Last planner, everyday learning, shared understanding & rework
Transcript of Last planner, everyday learning, shared understanding & rework
![Page 1: Last planner, everyday learning, shared understanding & rework](https://reader031.fdocuments.in/reader031/viewer/2022012018/6168698bd394e9041f6f6a06/html5/thumbnails/1.jpg)
Last planner, everyday learning, shared understanding & rework
Alan Mossman The Change Business, UK
Prof Dr Shobha Ramalingam National Institute of Construction Management and Research (NICMAR), Pune, India,
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
Agenda• Findings — our propositions• Introduction• Research question• How we got there• What comes next
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
![Page 2: Last planner, everyday learning, shared understanding & rework](https://reader031.fdocuments.in/reader031/viewer/2022012018/6168698bd394e9041f6f6a06/html5/thumbnails/2.jpg)
PropositionsProposition 1: Less rework will be required when performers can develop a
shared understanding of the Conditions of Satisfaction (criteria) with those (customers) who will assess their work
Proposition 2: Shared understanding is most likely when the criteria are explicit
Proposition 3: Everyday learning will help make tacit information more explicit.
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
Introduction• Common understanding à reduced snagging/punch list [Pasquire 2012]• Shared understanding of a project [Pasquire & Court 2013]
shared understandinginformationprior work
peopleequipment materials
safe external conditionssafe space
directives
resources
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning after Koskela 1992
![Page 3: Last planner, everyday learning, shared understanding & rework](https://reader031.fdocuments.in/reader031/viewer/2022012018/6168698bd394e9041f6f6a06/html5/thumbnails/3.jpg)
Introduction• Common understanding à reduced snagging/punch list [Pasquire 2012]• Shared understanding of a project [Pasquire & Court 2013] • Shared understanding à communication & collaboration [Koskela et al 2016]• Shared understanding underpins flow [Pasquire & Ebbs 2017]• Glenn Ballard’s discussion in the concluding chapter of his PhD [2000]
• Rework 5-10% of project costs (or more)• Everyday learning à everyday improvement, building new habits
• Episodic learning (e.g. middle & end of project lessons learned) doesn’t work
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
Research Question
RQ = how can we reduce rework arising from misunderstanding the Conditions of Satisfaction?
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
the customers’ criteriavalue for customers & next trades in line
![Page 4: Last planner, everyday learning, shared understanding & rework](https://reader031.fdocuments.in/reader031/viewer/2022012018/6168698bd394e9041f6f6a06/html5/thumbnails/4.jpg)
How we got there
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning after Fernando Flores 2013
Promise cycle
Rework: when the production crew misunderstand what’s wanted
Ballard 2000
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
It’s important that the assessors (customers) & production crew have a shared understanding
![Page 5: Last planner, everyday learning, shared understanding & rework](https://reader031.fdocuments.in/reader031/viewer/2022012018/6168698bd394e9041f6f6a06/html5/thumbnails/5.jpg)
Directives related plan failuresI didn’t understand the
real criteria for my deliverable
Incorrect specification of pre-requisites
I didn’t understand what the requestor needed and why she wanted it
I didn’t understand the applicable requirements
Redefinition of criteria occurred during the
planned weekIncorrect specification
of output
Incorrect specification of processes
Incorrect specification of resources
The directives were incorrect
What changes in directives are needed? Who can make the changes?
Why didn’t you understand what the requestor needed?What stopped you understanding the requirements? What would prevent repetition?
Why did criteria change during the week? What could be done to avoid the need for change?What stopped the prod’n crew learning of the change while they worked? after
Ballard 2000 Fig 10.2
Most construction knowledge is Tacit
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
after Nonaka 1994
![Page 6: Last planner, everyday learning, shared understanding & rework](https://reader031.fdocuments.in/reader031/viewer/2022012018/6168698bd394e9041f6f6a06/html5/thumbnails/6.jpg)
What helps people feel safe to share information?
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
psychological safety e.g. Edmondson 1999, 2019
after Chiu et al 2006
8 structured planning conversations in LPS
1. Risk Planhttp://bit.ly/ebbs-risk-pdf
2. Milestone Plan
3. Phase Plan
8. learning& improving
should docan dowill do
doing
sets milestones
agree handovers
Making work ready in the Look Ahead window
promise
monitor completions & reasons for late delivery
did Learn from & act onreasons for late (& early) delivery
foundation for promising
5. D
esig
n of
Op
erat
ions
should dosystematic risk review with teambe aware
produce
planexperimentimprove
learn
promiseplanplanplanplan
© Alan Mossman 2021
what’s done?what isn’t?what needs to change?
http://bit.ly/ebbs-risk-mp4
4. Look Ahead Plan
6. CommitmentPlan
7. Productionmanagement
![Page 7: Last planner, everyday learning, shared understanding & rework](https://reader031.fdocuments.in/reader031/viewer/2022012018/6168698bd394e9041f6f6a06/html5/thumbnails/7.jpg)
What comes next?• Rigorously observe what happens in the field;• Root cause analysis of rework to establish if lack of shared understanding of
the directives created the need for rework; • What makes it easier/more difficult to share understanding of the
Conditions of Satisfaction/criteria in a construction project – in design, in off-site fabrication, in assembly? • How can we make it easier for project stakeholders to share tacit knowledge
online and to recognise the importance of sharing implicit knowledge to mitigate risk? • What makes it easier for workers to stop and correct defective work?
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning
Thank you!Alan Mossman [email protected] +44 7968485627
Prof Dr Shobha Ramalingam [email protected],
Reliable promising, Last Planner® System, Flow, Rework, Everyday learning