2Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010
2
Presentation Outline FAA Rationale for Groove Requirements
Previous FAA Pavement Grooving
Standards
Current FAA Pavement Grooving Standards
Groove Measuring Methods
Comparison of Manual versus AutomatedGroove Measurements
Summary Acknowledgements
-
8/9/2019 Larkin-FAA Pavement Grooving
3/24
3Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010
3
FAA Airport Pavement Grooving
Requirements
Paragraph 2-15 of FAA AC 150/5320-12C
states: Cutting or forming grooves inexisting or new pavement is a proven andeffective technique for providing skid-resistance and prevention of hydroplaning
during wet weather. Grooving of all runways,.. serving ..turbojet
aircraft, is considered high priority safety
work and should be accomplished duringinitial construction.
-
8/9/2019 Larkin-FAA Pavement Grooving
4/24
4Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010
4
FAA Airport Pavement Grooving
Requirements, cont.
Paragraph 2-16 of FAA AC 150/5320-12C suggests
considering the following for other runways:- History of aircraft hydroplaning,
- annual rainfall rates and intensity,
- surface abnormalities impeding runoff,
- surface texture such as contaminant,
- crosswind effects,
- dropoffs at the end of the runway safety areas,
etc.
-
8/9/2019 Larkin-FAA Pavement Grooving
5/24
5Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010
5
Previous FAA Groove Standards
-
8/9/2019 Larkin-FAA Pavement Grooving
6/24
6Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010
6
Current FAA Groove Standards
-
8/9/2019 Larkin-FAA Pavement Grooving
7/24
7Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010
7
Field Measuring of Pavement Grooves
In September 2008, representatives from aUS airport contacted the FAA to help
resolve a dispute between the airport and acontractor constructing a runway. Thedispute centered on whether the contractor
saw-cut the grooves in rigid pavementaccording to the AC.
The challenge to the FAA was to determine
an appropriate method of measuring theconstructed grooves for compliance with
the AC.
-
8/9/2019 Larkin-FAA Pavement Grooving
8/24
8Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010
8
Field Measuring of Pavement Grooves
Furnish a grooving profiling procedure ofthe runway.
This procedure would have to determine thenecessary sample size to ensure astatistically significant confidence level.
A 12,000 ft. runway can have approximately95,000 grooves, this procedure had toaccommodate a similar population.
-
8/9/2019 Larkin-FAA Pavement Grooving
9/24
9Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010 9
Groove Measurement Methods Two methods were identified;
a manual method measuring the depth,width, and separation of individual groovesusing a depth gage and calipers and,
a method using a laser displacement sensoraffixed to a passenger vehicle.
both methods were compared to each other
on the same slab and in the same line.
-
8/9/2019 Larkin-FAA Pavement Grooving
10/24
10Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010 10
Manual Groove Measurement
-
8/9/2019 Larkin-FAA Pavement Grooving
11/24
-
8/9/2019 Larkin-FAA Pavement Grooving
12/24
12Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010 12
Manual Depth Gage Measurements
Groove Measurement Worksheet
Distance Depth by Depth byGroove Between Width Gage SELCOM
Number (in.) (in.) (in.) ProFAA
(in.)
01 1.306 0.159 0.1872 0.1638
2 1.321 0.17 0.1806 0.1615
3 1.314 0.186 0.1786 0.1649
4 1.322 0.177 0.1705 0.1706
5 1.322 0.175 0.1472 0.1367
6 1.314 0.185 0.1308 0.1163
7 1.306 0.187 0.1489 0.1468
-
8/9/2019 Larkin-FAA Pavement Grooving
13/24
13Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010 13
Laser Groove Measurement
-
8/9/2019 Larkin-FAA Pavement Grooving
14/24
14Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010 14
Laser Displacement Sensor
Specifications
Manufacturer/Model: LMI Selcom 2207-
200/325 Spot size: 0.04 in (1mm)
Range: 8 in. (200mm)
Resolution: 0.002 in (0.049mm) (12 bits) Primary sample rate: 32 kHz
Storage sample rate: 8 kHz (11 samples/in at
40 mph) New system samples and stores at 64 kHz
-
8/9/2019 Larkin-FAA Pavement Grooving
15/24
15Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010 15
ProGroove Grooving Data
A 13,000 ftrunway has
about
104,000grooves.
