𝑘𝑘)• Four strands extended (36% of total strands per girder)

•Introduction •Bridge System •Tests Results •Conclusions

28

Page 29: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

(5) Girder-to-Cap Beam Connection for Positive Seismic Moment• No visible cracks in the girder-to-cap beam either in the interior or the exterior girders.

•Introduction •Bridge System •Tests Results •Conclusions

Exterior girder-to-cap beam connectionInterior girder-to-cap beam connection

29

Page 30: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

BRIDGE 2: Tested October, 2018

30

Page 31: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Cyclic Large-Scale Column Testing

Objectives:• Emulate the structural and seismic behavior of the previously tested cast-in-place model

using precast connections with non-proprietary cementitious composite material filled ducts.

• Compare the structural and seismic behavior of previously tested PNC details that used Ultra-High Performance Concrete filled duct connections

31

Page 32: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Deployed Research Becomes Standardized Design Guidance

32

Page 33: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

THREE EXAMPLES BEING COMBINED AS ATTACHMENTS TO MTD 20-20

Guidance Includes Examples

33

Page 34: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

CT Seismic Policy: No-Splice Zones in Plastic Hinge Regions

34

Page 35: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Splice Requirements for Main Longitudinal Reinforcement

35

Page 36: LATEST SEISMIC ABC APPLICATIONS...• MTD 20-20 & Design Examples • SDC 2.0. 2. 2008. 2019. Caltrans PC & ABC Seismic Research Contracts. 3. LAUREL STREET OC ROUTE 780, VALLEJO,

Precast Girder Connection Design Guidance

36