Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where...

17
Large-Scale Floodplain Revegetation Matt Blakeley-Smith Greenbelt Land Trust State of the Willamette January 15, 2020

Transcript of Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where...

Page 1: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Large-Scale Floodplain Revegetation

Matt Blakeley-Smith Greenbelt Land Trust

State of the Willamette January 15, 2020

Presenter
Presentation Notes
Define where working
Page 2: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Project Goals

• Increase Floodplain / River Connectivity • Create 400 Acres of Floodplain Habitat Driven by Declining Salmonids

Photo: River Design Group

Presenter
Presentation Notes
Note Partners: OWEB, Meyer, BPA, RDG, USFWS, ODFW, TNC, PGE Willamette River Basin Planning Atlas
Page 3: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Biological Inventories

Reviewers & Funders

Landowner Meetings

Goal Development

Presenter
Presentation Notes
The foundation of the Harkens Lake project was laid-out ten years previously in the Willamette River Basin Planning Atlas. Outreach with landowners took at least three years before we even acquired the easement and probably five years before the first tree was planted. That was made possible by MMT commitment with capacity funding.
Page 4: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Research & Demos

Need for Cross-Discipline Collaboration Trials to adapt Ag techniques to restoration projects

Presenter
Presentation Notes
We need to be open to innovation and creativity. OSU extension, Horticulture, State Parks, and Meyer worked for 2 years to screen herbicides for Riparian forest restoration, yet it has been slow to catch on with practitioners. This is how we, the practitioners, are able to learn from the research folks and put best practices into action.
Page 5: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Plant Materials

• Reference Forest Stands • USDA Field Guide to Riparian Plant

Communities in Northwestern Oregon • BEF Collaborative Grow

Presenter
Presentation Notes
Existing reference stands are far and few between and often missing historical species USDA published Field Guide provides great guidance on what currently exists We have all benefitted from the BEF collaborative grow Challenge with “Frankenstein Plant Communities” Ex. Valley Ponderosa Pine.
Page 6: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Challenges with Scaling-up

Presenter
Presentation Notes
The old ways of doing things on the small scale are not appropriate on large sites.
Page 7: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400
Presenter
Presentation Notes
Large agricultural sites require different techniques and have the potential to make the largest impacts.
Page 8: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Restoration has a Success Problem

Presenter
Presentation Notes
We need the support of private landowners, yet they don’t have confidence that we know what we are doing. Or our values aren’t aligned.
Page 9: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Introducing AAA Restoration Adapting Agricultural Axioms / How would a farmer do it?

Presenter
Presentation Notes
Farmers have perfected their planting strategies decades ago. Yet we haven’t been partnering with them in a meaningful way to help find solutions to problems.
Page 10: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Layout

• 12 – foot Rows

• 6 – foot seeding “The Bio-Barrier”

• 3 – foot spray band

Presenter
Presentation Notes
Note 3:1shrubs to trees 1200 stems Block planting Thinning Wildflower mixes
Page 11: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Sureguard – Preemergent herbicide

• 24(C) Special Local Needs Label • Season-long weed control • Applied in off-season

Presenter
Presentation Notes
OSU Extension A no brainer for a farmer, but seldom do restoration professionals use preemergents Why? Lack of knowledge. Stigma of long lasting chemicals. Consider economics of contractors they have an incentive to work hourly and often project managers are getting advice from contractors.
Page 12: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Selective Herbicides

• Grass specific • Broadleaf specific • ATV is 7x cheaper vs hand spraying

Page 13: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Thinning

Presenter
Presentation Notes
An extra step in PE now is thinning since many plantations are overstocked. See CREP project on right. But what we want ecologically are large individual trees with spreading canopies and a multi-story understory on left.
Page 14: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Drone Monitoring

Page 15: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Canopy Analysis w/ GIS

Page 16: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

Challenges

• Social constraints • Labor / turnover • Herbicide expertise • Disincentives • Sunk cost trap

Presenter
Presentation Notes
Social constraints include population density, infrastructure, size of parcels, cost of land. Note significant investment in hazelnuts on left. Not going to switch to habitat.
Page 17: Large-Scale Floodplain Revegetation · State of the Willamette . January 15, 2020 . Define where working. Project Goals • Increase Floodplain / River Connectivity • Create 400

• Deep Partnerships • Precision Ag

Opportunities