LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations...

14
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee New Champlain Bridge Corridor Project Centre Saint-Charles – April 7, 2016 LaSalle Overpass & May Street

Transcript of LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations...

Page 1: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee New Champlain Bridge Corridor Project Centre Saint-Charles – April 7, 2016

LaSalle Overpass & May Street

Page 2: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 2

Objective of the presentation

1. Discuss progress of the proposed LaSalle Overpass development

2. Discuss progress of the proposed May Street reconfiguration

3. Questions and discussion

Page 3: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 3

1 – LaSalle overpass Looking SOUTH

Page 4: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 4

1 – LaSalle overpass Looking NORTH

Page 5: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 5

1 – LaSalle overpass Characteristics

Page 6: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 6

Revitalization of abutment wall artwork Public bench

based on users

Pedestrian & ambient lighting

1 – LaSalle overpass Subjects under discussion

Page 7: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project

Lighting proposal

7

To replace bollards: proposal for lighting columns with other sources of illumination to

add to the ambient lighting on the walls

Ambient lighting

Pedestrian lighting Auto traffic lighting

Page 8: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 8

Piste cyclable

2 – May Street Context

Bike Path

Page 9: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 9

2 – May Street Existing abutment wall

Page 10: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 10

2 – May Street Entrance to pedestrian walkway and bike lane between May and Wellington streets

Page 11: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 11

2 – May Street Exit from pedestrian walkway and bike lane on May Street

Page 12: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project

2 – May Street Development constraints

12

JAC

QU

ES L

AUZO

N S

T.

RU

SHBR

OO

KE S

T.

WEL

LIN

GTO

N S

T.

Page 13: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

New Champlain Bridge Corridor Project 13

Section of street Paving 6.0 m Sidewalk 1.5 m (south) Borough street light (south)

SMALL - Spirea latifolia

LARGE – Amelanchier canadensis

MEDIUM – Physocarpus opulifolius Green strip shrubbery: between Jacques Lauzon & Rushbrooke Sts. • Criteria: spring & summer flowering (see

photos of typical shrubbery samples) Note: Green strip shrubbery drawing is currently being prepared.

2 – May Street Development proposal

CLIMBING – parthenocissus quinquefolia

May St.

Highway

Building

Wel

lingt

on S

t.

Page 14: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee

3 – Questions & Discussion