-
8/9/2019 Larkin-FAA Pavement Grooving
16/24
16Federal AviationAdministrationFAA Pavement Grooving RequirementsApril 2010 16
Example Groove PlotsExample zoomed plot over about 35 feet.
Close-up zoomed plot of standard grooves.
-
8/9/2019 Larkin-FAA Pavement Grooving
17/24
17Federal AviationAdministrationFAA Pavement Grooving RequirementsApril 2010 17
Comparison of ProGroove and Manual Groove
Calculation at ACY Runway 4ACY Grooves S to N
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
1 14 27 40 53 66 79 92 105 118 131 144 157 170 183
Groove Number
Groove
Depth,
in
Depth Gauge
SELCOM
-
8/9/2019 Larkin-FAA Pavement Grooving
18/24
18Federal AviationAdministrationFAA Pavement Grooving RequirementsApril 2010 18
Current FAA Pavement Grooving
Requirements Instruments for measuring groove width
and depth must have a range of at least 0.5
inches and a resolution of at least 0.005inches. Gage blocks or gages machined to
standard grooves width, depth, and spacing
may be used. Instruments for measuring center-to-center
spacing must have a range of at least 3.0
inches and a resolution of at least 0.02inches.
-
8/9/2019 Larkin-FAA Pavement Grooving
19/24
19Federal AviationAdministrationFAA Pavement Grooving RequirementsApril 2010 19
Current FAA Pavement Grooving
Requirements
The Engineer will measure grooves in five
zones across the pavement width.Measurements will be made at least THREE
times during each days production.Measurements in all zones will be made foreach cutting head on each piece ofgrooving equipment used for each daysproduction.
-
8/9/2019 Larkin-FAA Pavement Grooving
20/24
20Federal AviationAdministrationFAA Pavement Grooving RequirementsApril 2010 20
Current FAA Pavement Grooving
Requirements The five zones are as follows:
Zone 1 Centerline to 5 feet left or right of the centerline. Zone 2 5 feet to 25 feet left of the centerline.
Zone 3 5 feet 25 feet right of the centerline. Zone 4 25 feet to edge of grooving left of the centerline. Zone 5 25 feet to edge of grooving right of the centerline.
Width or depth measurements less than 0.170 inches shall beconsidered less than 3/16 inches.
Width or depth measurements more than 0.330 inches shallbe considered more than 5/16 inches.
Width or depth measurements more than 0.235 inches shallbe considered more than 1/4 inches.
-
8/9/2019 Larkin-FAA Pavement Grooving
21/24
21Federal AviationAdministrationFAA Pavement Grooving RequirementsApril 2010 21
Comparison of Previous and Current
Groove Standards
-
8/9/2019 Larkin-FAA Pavement Grooving
22/24
22Federal AviationAdministrationFAA Pavement Grooving RequirementsApril 2010 22
Current Groove Measurement
Methodology
-
8/9/2019 Larkin-FAA Pavement Grooving
23/24
23Federal AviationAdministrationFAA Pavement Grooving RequirementsApril 2010 23
Summary
The revision to FAA AC 150/5370-10E,Standards for Specifying Construction of
Airports, dated 9/30/2009 clarifies thefollowing grooving requirements:
- combined rigid and flexible in one section,
- established criteria for acceptance testingequipment and the procedure for groove
measurement in the field for acceptance,
- augmented existing PWL acceptancestandards for pavement grooving.
-
8/9/2019 Larkin-FAA Pavement Grooving
24/24
24Federal AviationAdministration
FAA Pavement Grooving RequirementsApril 2010 24
Acknowledgements
Mr. Jeffrey Rapol, AAS-100